QA449CIRCUIT SPECIFICATIONS.pdf
PDF 54 KB Posted
- Solicitation number
- HC101321QA449
- Issued by
-
Defense Information Systems Agency
About this file
THIS IS A DIVERSITY REQUIREMENT PAIRED WITH TSR RU11JUN217198 This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation proposals are being requested and a written solicitation will not be issued. This solicitation is issued as a request for quote (RFQ). This solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2005 83. The provisions that apply to this acquisition are identified in the DITCO Basic Agreements and Section M of the attached document. The associated North American Industrial Classification System (NAICS) code for this procurement is 517311 with a small business size standard of 1500. All quoted prices shall be identified in CLIN 0001 and applicable SLINs 0001AA, 0001AB, etc. as applicable for monthly recurring charges and CLIN 0002 and applicable SLINs 0002AA, 0002AB, etc. as applicable for non-recurring charges. CLIN/SLINs shall include item descriptions, quantities and units of measure. The requested service date and acceptance criteria are outlined in the attached inquiry. The product and service code for this telecommunications requirement is DG11. The selected company must comply with the following commercial item terms and conditions, which are incorporated herein by reference and as outlined in existing basic agreements: FAR 52.212 1, Instructions to Offerors - Commercial Items, applies to this acquisition; FAR 52.212 3, Offeror Representations and Certifications - Commercial Items - the selected offeror must submit a completed copy of the listed representations and certifications if there is no existing basic agreement FAR 52.212 4, Contract Terms and Conditions Commercial Items FAR 52.212 5, Contract Terms and Conditions Required to Implement Statutes or Executive Orders Commercial Items, paragraph (a) and the selected clauses in paragraph (b) in the existing basic agreement. Quotes are due 4 Oct 2021 4:00PM (CDT) at DITCO Scott AFB, IL via email to (see below) Point of Contact Donna M Voss, 618-418-6877, donna.m.voss7.civ@mail.mil
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HC101321QA449_v0.zip | ZIP file | |
| Sample Vendor Block Diagram and Maps.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CIRCUIT SPECIFICATIONS:
-TELECOMM PROVIDER MUST PROVIDE TOTAL FIBER MILES AND ROUND TRIP DELAY (RTD) FROM THE
CUSTOMER "A" LOCATION TO THE CUSTOMER "Z" LOCATION
- THIS REQUIREMENT MUST BE ENGINEERED AND PROVISIONED TOTALLY DIVERSE END TO END TO THE GOVERNMENT'S SERVICE DELIVERY POINTS (SDP'S) FROM TSR RU11JUN217198; MEANING THAT THE PHYSICAL PATHS ARE TOTALLY SEPARATE INCLUDING MAN HOLES, CONDUIT, (CENTRAL OFFICE LOCATIONS), AND FIBER BUILDS. ADDITIONALLY, AS A MINIMUM MUST HAVE 50 METERS PHYSICAL
SEPARATION FROM TSR RU11JUN217198
***THE 50 METER SEPARATION IS WAIVED INSIDE BLDG 33 FOR POINT MUGU LOCATION. ***
- THE VENDOR MUST PROVIDE LIGHT LEVEL READINGS (SIGNAL STRENGTH IN DBM) ON THE EXTENSION FROM COMMERCIAL POP TO THE GOVERNMENT SERVICE DELIVERY POINT (SDP) AT THE "A" AND "Z" LOCATION PRIOR TO CIRCUIT TURN OVER TO THE GOVERNMENT ENSURING LEVELS ARE WITHIN SPECS.
LIGHT LEVELS MUST BE ADJUSTED TO -3 TO -9 DBM.
-THE VENDOR MUST TERMINATE 10GB ETHERNET SERVICE AT SERVICE DELIVERY LOCATIONS, IAW
UNIQUE INSTALLATION FACTORS.
- VENDOR MUST CONDUCT WALK-THROUGH SITE SURVEY PRIOR TO INSTALLATION AT BOTH
LOCATIONS.
