Q and A - Padded Walls.docx
DOCX document 25 KB Posted
- Solicitation number
- BD-24-1401-ECSD1-ECSD1-91244
- Issued by
- Essex County, Massachusetts
About this file
This document is a Question and Answer session related to Bid BD-24-1401-ECSD1-ECSD1-91244 for the Furnish and Install of a Detention Surface Padding System in the state of Massachusetts. The bid is for padded walls in two rooms, one with existing steel walls and the other with FRP paneling. The existing VCT flooring in the rooms will remain, except for the area adjacent to the drains where the flooring will be removed and replaced with a concrete floor. No specific bid forms are required, and only a product specification sheet needs to be submitted. The prevailing wage schedule to be used is the current Davis-Bacon wage for Massachusetts, posted on CommBuys. The working hours are anticipated to be 6 AM to 2 PM, with potential for later hours depending on staffing. The quote/proposal can be submitted via email to sshrestha@essexsheriffma.org.
The contract opportunity does not specify pricing terms, set-asides, incumbents, or funding sources. The scope of work is to furnish and install a Detention Surface Padding System in two rooms with specific wall and flooring conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ECSD Authority for release of information~10.pdf | ||
| ECSD PREA Form~12.pdf | ||
| Scope of Work~3.docx | DOCX document | |
| Prevailing Wage~4.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid BD-24-1401-ECSD1-ECSD1-91244 Question and Answers
1. Just to confirm there are two (2) rooms that will be padded. One has the steel on the walls and the other has the FRP paneling on it. Both will stay on under the padding A. Yes those are the two rooms we would like Padded, the FRP one and the Steel. As long as their product can be successfully applied over the existing material then yes that is fine.
1. The VCT floor will be staying on and we will install over that (except in the area adjacent to the drains where we will remove that and install to the concrete floor) A. The VCT is fine to stay, again as long as their product can go over it successfully
1. Please verify the substrate of the walls in both of the rooms A. I’ve been told that behind the walls is expanded metal with 5/8 plywood and sheet rock.
1. Will there be any specific “bid forms” that need to be submitted?
A. Any format is accepted
1. Area there any other product information that needs to be submitted.
A. We would like a spec sheet of the product being used if possible.
1. Can you please verify the wage schedule to be used for this job? (I’m assuming the most current Davis-Bacon) A. Prevailing Wage MA- posted in commbuys
1. What will the working hours need to be?
A. Working hours would be 6am to 2 PM but can go later depending on the staffing situation. ( Also, not sure what would work for the infirmary staff, so that could change.)
1. Can the quote/proposal be submitted via email, or will a hard copy be needed?
A. Please email to sshrestha@essexsheriffma.org