Q&A Document 1.pdf
PDF 2 KB Posted
- Solicitation number
- 25-2570
- Issued by
- Muskegon County, Michigan
About this file
This document is a Questions & Answers (Q&A) document for the 2025 Resource Recovery Center Underground Improvements project issued by Muskegon County, Michigan. The document contains one question and answer related to insurance requirements for the project, specifically addressing whether an installation floater is necessary for a pipe project. The Q&A entry is dated 04/01/2025 and directs interested parties to refer to page 20 of the insurance requirements section for detailed information about the installation floater.
The Q&A document provides limited information beyond the single insurance-related query. While it confirms the project involves underground improvements at the Muskegon County Resource Recovery Center, no additional details about project scope, budget, timeline, or specific insurance requirements are provided in this document. Potential bidders would need to consult the full bid package, particularly page 20 referenced in the answer, to obtain comprehensive information about the project's insurance expectations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9 BLANK.pdf | ||
| 25-2570 2025 RRC Underground Improvements.pdf | ||
| 25-2570 2025 RRC Underground Improvements Bid Sheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers - 1
Project 25-2570 - 2025 Resource Recovery Center Underground Improvements
Buying Organization Muskegon County
No Question/Answer Question Date
Q1 Question: Insurance Requirement
Is an installation floater necessary for a pipe project?
Answer: The Installation floater was requested in paragraph #8 of the Insurance Requirements. Please see page 20.
04/01/2025