About this file

This document is a Performance Work Statement (PWS) for a federal contract opportunity to dispose of excess furniture and equipment from the United States Air Force Academy (USAFA) Sijan Hall dormitories.

The PWS outlines the contractor's responsibilities, which include creating an inventory, preparing the excess furniture and equipment for turn-in to the Defense Logistics Agency (DLA), coordinating transportation, and disposing of any non-government assets and trash. Key objectives are to clear storage areas and meet DLA guidelines. The contractor is expected to accomplish all DLA paperwork, coordinate with local installations, and properly handle any hazardous materials. Specific requirements include turn-in procedures, coordination and transportation, cleanup of storage areas, and use of loading areas. Constraints include installation access requirements and restrictions on working during base closures, parades, and special events.

The related federal contract opportunity is a sources sought notice for the Sijan Hall excess furniture and equipment disposal requirement, with a NAICS code of 484210 and a size standard of $34 million in annual revenue. The Air Force Academy anticipates this will be a small business set-aside. Interested parties are requested to submit a capabilities package with details on their company, any teaming arrangements, and relevant past experience.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Furniture and Equipment Disposal Page 1 of 6

UNITED STATES AIR FORCE ACADEMY

SIJAN HALL

Excess Furniture & Equipment Disposal

Version 1.0

Furniture and Equipment Disposal Page 2 of 6

Table of Contents

1. Introduction

2. Background

3. Disposal / Clearing of Storage Areas

4. Objectives

5. Scope

6. Specific Requirements

6.1. Task Description

6.2. Key Deliverables, Milestones and Schedule

7. Constraints

7.1. Installation Access

7.2. Work Interruptions

Furniture and Equipment Disposal Page 3 of 6

1. Introduction The United States Air Force Academy (USAFA) has a requirement to clear all dormitory storage areas of excess furniture and trash. USAFA needs the creation of a complete inventory, preparation of excess furniture for turn-in, coordination and transportation of excess furniture and equipment to through proper Department Logistics Agency (DLA) guidelines. The primary goal of this project is to provide a solution and services necessary for a contractor to transport excess furniture and or equipment to DLA that will result in improvements in efficiency, agility, innovation, and potential cost savings the emptying of crucial space will allow.

This Performance Work Statement PWS issued by USAFA describes the expected results to be achieved with regard to executing the disposal of excess furniture and equipment.

2. Background Between 1992 and 1997, the USAFA Cadet Wing underwent a complete renovation of both dormitories and purchased metal and wood furniture to outfit over 2,800 dorm rooms and 40 Student Activity Rooms to accommodate 4,300+ cadets and 160 offices. The Government estimates approximately 5,000 metal welded bookshelves, 6,000 lounge chairs, 3,000 metal desk with upper desk, 4,500 metal beds with drawers, 40 AOC/AMT wood desk with large-connected tables, hundreds of office chairs, and other items i.e., lamps, bookends, etc. This furniture no longer meets requirements and needs to be removed.

3. Disposal / Clearing of Storage Areas Turn in of Government Property to DLA and dispose of non-real property assets, and removal of all broken items, and trash.

4. Objectives The objective of this PWS is to outline the service the contractor needs to provide by showing a high-level view on what needs to be accomplished. USAFA has outlined contractor objectives that the proposed furniture and trash disposal will achieve.

- Contractor is expected to follow all rules on accomplishing paperwork and adhere to all rules and regulations on disposal of personal Government property.

- Contractor is expected to dispose of miscellaneous items in the storage areas and trash.

- Contractor may be expected to donate items that are able to be donated, if applicable through appropriate DLA guidance.

Furniture and Equipment Disposal Page 4 of 6

5. Scope The scope of this PWS is for primarily dormitory type furniture and equipment located on USAFA. Contractors are expected to dispose of all excess furniture, trash, and equipment that is no longer needed. These items will need to be disposed of through DLA (aka DRMO), the dump, or donated as appropriate.

6. Specific Requirements

6.1. Task Description

Contractor is expected to accomplish all paperwork for DLA material/equipment turn-in, and work with Peterson SFB and Fort Carson Army installations to accomplish all requirements to dispose of Excess Personal Government property.

6.1.1. Task 1 – Turn-in:

• Contractor is expected to accomplish, coordinate, track and provide copies of all paperwork coordinated through or with Peterson AFB DLA office to the program manager at USAFA Cadet Wing Facility. Website, www.dla.mil/disposition-services/, Phone Number 719-600-4633.

• Contractor is expected to follow all rules on accomplishing paperwork and adhere to all rules and regulations on disposal of Government property. The DLA How to Guide at https://www.dla.mil/Disposition-Services/DDSR/Turn-In/.