-THE VENDOR MUST CONTACT DISA GOC IP BACKBONE ENGINEERING AND IMPLEMENTATION GROUP UPON RECEIPT OF A VALID TSO TO ESTABLISH THE COORDINATION AND ACTIVATION PROCESS. PHONE:
(C) 618-418-8627, (D) 418-8627.
- THE VENDOR MUST CONTACT DISA GOC TIER-II ENGINEERING 48 HOURS PRIOR TO BEGINNING THEIR
END-TO-END TESTING. PHONE: (C) 618-418-8627, (D) 418-8627.
- THE PROVIDER MUST CONDUCT A SATISFACTORY 24-HOUR TEST FROM THE DROP SIDE OF THEIR OR LOCAL EXCHANGE CARRIERS FDP INSTALLED IN THEIR EQUIPMENT SUITE AT THE "A" LOCATION TO THEIR OR LOCAL EXCHANGE CARRIERS FDP INSTALLED IN THEIR EQUIPMENT SUITE AT THE "Z"
LOCATION AND MUST INCLUDE THE EXTENSION BETWEEN THE COMMERCIAL DEMARC AND THE
GOVERNMENT'S SDP. VENDOR MUST ENSURE TEST SETS ARE PLACED AT THE DROP SIDE AT THE "A" LOCATION AND AT THE "Z" LOCATION. TESTING MUST BE SATISFACTORY PRIOR TO TURN OVER TO THE GOVERNMENT FOR ACCEPTANCE TESTING. THE VENDOR MUST TEST THE CIRCUIT FOR 24 HOURS IAW
THE FULL ITU-T.Y.1564 BENCH MARKING METHODOLOGY FOR NETWORK INTERCONNECT DEVICES
STANDARD, AND AT THE COMMITTED INFORMATION RATE (CIR) IAW ITU-T-Y.1564.
1. CIRCUIT REQUIRES THE FOLLOWING PARAMETERS:
(A) FIBER TERMINATION: FRAME FORMAT: 10GB ETHERNET (OPTICAL HANDOFF-10GB ETHERNET-LAN- PHY-SINGLE MODE FIBER), 1310NM. "SC" OR "LC" CONNECTORS AS DETERMINED BY SITE SURVEY.
NOTE: WHEN EXTENDED REACH OPTICS ARE USED THAT CHANGE THE TX/RX WAVELENGTH OF THE
OPTIC, THE VENDOR WILL NOTIFY THE GOVERNMENT 30 DAYS PRIOR TO DELIVERY
(B) COMMITTED INFORMATION RATE (CIR): 10GB.
(C) ETHERNET FRAME SIZE WILL BE CONFIGURED TO SUPPORT MAXIMUM TRANSMISSION UNIT (MTU)
OF 9000 OCTETS (BYTES) JUMBO FRAMES.
(D) NO NETWORK INTERFACE UNIT, DEDICATED PATH.
(E) GFE CLOCKING: VENDOR ESFU (OR EQUIVALENT) NOT TO BE ENGINEERED INTO CIRCUIT.
(F) TESTING CRITERIA: VENDOR MUST TEST THE CIRCUIT FOR 24 HOURS IAW THE FULL ITU-T.Y.1564
BENCH MARKING METHODOLOGY FOR NETWORK INTERCONNECT DEVICES STANDARD, AND AT THE
COMMITTED INFORMATION RATE (CIR) IAW ITU-T-Y.1564. NOTE: ETHERNET FRAME SIZE DESIGNATOR
'H' (MTU) IS EQUAL TO 9000 BYTES
(G) LINE MUST REMAIN FULLY OPERATIONAL AND AVAILABLE TO USERS 24 HOURS A DAY, SEVEN DAYS
PER WEEK, MONTHLY PERFORMANCE OF 99.5% AVAILABILITY OR BETTER.
(H) 1 HOUR RESPONSE TIME TO RESPOND TO CUSTOMER UPON RECEIPT OF TROUBLE.
