This is a Bidders Questions & Answers document for RFP #250000002585 issued by the State of Michigan for an Archaeological Inventory (Heritage) Survey of areas within the Huron-Manistee National Forest (HMNF) for the Michigan Forest Resource Division. The scope of work requires consultants to conduct a complete pre-field Class I archaeological research, including archival and informant data searches, geomorphological analysis, and field surveys across designated probability areas. Consultants must identify previously recorded cultural resources, conduct shovel testing in moderate probability areas using their professional judgment, and excavate high probability areas as designated by the HMNF. The contract includes strict timeline requirements: all field work must be completed by November 15, 2025; draft reports submitted by December 15, 2025; and final reports with revisions submitted by January 15, 2026. The HMNF will provide shapefiles of work areas and access to digitized and hard-copy cultural resource records upon contract award, though records are not currently centralized in a digital database across all five regional offices (Cadillac, Wellston, Baldwin, Mio, and Oscoda).
The document clarifies that the HMNF has not completed a comprehensive pre-field inventory, placing full responsibility on the consultant to conduct Class I research at HMNF offices and the State Historic Preservation Office (SHPO) archives, verify all previously identified sites, and identify methodological requirements including metal detection and soil coring as necessary. The contract timeline cannot be extended regardless of ARPA permit receipt dates, though the state indicated willingness to consider extending the proposal deadline. The consultant is expected to provide professional expertise in designating testing areas for moderate probability zones and conducting geo-archaeological research to identify coastal landforms and other relevant cultural landscape features. An example of the Forest Service cultural resource record form R9-2300-8 (Version 2021-2) will be provided to bidders prior to submission.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HMNF_Heritage_Resource_Site_Update_Monitoring_Form_.rtf | RTF text file | |
| FS_Cultural_Resources_Record_Form_R9_2300_8.docx | DOCX document | |
| RFP 250000002585 Heritage Surveys.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan.gov/MiProcurement
BIDDER QUESTIONS & ANSWERS
RFP# 250000002585
Archaeological Inventory (Heritage) Survey Areas for Michigan Forest Resource Division Bidders who have questions for the above Solicitation must fill the sections below and attach the document in an email to the Solicitation Manager, as described in the Instruction to Bidders.
| Q # |
| Page # |
| Bidder Question |
| Answer (to be completed by the State) |
| 1. |
| 1 |
| Will you consider extending the proposal deadline to Monday, July 7 |
| We could consider extending the proposal deadline, but an extension of the proposal deadline does not result in an extension of the contract time (below). |
CONTRACT TIME
1. All field work shall be completed by November 15, 2025;
1. The draft report(s) shall be submitted to the Forest Service by December 15, 2025. The Forest Service will have 15 calendar days to review the draft;
1. All necessary revisions or additions shall be made, and the required copies of the final reports shall be submitted by January 15, 2026.
| 2. |
| 33 |
| Have the “archival and informant data searches to identify previously recorded or reported cultural resources within the project areas” been completed? Or does the consultant complete the data searches prior to fieldwork |
| The consultant completes the data searches prior to fieldwork |
The Huron-Manistee National Forest (HMNF) has not conducted a complete Pre-field (Class I) for the project areas/Area of potential Effect (APE);
the consultant will be expected to conduct a complete Class I at the HMNF (SO) and Ranger Districts, as well as with SHPO’s archives.
The HMNF is in the process of scanning/digitizing all site and survey records on the Forest, but the consultant will likely have to conduct their pre-field (Class I research) on Forest.
| 3. |
| 33 |
| For Moderate Probability Areas, have the “Specific landforms” been designated for shovel testing? Or will these areas be identified by the consultant and then designated for testing by your office? |
| The consultant will be expected to designate these specific areas in their pre-field work/planning and use judgment in the field |
(the moderate probability areas are designed this way).
| 4. |
| 33 |
| For High Probability Areas, have the “specific designated landforms” been identified for shovel testing? Or will they be identified by the consultant and then designated for testing by your office? |
| These specific areas will be designated by the HMNF, and are expected to be excavated as directed. |
| 5. |
| 34 |
| Are all previously identified sites and/or historic resources that have not been field verified included in the Moderate or High Probability Areas? Have these locations been identified? |
| No, the consultant will be expected to conduct complete Class I research, and verify (re-visit/monitor, complete a HMNF site monitoring form) for all previously recorded sites within the APE |
| 6. |
| 34 |
| Are the locations of “transportation features, dune ridges within wetlands, edges of wetlands and riparian features, forest openings,” “potential historic sites identified from archival and informant sources, aerial photos, Forest Service timber type maps, and other non-field sources” been identified and are they located in Moderate and/or High Probability Areas? |
| No, the consultant will be expected to conduct all Class I research, and geo-arch research as well. |
| 7. |
| 34 |
| Have all areas requiring special methodologies (including metal detection and soil coring) been identified? |
| No. The consultant is expected to complete a formal pre-field data search and adjust methodologies as determined in the field. |
| 8. |
| 35 |
| Have “Nipissing and post-Nipissing shorelines. Ancient beach ridges, barriers, and spits,” and “other coastal landforms,” that will require survey been identified? |
| No, the consultant will be expected to conduct all Class I research, and geo-arch (geomorphological) research as well. |
| 9. |
| N/A |
| How many previously identified sites and historic resources are located within each work area? |
| Unknown, The HMNF has not conducted a complete Pre-field (Class I), but will share all site/survey records |
This is expected of the consultant.
| 10. |
| 33 |
| Can the Contract Time schedule be altered according to the date of receipt of the signed ARPA permit? |
| The Contract Time will not be altered. |
| 11. |
| 35 |
| Can shapefiles of each work area including locations of pertinent cultural and environmental resources be provided? |
| Yes, the shapefiles will be shared with the consultant upon award of this contract. |
| 12. |
| 33 |
| Are the Forest Service cultural resource inventory records digitized and available to contractors on a database? If so, what steps are necessary to get access? |
| No, not all records are digitized. The consultant will have access to any digitized record pertinent to the project area as well as access to any hard-copy record held by the Forest Service upon award of this contract. |
| 13. |
| 33 |
| If Forest Service cultural resources are not available on a database, are they stored in a centralized location or dispersed across regional offices? |
| If the records are not digitized, they are held by the Forest Service at one of the five offices (Cadillac, Wellston, Baldwin, Mio, or Oscoda). |
| 14. |
| 35 |
| Can an example of Forest service cultural resource record form R9-2300-8 be provided ahead of bid submission? |
| Yes |