PWS WastewaterGrease Removal112525.pdf

PDF 302 KB Posted

Attached to
Wastewater&GreaseRemovalJBMDL
Solicitation number
Not on record
Issued by

About this file

Performance Work Statement Summary: Wastewater & Grease Removal at Joint Base McGuire-Dix-Lakehurst

This is a Performance Work Statement (PWS) dated November 25, 2025, for wastewater and grease removal services at Joint Base McGuire-Dix-Lakehurst (JB MDL) in New Jersey. The contractor shall provide comprehensive management, labor, equipment, tools, supplies, and materials for emptying, cleaning, inspecting, and transporting wastewater from approximately 87 septic tanks and permanent latrine holding pits, plus 33 grease traps located across three installation areas (Dix, McGuire, and Lakehurst). Wastewater must be transported to the Joint Base Wastewater Treatment Plant (WWTP) at Building 4352 or to contractor-selected off-site disposal locations. Grease trap contents must be disposed of at New Jersey State-approved off-base facilities. The contractor shall also provide cleaning of permanent latrine buildings within 24 hours of notification and shall provide 1,000-gallon and 10,000-gallon contractor-supplied holding tanks on a weekly rental basis as requested. The contractor must respond to emergency service calls within 24 hours to prevent Notices of Violation.

Performance requirements include emptying wastewater at 95% compliance with industry standards, cleaning holding tanks at 95% compliance, inspecting tanks at 100% compliance, transporting wastewater at 95% compliance, cleaning permanent latrine buildings within 24 hours at 95% compliance, providing holding tanks within 24 hours at 90% compliance, and responding to service calls at 95% compliance. The contractor must be a New Jersey State-certified licensed waste hauler, maintain current licensing throughout contract performance, provide all required transportation manifests within seven days of delivery, maintain spill cleanup kits, comply with all environmental regulations, and maintain liability for any spills, leaks, or regulatory violations. Normal operating hours are 7:30 AM to 4:15 PM Monday through Friday; contractor employees must wear company identification badges and uniforms and comply with all base security, anti-terrorism, and safety requirements. The appendices include estimated workload data, security requirements, safety guidance, anti-terrorism awareness information, and emergency response procedures.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

FOR

WASTEWATER & GREASE REMOVAL

AT

JOINT BASE MCGUIRE-DIX-

LAKEHURST (JB MDL, NJ)

Joint Base McGuire-Dix-Lakehurst

25 November 2025

PERFORMANCE WORK STATEMENT FOR THE REMOVAL OF WASTEWATER &

GREASE AT JOINT BASE MCGUIRE-DIX-LAKEHURST

1.0. DESCRIPTION OF SERVICES. The contractor shall provide all management, labor, equipment, tools, supplies, and material necessary for the emptying, cleaning, inspection, transporting, and offloading of wastewater from septic tanks, permanent latrine holding pits, contractor provided holding tanks, grease traps or other areas at Joint Base McGuire-Dix-Lakehurst (JB MDL). The contractor shall empty wastewater from different storage locations and safely transport the contents to the Joint Base Wastewater Treatment Plant (WWTP) or a contractor chosen off-site location for disposal. Grease trap contents shall be disposed of off-site In Accordance With (IAW) industry standards. In addition, the contractor shall perform the cleaning of various permanent latrine buildings when required.

1.1. BASIC SERVICES. The scope of work includes the emptying of the wastewater tanks and pits, the cleaning of various holding tanks, the inspection of tanks, the cleaning of permanent latrine buildings, the transportation of the wastewater, and the safe off-loading into the Wastewater Treatment Plant (WWTP), Building 4352 located on Sunrise Rd. off Texas Ave (Fort Dix). The holding tanks vary in both size and location. A listing of the locations and their capacities can be found in Appendix A of this document. The list in Appendix A is not exhaustive as mission requirements change from time to time, and buildings may be added or deleted. Tank and pit locations include but are not limited to: approximately eighty-seven (87) wastewater holding locations, and thirty-three (33) grease traps. For the purposes of this contract, holding tanks are defined as any septic tank, permanent latrine, grease trap, contractor provided holding tank used for the storage of wastewater or grease.

