This document is a Performance Work Statement (PWS) for the calibration and repair of electrical test equipment for the U.S. Army Prime Power School (USAPPS) located at Fort Leonard Wood, Missouri. The PWS details the specific equipment to be calibrated, the calibration standards and timeline, repair services, transportation requirements, reporting obligations, and contractor responsibilities.
The related federal contract opportunity is a sources sought announcement from the U.S. Army Corps of Engineers (USACE) - Humphreys Engineer Center Support Activity (HECSA) for a Firm Fixed Price contract to provide calibration services for electrical equipment for the 249th Engineering Battalion in Virginia, North Carolina, and Hawaii. The sources sought requests information on vendor capabilities to provide the required calibration and repair services, mobile delivery options, shipping, and a rough order of magnitude estimate. Responses are due by 3:00 PM EST on 28 August 2023.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CEPP-S 29 April 2024
MEMORANDUM FOR RECORD
Subject: Performance Work Statement for Prime Power School Electrical Test Equipment Calibration and Repair
1. General Information. The Prime Power School (USAPPS) requires calibration services for electrical test equipment that is not supported by the US Army Test, Measurement, and Diagnostic Equipment (TMDE) Activity. Henceforth, within this document, the terms “TMDE” and “Equipment” are synonymous and interchangeable.
The TMDE items are located at Building 12630, Fort Leonard Wood, MO 65473.
2.1. Background. The USAPPS provides industry standard technical training to Army Soldiers and Navy Seabees, enabling their ability to install, maintain, and operate utility-grade power production and distribution systems in support of unified land operations and humanitarian support missions worldwide. The USAPPS trains active duty and reserve service members in the troubleshooting, construction, installation, operation, and maintenance of low-to-medium voltage power and distribution systems in support of the USAPPS mission. This mission-focused training prepares Soldiers and Sailors to be safe, productive, and efficient technical specialists in a complex and dynamic operating environment.
2.2. Definition: Proper terminology is important to understand our requirement.
Henceforth, “mobile calibration” or “onsite calibration” is defined as the act of the contractor driving from their location to our location, where they perform calibration and repair services onsite at our location. “Mobile pickup and delivery” is defined as the act of the contractor driving from their location to our location, where they retrieve our items requiring calibration and/or repair, then transport our equipment to their location for calibration and/or repair, then transport our completed equipment back its respective location.
3. Scope. The contractor will calibrate the following items:
Part Number
Nomenclature Quantity
TDS40 Megger Total Discharge System 1
PDS60 Megger Partial Discharge System 1
CAL1 Megger Unit Calibrator 1
5250 Hipotronics Thumper 1
DEPARTMENT OF THE ARMY
U.S. Army Prime Power School Building 12630 FLW 28
Fort Leonard Wood, Missouri 65473
CEPP-S
SUBJECT: Performance Work Statement for Prime Power School Electrical Test Equipment Calibration
550503 Megger, Transformer turns-ratio tester (3ɸ)
4100-10 Phenix Technologies, 100kV DC Dielectric test set
640-0.4P Phenix Technologies 40 kV AC High-Pot 1
730-2M Hipotronics AC Dielectric Test Set 1
BITE2 MeggerTest Equipment Battery Impedance
BK130-1 Phenix Technologies AC Dielectric Test Set (W/130kV Tower)
CB-8160 AVO Multi-Amp Universal Circuit Breaker test set
CBT-1201 Vacuum Interrupters Inc., Circuit Breaker Timer
CRT-400 Alber (Vertiv) Battery cell resistance tester
DELTA
AVO Biddle 10kV Insulation Test Set Cat No: 672001
DELTA
Megger Power Factor Test Set(W/High Voltage Unit)
DRLO200-
Megger Digital Low Resistance Ohmmeter
FB759X Megger Ground Testing Kit 1
HC-5 Phenix Technologies Portable High Current test set
INGVAR Megger Test Set 2
MAC-TS4 Electronic Vacuum Int. Test Set 5
MCT1600
B
Megger, Current Transformer Test Set 2
MIT 1025 Megger, 10 kV Insulation Resistance Test set
MIT515 Megger 5kV Insulation Resistance Test Set
MIT525 Megger 5kV Insulation Resistance Test Set
MPRT843
Megger Protective Relay Test Set 4
MTO250 Megger, 50A Transformer Ohmmeter 1
MTO330A Megger Ohmmeter 2
OTS60SX AVO Megger, Semi-Automatic Oil Test Set
SMRT 46 Megger Relay Tester 4
TTR310 Megger, Transformer turns-ratio tester (3ɸ)
TTR330 Megger, Transformer turns-ratio tester (3ɸ)
