Q and A June 30 #2.pdf

PDF 122 KB Posted

Attached to
Promoting American Leadership, Values, and Economic Prosperity in Artificial Intelligence
Opportunity number
SFOP0008191
Issued by

About this file

Questions and Answers June 30 II

View the file

Other files

File Type Posted
Q and A July 14 #2.pdf PDF
Q and A July 14 #1.pdf PDF
Q and A July 13.pdf PDF
Q and A June 30_.pdf PDF
Q and A June 24.docx DOCX document
Budget Template.xlsx XLSX spreadsheet
Budget Guidelines.pdf PDF
PSIs.pdf PDF
NOFO Final 6 7_clean.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of State Bureau of Economic and Business Affairs

NOFO SFOP0008191

Promoting American Leadership, Values, and Economic Prosperity in Artificial

Intelligence (PALVE PAI)

Q and A #2, June 30, 2021

Question 1: What are the expected roles of institution in planning the meetings/workshops.

Would it be something in consultation with EB/CIP, missions and the country desks?

DOS Response: This cooperative agreement will be carried out in close cooperation with the awarding bureau, EB/CIP. Areas of substantial involvement will be discussed with the Recipient and outlined in the Award Agreement.

Per the NOFO, A6, Substantive Involvement: “This potential award will be a cooperative agreement requiring substantial involvement on the part of the Department of State (DOS), awarding bureau, EB/CIP, including, but not limited to, close collaboration and approval of each phase of the project before moving to the next, to include participant/beneficiary selection”.

Question 2: Would the budgeted amount be transferred to the recipient institution? If that is the case, then does it imply that all meeting/workshop related expenses (such as travel of participants, venue, per diem expenses, etc.) will be managed by the recipient institution (in consultation with EB/CIP)?

DOS Response: Correct. Recipient will be required to enroll in the USG-administered Payment

Management System. This requirement is described in section F1: Federal Award Notices.

Question 3: Expected start date: September 2021?

DOS Response: Performance is expected to begin before the end of the 2021 fiscal year, please see the NOFO.

Question 4: Under Criteria E1: Could you provide any specifics?

DOS Response: Please refer to the specifics outlined in paragraph E1. No additional specifics can be provided. Good luck.