1.1.1 REMOVAL OF HOLDING TANK CONTENTS. The contractor shall remove wastewater and grease contents with the proper pumping/tank/and transportation equipment in accordance with industry standards. The contractor shall be careful not to spill any contents onto the ground. Any spills shall be immediately cleaned up by the contractor and the incident reported in accordance with paragraph 5.2. of this PWS.

1.1.2. CLEANING OF HOLDING TANKS. The contractor shall clean all holding tanks as required in accordance with industry standards after the emptying of each holding tank. In some instances, the contractor might be required to use high water pressure equipment.

1.1.3. INSPECTIONS OF HOLDING TANKS. The contractor shall visually inspect all holding tanks and all components (piping, fittings, valves, etc.) for cracks, leaks, deterioration, and serviceability. The contractor shall notify the Contracting Officer Representative (COR) immediately of any deficiencies found during the inspection process. In addition, the contractor shall follow up with a written report of the deficiencies within two (2) days of identifying the deficiency.

1.1.4. TRANSPORTATION OF EFFLUENT. The contractor shall transport wastewater to the WWTP, Building 4352. Grease trap waste must be disposed of at a New Jersey (NJ) State approved off-base location, and a list of off-site locations used must be provided to the COR. The contractor shall provide all required transportation manifests to the COR within seven (7) days of delivery. The contractor shall be a New Jersey State certified licensed waste hauler. The contractor shall also maintain their licensing and certification for the entire period of performance of the contract, with copies of any renewals being supplied to the COR within seven business days of receipt.

1.1.5. OFFLOADING OF WASTEWATER. The contractor shall provide the proper tank truck/equipment required for the servicing and transporting of wastewater in accordance with industry standards. The contractor shall be held liable for cleaning up of any spills and/or leaks at no additional cost to the government. In the event of a reportable spill, the contractor is responsible for any violations issued by any regulator including payment of fees, fines, penalties or damaged assessed. See paragraphs 5.0, 5.1,

5.2 of this PWS for complete requirements. All disposals will be documented in accordance with all local, state, and federal laws. The contractor has the option to use the WWTP, or an off-post disposal site at no additional expense to the government. After offloading at the WWTP, the contractor is responsible to rinse down the dump basin and remove any debris. If the WWTP is inoperable, the contractor shall be notified whenever possible in advance by the COR. If waste has been collected when the WWTP is not operational, then the contractor will be required to dispose of waste collected at an appropriate off-base disposal site at no additional expense to the government.

1.1.6 CLEANING PERMANENT LATRINE BUILDINGS. The contractor shall perform cleanings for the permanent latrine buildings listed in Appendix A of this document within 24 hours of notification by the COR. All surfaces of sinks, toilets, urinals, lavatories, plumbing fixtures, dispensers, doors, walls, partitions, stalls, stall doors, entry doors (including handle, kick plates, ventilation grates, metal guards) and other surfaces shall be cleaned. The buildings sinks, fixtures, mirrors, walls, and floors shall be free from soil and other removable matter. A cleaning shall include any sweeping, spraying, power washing, scrubbing, pumping and other work required to effectively provide a facility free of debris and removable matter.

1.2. HOLDING TANKS DECRIPTIONS/REQUIREMENTS.

1.2.1. SEPTIC TANKS. The contractor shall empty, clean, and inspect various septic tanks identified in Appendix A on a scheduled basis as directed by the COR. Access to the septic tanks can be made through the existing access manhole of each septic tank.

1.2.2. PERMANENT LATRINES WITH HOLDING PITS AND SEPTIC TANKS. The contractor shall empty, clean, and inspect various permanent latrines (includes holding pits and septic tanks) as directed by the COR. Sewage shall be pumped from the latrine buildings’ holding pits and septic tanks into a transportable tank. Any sewage or other materials not removable by pumping shall be removed manually from the holding pit and septic tank. Access to each latrine’s holding pit can be made through an existing manhole located adjacent to the building.