(I) VENDOR REQUIRED TO HAVE CIRCUIT VISIBILITY TO ASSIST IN ANY CIRCUIT OUTAGES.
(J) VENDOR MUST HAVE A 24X7 NETWORK OPERATIONS CENTER.
(K) TELECOM PROVIDER MUST MAINTAIN OPERATIONS, MAINTENANCE AND ADMINISTRATION
MONITORING OF ETHERNET CIRCUIT.
TEST & ACCEPTANCE INSTRUCTIONS:
1. THE COMMERCIAL CIRCUIT WILL BE ACCEPTED ON BEHALF OF THE GOVERNMENT BY THE DISA GOC IP
BACKBONE ENGINEERING AND IMPLEMENTATION GROUP, SCOTT AFB, IL.
2. VENDOR WINNING AWARD IS RESPONSIBLE FOR INSTALLATION AND MAINTENANCE OF THE SERVICE
IAW THE UNIQUE INSTALLATION FACTORS.
3. INSIDE WIRING IS AUTHORIZED IAW THE UNIQUE INSTALLATION FACTORS.
4. VENDOR MUST COORDINATE SITE VISIT WITH POC'S 72 HOURS IN ADVANCE PRIOR TO REQUIRING
ACCESS TO FACILITIES AT BOTH USER LOCATIONS.
5. VENDOR MUST CONTACT DISA GOC TIER-II ENGINEERING 48 HOURS PRIOR TO BEGINNING THEIR
END-TO-END TESTING.
6. ALL EQUIPMENT AND CIRCUIT PROBLEMS WILL BE REPORTED BY PHONE TO THE DISA GOC IP BACKBONE ENGINEERING AND IMPLEMENTATION GROUP, SCOTT AFB, IL. PRIMARY :(C) 618-418-9950, TOLL FREE: 855-868-9950.
MINIMUM TECHNICAL SPECIFICATIONS: SPECIFIC FORMAT TO BE USED IS: LINE RATE: 10.3125
GIGABITS/S, +- 100 PPM LINE CODE: OPTICAL
1. TEST AND ACCEPTANCE: THIS CIRCUIT SHALL PASS A FULLY DOCUMENTED, SATISFACTORY, 72 HOUR
SOAK TEST BY DISA GOC AT SCOTT AFB, IL. PRIMARY: (C) 618-418-8627 (D) 418-8627.
2. ERROR PERFORMANCE: ERROR PERFORMANCE SHALL BE BETTER THAN THE FOLLOWING
PARAMETER THRESHOLDS TO BE ACCEPTABLE: AVAILABILITY SHALL BE GREATER THAN 99.5% OR BETTER. FRAME LOSS SHALL BE EQUAL TO ZERO WHEN TESTING AT 10 GIGABIT HIGHEST FRAME RATE, AND SHALL MEET ITU-T-Y.1564 STANDARDS. JITTER SHALL BE LESS THAN 3 MSEC. DELAY SHALL BE
BETTER THAN 10 MSEC.
3. MEAN TIME TO LOSS OF BIT COUNT INTEGRITY (MTTLBCI) SHALL BE GREATER THAN 24 HOURS.
4. ROUND TRIP DELAY (RTD) FOR THIS DISA TRANSPORT TRUNK WILL BE MEASURED IN MILLISECONDS FROM THE CUSTOMER'S SERVICE DELIVERY POINT (SDP) SITE-A TO THE CUSTOMER'S SERVICE DELIVERY POINT (SDP) SITE-Z. THE RTD SHALL BE LESS THAN OR EQUAL TO EFFECTIVELY SUPPORT THE
GOVERNMENT'S MISSION. THE GOVERNMENT ACCEPTING AUTHORITY WILL CONFIRM THE RTD
DURING THE TURN-UP AND TEST PHASE AND IF IT DOES NOT ALIGN WITH THE CONTRACTORS
PROPOSAL, DISA IE161 WILL NOTIFY DITCO IMMEDIATELY IN WRITING.