This document is a Question and Answer summary for a lower trail resurfacing solicitation in South Slough, Oregon, addressing clarifications and specifications for multiple project components. The project encompasses resurfacing education platforms with composite materials, rebuilding decks to residential specifications with 12-inch on-center stringers and posts set 3 feet deep and backfilled with rock, removing and replacing a restroom building while managing underground tank and wood removal per Department of Environmental Quality approval, renovating an education shed including roof replacement with 29-gauge classic brown metal roofing and medium brown paint, and constructing a gravel pad for portable restrooms approximately 12-18 inches deep over a 14-foot by 8-foot area with geotextile underlayment. Specific materials include pressure-treated facia boards, composite decking in earth-tone colors selected by the owner, a metal security door to be provided by the owner with matching locks, and complete removal of existing gutters from the shed. Existing deck and structure footprints must be maintained unless adjustments are approved by the owner, and any work areas will be closed to the public during work hours for safety purposes.
The Q&A document does not specify pricing terms, budgets, set-asides, or incumbent vendors. Change orders are available for unforeseen rot or damage discovered during construction that was not designated for replacement in the original scope. Non-slip composite decking is not mandatory, and ADA compliance is not currently required for the project. All decisions regarding material specifications and design adjustments require owner approval, and the restroom removal will be managed by the owner in coordination with regulatory compliance requirements. The document provides technical guidance only and does not contain procurement timeline details, response deadlines, or funding information.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Oregon Standard Terms Conditions v2021~4.pdf | ||
| OregonBuys Vendor Formal Solicitation Response.pdf | ||
| Mustang Sizing Sheets~1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q & A for lower trail solicitation in South Slough
When resurfacing education platforms
• Will change orders be granted for any rotten/ damaged wood that is not being removed and replaced? If there is rot found on any structure that needs to stay, then a change order can be negotiated with owner.
• Are facia boards around perimeter of deck to be replaced with composite material? Facia boards will need to be pressure treated.
• Are there any specs (size, color, brands etc.) of composite wood to be used? Or is it at discretion of the contractor? Brands or size does not matter but color will be chosen by owner. Preferably something that blends in with the woods, browns tans etc.
• Can small trail from education shed to the 3 outlaying decks be closed during work hours for safety of moving materials in and out? Any area or specific trails where work will be done will be closed to the public during work hours. All trails are closed from dusk to dawn.
• Is a non-slip composite material mandatory for the decks? Not mandatory
• Are the decks to be built to commercial specs (12 inch on center stringers) or residential (16 inch on center stringers)? 12 inch on center stringers
• For new and rebuilt decks there is no ADA compliancy that needs to be followed? Not required at this time. Existing decks need to be built in exact same footprint.
When building new decks
• New decks are to be designed/built to resemble existing decks structurally? Yes as much as possible unless due to the siting it needs to be adjusted. All adjustments need to be cleared through owner first.
• Are posts expected to be set in ground to specific depth/footing size? 3 feet deep.
• Are posts to be concreted in or backfilled with rock? Backfilled with rock
When tearing down restroom
• As I understand the park will be handling all dealings with DEQ on removal and backfill of restroom? DEQ has already approved the project and owner will follow up with pictures of fill afterwards as required. Owner will complete all tasks required by DEQ
• As I understand the tank does not need to be removed completely? How far below ground level does tank need to be removed? The tank does not need to be removed at all unless there is any part that is above ground after building is removed. The building needs removed completely
• Does all wood below ground level need to be removed? Is there an acceptable depth below ground level to leave wood? All wood underground needs to be removed. The structure underground that contains the waste is fiberglass.
• Can pit be backfilled with sand and water compacted to withing 18” of ground level then topped off with compacted rock? Yes it can. The top fill will need to be dirt so that vegetation will grow.
When working on education shed
• Will change orders be granted to any roof sheeting/truss damage of rot on the roof of structures? If there is any rot found that has not been designated for replacement, consult with owner and change orders can be negotiated.
• Is there any specific style, gauge, or color of metal rooting to be installed? Metal roofing, 29 gauge, classic brown
• Any specific brand/style/color of paint to be used on shed? No specifics on brand/style. Color will need to be something that blends in with environment.
Medium brown color
• Any certain style/color/thickness/locks/ or security rating for the door that will be replaced? The more secure the better, door needs to be metal. Owner will provide lock so that it matches all lock sets within the reserve.
• Is contractor to replace or reinstall gutters on the shed? Completely remove gutters. no gutters going back on building.
When building rock pad for portable restrooms
1. I am unable to locate any documents on this portion of the project, can you clarify where it states this in the ITB or scope of work? Lay gravel pad where handicapped porta-potties will be placed. Gravel needs to have sloped area for pedestrian entry. Gravel needs to be approximately 12-18 inches deep and cover an approximate area of 14 ft. x 8 ft. area.
2. Is Geotech to be used under rock? yes
3. To what thickness does rock need to be placed? 12 – 18 inches