1.2.3. CONTRACTOR PROVIDED HOLDING TANKS. The contractor shall provide, empty, and service wastewater tanks on an as needed basis. The contractor shall provide 1,000 gallon and 10,000-gallon tanks (as a weekly rental) when requested by the COR. The contractor shall place all tanks within 24 hours of notification by the COR. The contractor shall provide emptying on an as-needed basis, as directed by the COR. The contractor shall invoice separately for the rental and gallons pumped (i.e. the contractor drops a tank and pumps 1,000 gallons every other day, the contractor would invoice for the total number of gallons pumped and one tank rental for each week it is being used).

1.2.4. GREASE TRAPS, IDENTIFIED IN APPENDIX A. The contractor shall completely remove all liquids and solids from various grease traps. Skimming off the top layer of grease is not acceptable. The grease traps will be cleaned thoroughly to remove grease and scum from the inner walls and baffles. Grease shall not be flushed into the sanitary system. Any grease, sludge, solid debris, or other materials not removable by pumping shall be removed manually from the grease traps. The contractor shall perform grease trap pumping when directed by the COR. An estimated workload schedule has been provided in Appendix A. Upon notification by the COR, the contractor shall unclog grease traps in accordance with industry standards. The contractor shall take all necessary precautions to always prevent any spillage and/or leakage of waste material. The grease shall be disposed of at a NJ State approved off-base disposal site (list should be furnished to the COR). The contractor shall maintain grease disposal manifests and provide an electronic copy to the COR monthly.

1.3. SERVICE CALLS. In the event that a holding tank overflows or become unusable, the contractor shall respond to a service call within 24 hours to prevent a Notice of Violation (NOV). The contractor shall provide a point of contact to the COR at time of award. The contractor must have a point of contact established for 24-hour operations in the case of an emergency. A service call will be a set dollar value and will be charged in addition to the number of gallons pumped (i.e. the contractor comes in for a service call and pumps 3,000 gallons, the contractor would invoice for the 3,000 gallons and one service call). The contractor will at times be required to unclog or cleanout drain lines between the facilities and the grease trap location, and at times may be required to use a high-pressure jet machine to remove any obstructions. Should wastewater accumulate inside or outside of facilities due to a sewage or septic emergency, a service call may be requested for wastewater removal support.

1.4. REPORTS/DOCUMENTATION. The contractor shall prepare and submit legible written reports and documentation for the emptying, cleaning, inspection, transporting and disposal of each holding tank and grease trap. The contractor shall provide the COR with a copy of the pumping ticket for each location and is also required to sign in and provide all required information on the “Septic Sign In” log located at the Wastewater Treatment Plant on Fort Dix when offloading their vehicle. In addition, the reports shall include the disposal locations for each type of wastewater as well as the Joint Base source for environmental reporting requirements (i.e., 200 gallons of grease; Dix; delivered to Dining Facility). Pumping/trip tickets shall be provided if applicable. The reports and/or documentation shall be forwarded to the COR within 7 business days of the completion of service.

2.0. SERVICE SUMMARY (SS).

3.0. GOVERNMENT FURNISHED PROPERTY AND SERVICES. Water for the cleaning process can be acquired at Times Square, Building 9509/9510 on the Dix Ranges. Other water source might be available if specially coordinated by the COR. The contractor shall use backflow water preventer where necessary IAW industry standards. The Wastewater Treatment Plant (WWTP) Building 4352 is available for use. All reasonable quantities of utilities will be available to the contractor without charge. Any

Performance Objectives Performance Work Statement Paragraph

Performance Thresholds

Method of Surveillance

Emptying of Wastewater.

Perform removal IAW industry/environmental standards

1.1.1 1.2.1

95% of the time Review of Quarterly Reports/Periodic Surveillance

Cleaning of Holding Tanks.