• Contractor is expected to follow DLA instructions for all property to be turned in, to include all furniture appropriately palletized and banded to meet DLA turn-in requirements.

• Contractor is expected to load items at building 2350 either by loading dock and/or forklift.

• Contractor is expected to off load all turned in assets at Fort Carson DLA disposal yard.

(FT Carson normally has fort lifts and will unload).

6.1.2. Task 2 – Coordination, Transportation and Disposal:

• Contractor is expected to dispose of non-government assets as identified by the facility manager and remove all garbage to an appropriate refuse site off the installation.

• Contractor is expected to work with Peterson SFB to identify items that cannot be turned into DLA for disposal to an appropriate refuse site off the installation.

http://www.dla.mil/disposition-services/ https://www.dla.mil/Disposition-Services/DDSR/Turn-In/

Furniture and Equipment Disposal Page 5 of 6

• Contractor is expected to properly handle any hazardous material and electronics identified and dispose of such in accordance with federal, state and local laws.

• Contractor is expected to dispose of any trash and or garbage in accordance with local laws.

• If the contractor provides roll-off containers, up to 2 containers may be temporarily located at building 2350 and placed in the loading zone of stairwell #10, and identified with bold signs stating, “Contractor use only”. Containers may not be in place for more than 3 days. Prior written coordination to the placement of the containers must be approved within 3 days by the CW Facility Manager.

6.1.3. Task 3 – Cleanup of Cadet Storage/Work Areas:

• Building 2350 1D9, Storage area may be used as a primary storage location, staging area for contractor usage for the cadet dormitory disposal project.

• Contractor will be allowed to pallet/band within the primary storage area and will be allowed to temporarily locate or place pallets outside of the room along the north wall from 1D9 west to the corner of the facility. Pallets will not be stacked more than 2 high and will not take over 50% of the existing sidewalk. (Sidewalk 9’ wide).

• As the contractor clears storge room 1D9 excess furniture from other locations will be relocated to this area for disposal staging until all areas are cleared.

• Contractor is expected to work with CW Facility Managers to identify when additional items are available to be relocated to room 1D9, Facility Managers or their representatives are expected to deliver items within 3-5 duty days.

6.1.4. Task 4 – Loading Area:

• Building 2350 has a loading dock at the east end of facility, approximately 300 yards from 1D9 storage area.

• Roadside loading may be accomplished along Sijan Drive, with a flag person to control traffic. The road will not be shut down for longer than 5 minutes at any time.

• Contractor is expected to meet all Department of Transportation (DOT) standards.

6.2. Key Deliverables, Milestones and Schedule.

• The contractor will complete all DLA paperwork and provide a completed DLA signed copy to the Contracting Office and to the Facility Manager as proof items were turned in.

Furniture and Equipment Disposal Page 6 of 6

• A copy of any refuse disposal drop off, dumpster drop off, rental/disposal agreement will be provided as proof of disposal and provided to the Contracting Office and to the Facility Manager.

• A copy of any HAZMAT/Electrical disposal will be provided to the Contracting Office and to the Facility Manager as proof of disposal.

7. Constraints

7.1. Installation Access

• Contractor is expected to meet all military installation requirements for access on the

USAFA, Peterson SFB and Fort Carson Army installations.

• Access to USAFA will be though the south gate and will require an inspection through

ELVIS inspection point.

• Access to the Cadet areas will be through the Vandenberg Entry Control Point off

Vandenberg Drive. Monday-Friday from 0700 to 1730, (Gate closes at 1800).

• Parking will be allowed for company vehicles and POV’s in normal unreserved parking slots along Sijan drive and all-day parking in the lower Sijan lot. Vehicles will not be parked in loading zones or any area marked for reserved parking and no vehicles will be allowed under Sijan Hall except for forklifts.

• Restroom facilities are available for use within the laundry mat approximately 50 yards away from 1D9.

7.2. Work Interruptions

• Contractors are not allowed to work on the installation during base closures, parades, and special functions. A monthly event calendar will be provided.

1. Introduction
2. Background
3. Disposal / Clearing of Storage Areas
4. Objectives
5. Scope
6. Specific Requirements
6.1. Task Description
6.1.1. Task 1 – Turn-in:
6.1.2. Task 2 – Coordination, Transportation and Disposal:
6.1.3. Task 3 – Cleanup of Cadet Storage/Work Areas:
6.1.4. Task 4 – Loading Area:

6.2. Key Deliverables, Milestones and Schedule.

7. Constraints
7.1. Installation Access
7.2. Work Interruptions

Contractors are not allowed to work on the installation during base closures, parades, and special functions. A monthly event calendar will be provided.

File details come from the government source that posted it. Updated .