VIDAR Megger Vacuum Interrupter 3
VLF-34 Megger Test Set, Electrical 890026134- S
TTRU3-
ADV
Megger 3 Phase TTR 1
TTR330A Megger 3 Phase TTR 2
T600 FLIR Camera Infrared 2
190-204 Fluke Oscilloscope 2
435 Fluke Power Quality and Energy Analyzer
3.1. The contractor will also make necessary repairs to equipment as needed.
Repair costs will be charged to the original contract from a separate CLIN specifically meant for repair quotes and costs.
Broken Equipment that needs repair and calibration
Part Number
Nomenclature Issue Description QTY
5250 Hipotronics Thumper 1
550005B Megger, Transformer Turns-Ratio Tester (1ɸ)
Will not set to Unity 1
7BT-60 Hipotronics (Hubbell) Vacuum Bottle Tester
Does not Rise on either 500
/ 3K VPS
7BT-60 Hipotronics (Hubbell) Vacuum Bottle Tester
Volt Meter INOP 1
DRLO200-
Digital Low Resistance Ohmmeter Amp outputs not within range
DRLO200-
Digital Low Resistance Ohmmeter Defalts to Potential Fail 1
HH1150 Hipotronics TDR1150 Digital Time Domain Reflectometer
Measurements erratic / does not locate fault
HH1150 Hipotronics TDR1150 Digital Time Domain Reflectometer
Does not locate fault 1
L1050 AVO Biddle Portable locator Wand 1
L1050 AVO Biddle Signal Reciever (part of
AV20208)
L1050 Portable Locator (Emitter) Direct Connect Jack Broken 1
MCT1600B Megger, Current Transformer Test Set
Does not boot up 1
MPRT8430 Protective Relay Test Set One channel is INOP 1
MPRT8430 Protective Relay Test Set Comm Plug Loose 1
MRCT Relay and CT Tester Turns ratio function does not work
SMRT 46 Relay Tester CT Module inop 1
SMRT 46 Relay Tester Only Ch 1 Operates / Software bad
SMRT 46 Relay Tester CT Channel 1 Open / Software bad
TTR330 Megger, Transformer turns-ratio tester (3ɸ)
Key pad inop 1
TTR330A Transformer, Power Internal and External Communications INOP
3.2. Calibration Standards: All equipment will be calibrated in accordance with the manufacturer’s specifications, using reference standards whose accuracies are traceable to ISO/IEC 17025 and ANSI/NCSLI Z540-1.
3.3. Documentation: A signed certificate of calibration will be provided for each piece of equipment calibrated, showing the nomenclature, manufacturer, model number, equipment serial number, date calibrated, and date of next calibration. Calibration data will also be provided along with the certificate for each calibrated item, detailing all test readings recorded.
3.4. Timeline for Calibration: Upon receipt of equipment, the contractor will have
14 calendar days to inspect, inventory, calibrate, and then return equipment to its original owner in their respective geographic location. The 14 calendar day window begins when the contractor signs to for the equipment. The window closes on the date the contractor signs over the calibrated equipment to the original owner.
3.5 Transportation: Initial delivery or shipping to and from respective service centers, and return arrangements for each item having service performed, shall be the responsibility of the Contractor. Approved IP for each item to be serviced shall include total shipping and transportation costs to be incurred (as individual items or as a bulk arrangement). Modification of costs to be incurred due to unscheduled repair / replacement requirements shall be documented and presented to the designated POC for approval before the Contractor will proceed further. The government shall not be liable for any cost beyond that approved by the designated POC.
Points of Contact:
Mr. Jay D. Kaufman US Army Prime Power School
12630 FLW 28
Fort Leonard Wood, MO. 65473
TEL: 573-596-0467
FAX: 573-596-0875
EMAIL: jay.d.kaufman.civ@army.mil
Brian Parker US Army Prime Power School
12630 FLW 28
Fort Leonard Wood, MO. 65473
TEL: 573-596-0526
FAX: 573-596-0875
EMAIL: brian.e.parker.civ@army.mil
3.5. No later than 1700 hours CST every Thursday, the contractor provides a status report for all USAPPS equipment in the contractor’s possession. This status report will include, per serialized item: date of receipt, current calibration status, expected return date, and pertinent issues. Exact status report format will be discussed during the post-award kick off meeting described in Section 6.2.