Perform cleaning IAW industry/environmental standards

1.1.2 1.2.3

95% of the time Review of Quarterly Reports/Periodic Surveillance

Inspection of Holding Tanks.

Perform inspection IAW industry standards.

1.1.3 100% of the time Review of Quarterly Reports/Periodic Surveillance

Transport of Wastewater.

Perform transport IAW industry standards.

1.1.4

95% of the time Review of Quarterly Reports/Periodic Surveillance

Cleaning of Permanent Latrine Buildings.

Perform cleanings within 24 hours upon notification

1.1.6 95% of the time Review of Quarterly Reports/Periodic Surveillance

Provide Holding Tanks.

Perform delivery and hookup within 24 hours upon notification

1.2.4 90% of the time Review of Quarterly Reports/Periodic Surveillance

Service Calls.

Respond to service requests

1.3 95% of the time Periodic Surveys, Customer Satisfaction

Reports/Documentation.

Provides accurate reports and documentation

1.4 95% of the time Periodic Surveys temporary lines and connections that may be required shall be installed, maintained, and removed by the contractor at his expense and in a manner satisfactory to the COR.

3.1. SECURITY, FIRE AND MEDICAL SERVICES. The government will provide police and fire protection. In the event of a medical emergency, base ambulance service for transporting an injured employee to a local hospital is available. The Government will provide police and fire protection. McGuire Security Forces / Dix DOD Police Force can be reached at phone numbers 609-562-6001/2/3. Lakehurst DOD Police Force can be reached by dialing 732-323-4000. Base Fire Departments shall provide initial response and fire protection services to the contractor. The Base Fire Alarm Control Centers can be reached at phone number 911 from a base phone. If dialing 911 from a cell phone, the location must be fully identified to ensure that the proper responder is notified. The 87th Medical Treatment Facility (MTF) may provide urgent health care to any contractor employees or agents for injuries occurring while on duty.

Urgent health care is defined as medical care authorized to the extent necessary to save life or limb and prevent undue pain and suffering. Contractor employees will be transferred to a civilian medical facility as soon as they are appropriately stabilized. The cost of such treatment will be paid for, in full, within a reasonable period of time (as determined with/by the Base Legal Office’s assistance), by the contractor or the contractor’s employee and will not be borne by the 87th MTF, the United States Air Force or the government. Billing/accounts receivable is processed based on services provided, which is captured on an Air Force Form 552 (Pre-Hospital Evaluation Patient Care Report). Verbiage above is based upon the 87th MTF current practice of account receivable IAW AF 41-120, Medical Resource Operations, and is specific to Joint Base McGuire-Dix-Lakehurst, New Jersey. Should there be any universal language that the Defense Health Agency distributes, it is imperative that verbiage takes priority to the verbiage currently suggested or in use. Lakehurst Specific: Follow-on emergency medical care will be provided to contractor and their employees at Community Medical Center, Toms River. Charges for medical care will be at the contractors or employees’ expense. Emergency Medical Service phone number is 911 from a base phone.

If dialing 911 from a cell phone, the location must be fully identified to ensure that the proper responder is notified.

3.2. PHYSICAL SECURITY. The contractor shall be held fully accountable for any failure to maintain the physical security of all base restricted areas, secured facilities, or sites that they are responsible for providing services within. The contractor shall be responsible for the safekeeping and inventorying of all government-furnished keys and combinations issued for the performance of services within secured areas.

All losses or damages caused by the contractor, or by the contractor’s failure or negligence in maintaining proper security of these areas will be paid for by the contractor. Upon termination or completion of the contract, the contractor shall secure the previously issued keys and return them to the COR within twenty-four (24) hours.

3.3. ANTI-TERRORISM.

References:

• Department of Defense Instruction O-2000.16, Volume 1 DoD Antiterrorism (AT) Standards, Standard 18

• Defense Federal Acquisition Regulation Supplement (DFARS) (Reference (r)) reflects current DoD AT security requirements for defense contractors

• Joint Publication 3-07.2 Antiterrorism Terrorism is defined as: The unlawful use of violence or threat of violence to instill fear and coerce governments or societies. Terrorism is often motivated by religious, political, or other ideological beliefs and committed in the pursuit of goals that are usually political.

Antiterrorism is defined as: Defensive measures used to reduce the vulnerability of individuals and property to terrorist acts, to include rapid containment by local military and civilian forces.

Antiterrorism:

1. As a prelude and during performance of any contract, it is critical that the Contractor be supportive of all Department of Defense (DoD) requirements to protect personnel and their families, installations, facilities, information, and other resources from terrorist acts.

2. All Contractors and Sub-Contractors are responsible for providing their personnel information on the Joint Base McGuire-Dix-Lakehurst (JB MDL) Antiterrorism Program (AT). All contractors and sub-contractors will review the JB MDL AT Awareness Guide for Contractors pamphlet.

During performance of work, personnel security and protection of resources is critical for the installation to maintain a safe and secure work environment. Contractors and contracted personnel must be alert for any suspicious activities while on the installation. If any situation appears to be suspicious, immediate actions must be taken to properly notify the 87th Security Forces Squadron (SFS) Emergency Control Center (ECC) at 609-754-6001.

3. Contractors must ensure that contracted personnel and vehicles are strictly controlled during performance of duty. For instance, contractors shall use reasonable efforts to prevent any personnel or equipment from being placed in harm’s way or in a position that could aid or abet terrorists.

4. It is strongly recommended that all contracted personnel take the computer-based training (CBT) for the DoD-approved Antiterrorism Level I Training at: https://jko.jten.mil/courses/ATlevel1/launch.html.

Contractors are encouraged to contact the JB MDL Antiterrorism Office at 609- 562-5362/2445 for information regarding the installation Antiterrorism Program.

5. Force Protection Condition (FPCON) Impact on Work Levels: If the JB MDL FPCON level is elevated to Charlie, the installation shall evaluate the need for contract services to be discontinued. At FPCON Delta, services are discontinued. Services shall resume when the FPCON level has been lowered.

Administrative Note: In the event of an emergency, dial 9-1-1 from any land line on the installation. The call will be routed to the ECC (609-754-6001) on the Joint Base. If you use a cell phone and dial 9-1-1, you will be routed to the county 9-1-1 dispatch (Burlington County for McGuire and Dix or Ocean County for Lakehurst). Simply inform the dispatcher that you are on JB MDL, they will route your call to the JB MDL ECC.

3.4. RESTRICTED AREA ESCORTS. The government shall provide escort services for contractor employees to provide maintenance services within base restricted areas. The contractor shall coordinate the necessary government escort services with the COR.

4.0. GENERAL INFORMATION.

4.1. HOURS OF OPERATION. The normal hours of operation for the contractor to perform normal maintenance and repair services required under this contract are 7:30 AM to 4:15 PM, Monday through Friday. The contractor may find it necessary to deviate from the normal base hours of operation, to ensure timely completion of work under this PWS at no additional cost to the government.

4.2. FEDERAL HOLIDAYS. The contractor is not required to provide normal service on the following days:

New Year’s Day - 1 January Martin Luther King Day - 3rd Monday in January President’s Day - 3rd Monday in February Memorial Day - last Monday in May Juneteenth - 19 June.

Independence Day - 4 July Labor Day - 1st Monday in September Columbus Day - 2nd Monday in October Veteran’s Day - 11 November Thanksgiving Day - 4th Thursday in November Christmas Day - 25 December

If these holidays fall on Saturday, the preceding Friday will be observed. If these holidays fall on Sunday, the following Monday will be observed. If a holiday falls on a scheduled service day, the contractor will be responsible for rescheduling services for the first day post the holiday observance. The COR must approve in advance, excluding legal holidays, any exceptions to work hours and designated workdays. The contractor shall submit their request to COR no later than two (2) working days in advance of the requested change(s).