3.6. Out of Scope Repairs. If the equipment sent for calibration needs repair beyond calibration standards outlined by the manufacturer and this contract, a cost estimate for the repair will be provided to the USAPPS POC as listed above. This cost estimate will include at a minimum: the individual deficiencies, itemized quote for repair costs, and estimated time needed to conduct such repairs if requiring more than the 14 calendar days as outlined in Section 3.4. The contractor may not begin such repairs until given written permission by the POC. The POC will determine, on a case by case basis, whether or not to fund the repair. If the POC decides against funding the repair, the contractor will ship the equipment back to its appropriate location. If the POC decides to fund the repair, the POC will communicate this to the KO who will amend the contract as needed. Subsequently, additional funds will be issued to the contractor in order to execute repair(s), and the contractor will be notified by the POC to begin work.
The government is not responsible for any out of scope repairs conducted by the contractor without prior written approval.
4. Period of Performance. The period of performance for this contract begins on the effective date of award and lasts for one year, not to include potential option years. If the Period of Performance expires while the contractor is still in possession of USAPPS mailto:jay.d.kaufman.civ@army.mil mailto:brian.e.parker.civ@army.mil
TMDE, then the contractor will calibrate the items in their possession and return these items back to the USAPPS, at no additional cost to the Government.
5. Options.
5.1. The government reserves the right to extend the terms of this contract at the prices set forth, in accordance with the terms and conditions contained in clause 52.217-9 entitled “Option to extend the terms of the contact,” for five additional year-long periods.
5.2. The Government reserves the right to add or delete certain TMDE items detailed in Section 3 of this contract. If items are to be added or deleted to the contractual scope, both the contractor and requiring activity will agree to new pricing and terms per item.
6. Contractor Responsibilities.
6.1. The Contractor will furnish all equipment and personnel to meet the specifications of this contract.
6.2. The contractor agrees to attend, telephonically, a post-award kick off meeting convened by the USAPPS to discuss reporting requirements and project documentation. The Contracting Officer, and other government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings, the KO will apprise the contractor of how the government views the contractor's performance, and the contractor will apprise the government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.
6.3. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person, and an alternate, shall be designated in writing. The contract manager, or alternate, shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract.
7. Delivery Schedule.
7.1. The Government will notify the Contractor, in writing, prior to the transfer of equipment to the calibration site, and coordinate a pick-up date. The written notification will outline the return location of the equipment, model number(s), serial number(s), appropriate POC(s), and an itemized report on the condition of the equipment.
7.2 Within three working days of receiving the equipment, the contractor will provide, in writing, any discrepancies to the itemized equipment conditions report. If the contractor receives the equipment in conditions other than described in such report, the contractor must refute the report, citing specific reasons, e.g. a cracked screen not previously annotated by the report.
8. Unit Address.
Prime Power School 10025 Jean Ave Building 12630, FLW 28 Fort Leonard Wood, MO 65473
9. Contractor Manpower Reporting.
9.1. The contractor shall report all contractor and subcontractor labor hours required for performance of services under this contract via a secured data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/Default.aspx
9.2. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30.
While inputs may be reported at any time during the FY, all data shall be reported no later than October 30 of each calendar year. Contractors may direct questions to the help desk at https://www.ecmra.mil/Default.aspx
10. Security Requirements.
10.1. Physical Security. The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for Contractor use IAW AR 190-13, The Army Physical Security Program. At the close of each work period, Government facilities, equipment, and materials shall be secured.
10.2. The Contractor must pre-screen Candidates using the E-verify Program
(http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
https://www.ecmra.mil/Default.aspx https://www.ecmra.mil/Default.aspx
10.3. Security of Classified Items, Systems and Information. The Contractor, as a general rule, shall not have access to classified information; however, should classified documents fall into the possession of the Contractor, the Contractor shall immediately contact the COR for disposition instructions.
11. The point of contact for this memorandum is Mr. Jay Kaufman at (573) 596-0467 or jay.d.kaufman.civ@army.mil.
RUSSELL M. FRATELLO
CW4, EN
Commanding