4.2.1 BASE CLOSURES. Work scheduled but not accomplished because of base closure due to weather, exercises, or actual alert, will be accomplished as soon as possible after reopening the base. In the cases of severe weather, the contractor will call 609-754-2273 for Joint Base McGuire-Dix and 1- 866-690-5260 or 609-754-7777 Option 6 for the Expeditionary Center.

4.3. CONTRACTOR PERSONNEL. The contractor and their employees shall always comply with all base regulations and shall conduct themselves in a professional manner. Uniforms, badges, and good behavioral conduct will be mandatory. The contractor shall provide a complete and current employee roster to the COR and CO within ten (10) business days of the contract award. The contractor’s employee roster shall identify the primary and alternate site manager or foreman and the Quality Control inspector and their telephone or cell phone numbers. As changes in personnel occur, the contractor shall provide updated copies of their employee roster to the COR and CO with two (2) business days of said change.

4.4. CONTRACTOR EMPLOYEE UNIFORMS AND IDENTIFICATION. All contractor employees shall wear a distinctive company logo on their outer garment at all times. The contractor employee shall be neat and professional in appearance and meet current commercial standards. In addition, the contractor’s employees shall wear a company-issued identification badge with the company’s name, employee’s name and employee’s photo prominently displayed on their outer clothing.

4.5. TOBACCO POLICY. The contractor shall ensure that all contractor employees do not use tobacco products within 50 feet (ft.) of any base facility, around fuel tanks and generators, within any clearly marked “No Smoking” areas or within 50 ft. of any flight line aircraft parking areas.

4.6. SAFETY AND ACCIDENT REPORTING. The contractor shall be responsible for providing services under this contract IAW all base, local, State, and federal occupational safety requirements. The contractor shall ensure that all services are conducted safely at all times. The contractor shall ensure that all contractor employees are issued and properly use all required safety personal protective equipment. The contractor shall use mechanically sound and safe vehicles and equipment in the performance of services under this contract. The contractors shall take necessary corrective actions if the contractor’s employees are conducting operations in an unsafe manner. In the event of an accident, the contractor shall contact the base emergency 911 service (see paragraph 3.2) and the COR immediately. If dialing 911 from a cell phone, the location must be fully identified to ensure that the proper responder is notified. Additionally, the contractor and contractor’s personnel will be knowledgeable of and comply with all other base incident-reporting procedures.

4.7. HIRING GOVERNMENT PERSONNEL. The contractor is restricted from hiring the COR, inspectors, monitors, or any other government employees whose employment could result in conflict of interests in accordance with Joint Ethics Regulation, DOD 5500.7-R.

4.8. SECURITY REQUIREMENTS / VEHICLES AND PASSES. All contractor or contractor employees’ vehicles used for the performance of this contract shall comply with all local, State, and federal regulations. In addition, all vehicles described above must be registered through the Security Forces Squadron and will comply with JB MDL directives. After award of contract, the contractor shall request through the COR, CO and Security Forces to be issued base passes and identification badges for their employees and work vehicles IAW the attached McGuire AFB contractor Security Appendix 4 to Annex C to JB MDL JIDP – Sep 21. Reference Appendix C.

4.9 NON-PERSONAL SERVICES AND/OR INHERENTLY GOVERNMENTAL SERVICES. The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor feels that any actions constitute, or are perceived to constitute personal services, it shall be the contractor’s responsibility to notify the PCO immediately. These services shall not be used to perform work of a policy/decision making or management nature, (e.g., inherently governmental functions).

All decisions relative to programs supported by the contractor shall be the sole responsibility of the Government.

5.0 ENVIRONMENTAL COMPLIANCE. The contractor is required to comply with all applicable base, local, State, and federal environmental laws, and regulations, including Air Force Instructions in effect at the time of performance. The contractor is responsible for ensuring all company vehicles are equipped with spill clean-up kits. The contractor shall be responsible for obtaining and complying with any required operating permits. The contractor shall be responsible and liable for penalties, fines, or environmental damage claims that may be required or assessed by the local, State, or federal governments because of the contractor’s performance, or failure to perform, during this contract. The government will inspect for environmental compliance at its discretion and will notify the COR of any discrepancies found. In addition, contractor may be subject to contractual sanctions for environmental non-compliance including, but not limited to, termination, suspension, and debarment and adverse past performance assessment. Any damages incurred by the contractor’s operation or negligence shall be restored to their original condition by the contractor, at no additional cost to the government.

5.1 DISPOSAL OF WASTE. The contractor is responsible for the proper handling and disposal of solid waste. The contractor shall also be responsible for any enforcement action that may be taken by the State of New Jersey, other State or the federal government related to handling, transportation, and the proper disposal of solid waste materials. If notification, certifications, documentation, manifests, permits or any other written materials are required by law to be obtained, prepared and/or submitted. The contractor shall prepare the same and provide a written copy to the COR. Any action, which violates permit requirements for compliance, must be reported to the COR immediately.

5.2 NOTIFICATION OF ENVIRONMENTAL SPILLS. In the event the contractor spills or releases any unpermitted substance, hazardous substance or hazardous waste into the environment, the contractor shall immediately report the incident to the Fire Department IAW paragraph 3.1, the COR, and the CO. The contractor may be liable for the costs of clean up and remediation of any spills or the release of such substance into the environment. Please refer to the JBMDL Emergency Response Action Plan (RED PLAN), Appendix E for additional instructions.

5.3 MATERIALS. All materials used in the performance of services on the installation shall be in compliance with all industry standards, local, federal, and State laws, and will be used according to manufactures' recommendations. Materials will be used for intended purposes and will be stored and utilized in accordance with industry standards. The contractor will submit Safety Data Sheets on all materials to be used fifteen (15) days prior for approval by the COR.

6.0. APPENDICES.

A. ESTIMATED WORKLOAD DATA

B. SECURITY REQUIREMENTS

C. SAFETY GUIDE FOR CIVILIAN CONTRACTORS

D. ANTI-TERRORISM GUIDE FOR CONTRACTORS (FEB 2022)

E. EMERGENCY RESPONSE ACTION PLAN (RED PLAN)

APPENDIX A - ESTIMATED WORKLOAD DATA

The average estimated workload data is predicated on historical information and does not reflect a commitment or guarantee of firm work due to the dynamic mission of Joint Base McGuire-Dix- Lakehurst. Work located at Dix unless noted otherwise.

Septic Tanks

Facility Number Description Service Frequency 1817 AMXS Vehicles Biannually 1900 Quarters Biannually 2203 Mag 1 Biannually 2270 Welcome Center Monthly 25105 Wrightstown Gate Monthly 3164 POL Biannually 9013 Range HQ Weekly 9068 Range 17 (FBI) Weekly 9605 Boeing Vertol-Range

13C As needed

96166 Showers at COL As needed 9671 ARADCOM (Rt. 70) Annually 9691 Range Firehouse Biannually 9906 Brindle Lake As needed 99404 Range 59E As needed 9978 Range 1 Biannually 9985 ARDC As needed

NJ Road NJ Road Manhole Annually 851 (Lakehurst) Vehicle Maintenance Annually

Permanent Latrines with Holding Pits and Septic Tanks *As needed frequencies- average of 2x/year in spring/fall months* Facility Number Description Service Frequency

606 10th St Laurel Lake As needed 74201 LRC Range As needed 7439 Bennington Training

Area As needed

7463 Biv 24 EPW As needed 8514 DTA 3 As needed 8530 DTA 2 As needed 8571 Biv 2A As needed

85771 Biv 4A As needed 85781 Biv 3A As needed 8591 Biv 5 As needed 8594 Biv 6 As needed 8673 HF 11 As needed 8674 HF 11 As needed

9035 Biv 9 As needed 9033 Biv 8A As needed 9037 Biv 10 As needed 9039 Biv 11 As needed 9047 RGTD 7 As needed 9059 RG 14 Biweekly

90643 RG 15 As needed 90644 RG 15 As needed 90692 RG 16 As needed 90792 RG 18 As needed 90862 RG 19/20 As needed 90952 RG 21 As needed 90992 RG 22 As needed 9141 RG 8 As needed 9147 RG 7 As needed 9161 RG 3A As needed 9162 RG 9 As needed

91652 RG 10 As needed 91691 RG 11 As needed 9185 RG 05 As needed 9311 RG 65 As needed 9316 DTA 5 As needed 9406 RG 63 As needed 9409 RG 61 As needed 9426 RG 59D As needed 9435 BIV 19 As needed 9436 BIV 20 Showers As needed 9444 BIV 21 As needed 9448 BIV 18 Showers As needed

94591 RG 53 As needed 9466 RG 59C As needed

94751 RG 47 As needed 9486 RG 59B As needed 9516 BIV 16 As needed 9539 RG 39A As needed 9630 AFP 4 As needed 9646 BIV 13 As needed

97101 RG 32 As needed 9719 RG 34 As needed 9744 BIV 12C As needed 9757 RG 38 As needed 9767 RG 35 As needed

98011 RG 24 As needed 9830 RG 26 As needed 9836 RG 27C As needed 9842 RG 28 As needed 9848 RG 29 As needed

9866 RG 30B As needed 9888 BIV 11C As needed 9895 BIV 12 As needed

GREASE TRAPS DIX LOCATION

Facility Number Facility Description Capacity in

Gallons Service Frequency

1188 Childcare Facility 1500 Quarterly 3152 Golf Course- Mulligan’s 500 Monthly 5399 Burger King 1250 Monthly 5455 Deployment Flight 250 As needed 5455 Deployment Flight 500 As needed 5501 Dining Facility 250 Quarterly 5502 Dining Facility 250 Annually 5504 Dining Facility 250 As needed 5509 Dining Facility 250 Annually 5517 NCO Academy 250 Quarterly 5555 Dining Facility 4000 Quarterly 5610 Dining Facility 900 Quarterly 5640 Dining Facility 900 Quarterly 5904 Dining Facility 900 Quarterly 5986 Recreation Center 500 Quarterly 6054 Inside Bowling Alley 250 Monthly 6502 Snack Bar 250 As needed

GREASE TRAPS MCGUIRE LOCATION

Service Frequency

1706 Flight Kitchen 100 Quarterly 2007 Pudgy’s 2,100 Monthly 2414 Child Development Center 100 Quarterly 2430 Child Development Center 1,000 Quarterly 2635 Dining Facility 500 Monthly 2705 Community Center 1,000 Monthly 2840 Pizza Hut 900 Quarterly 3452 Exchange Food Court 500 Monthly

GREASE TRAPS LAKEHURST LOCATION

Service Frequency

657 Child Development Center 100 Quarterly 687 Fire Department 700 Quarterly

APPENDIX B

SECURITY REQUIREMENTS

INSTALLATION ENTRY CONTROL PROCEDURES FOR ALL CONTRACTORS

After award of contract, the Contractor shall request through the CO and Security Forces to be issued base passes and identification badges for their employees and work vehicles in accordance with the attached

Contractor Security Appendix – SEP 2023.

SFS Appendix - Contractor Appendix_0

APPENDIX C

87 ABW

JOINT BASE MCGUIRE-DIX-LAKEHURST

SAFETY GUIDE

FOR

CIVILIAN CONTRACTORS

March 2022

Adobe Acrobat Document

APPENDIX D

ANTITERRORISM GUIDE FOR CONTRACTORS (April 2024)

JB MDL AT

Awareness Guide for C

APPENDIX E

EMERGENCY RESPONSE ACTION PLAN (RED PLAN)

AUGUST 2024

Adobe Acrobat Document

File details come from the government source that posted it. Updated .