International Boundary and Water Commission United States and Mexico United States Section Water Accounting Division

International Boundary and Water Commission United States and Mexico United States Section

Front Cover

Performance Work Statement (PWS) Water Accounting Department Rio Grande City Gaging Station Stairway Improvements Rio Grande City, Texas

Solicitation

August 3, 2020

USIBWC Water Accouting Division

Rio Grande City Gaging Station Stairway Improvements

May 1, 2020 Performance Work Statement

USIBWC Solicitation Page-2 of 24

SECTION 1

PROJECT SPECIFIC INFORMATION

1.1 Project Overview

The United States Section of the International Boundary and Water Commission (USIBWC) requires services to replace the metal stairway at the Rio Grande City gaging station, repair the erosion along the stairway, and install erosion protection. Heavy rainfalls coupled with clearing and grading of the land adjacent to the gaging station has caused local precipitation runoff to drain towards the gaging station and erode the slope, affecting the structural integrity of the metal stairway leading to the gaging station.

1.2 General

This is a non-personnel services contract to provide Rio Grande City Gaging Station Stairway

Improvements. The Government shall not exercise any supervision or control over the Contract service providers performing the services herein. Such Contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.3 Description of Services

The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, utilities, and supervision necessary to perform the work as defined in this Performance Work Statement. The

Contractor shall perform to the standards in this contract.

1.4 Objective

To have a safe and properly functioning stairway at the Rio Grande Gaging Station with erosion protection and drainage devices that will prevent future erosion.

1.5 Project Location

A. USIBWC Rio Grande City, TX gaging station located at (26°22'3.65"N, 98°48'13.37"W).

B. The work is located completely within the United States but is adjacent to the international border with Mexico.

1.6 Period of Performance

The period of performance shall be for a maximum of one-hundred twenty (120) days after the contract has been awarded to the Contractor.

USIBWC Solicitation Page-3 of 24

1.7 Investigation of Site Conditions

A. The Contractor, as well as their subcontractors, is urged to visit the jobsite and to become fully aware as to the existing conditions affecting the work to be performed under this Contract. The site visit will be coordinated with the Water Accounting Division.

B. Submission of a quote shall be conclusive evidence that the Contractor has reviewed, investigated, and acknowledged all items below.

1. Conditions bearing upon transportation, disposal, handling, and storage of materials.

2. The availability of labor, water, electric power, and roads.

3. Uncertainties of weather and similar physical conditions at the site.

4. The conformation and conditions of the ground.

5. The character of equipment and facilities needed for the performance of the work.

C. Submission of a quote shall be conclusive evidence that the Contractor has investigated and is satisfied as to the conditions to be encountered, the character, quality, and work to be performed, and the quantities of materials to be furnished.

D. Submission of a quote constitutes agreement that Contractor has provided written notice of all conflicts, errors, ambiguities, and discrepancies discovered in PWS, that responses to these written notices are acceptable to Contractor, and that PWS is enough to indicate and convey understanding of all terms and conditions for performing and furnishing required work.

E. Contractor has the sole responsibility to make such independent investigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in accordance with the PWS.

F. The Government assumes no responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this Contract, unless that understanding, or representation is expressly stated in this

Contract.

G. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.

1.8 Duty to Inquire

A. Contractor shall review the full PWS.

B. If during review of these items, the Contractor finds discrepancies, omissions, conflicts, defects, errors, or ambiguities, they have a duty to inquire and shall notify the Contracting Officer prior to the question submission deadline as established in the solicitation. The Contractor shall also inquire about items that are unclear or open to interpretation.

C. The Contractor shall take no advantage of any item of which they have a duty to inquire.

USIBWC Solicitation Page-4 of 24

1.9 Work Restrictions

A. The Contractor is responsible for conducting business between the hours of 8:00 AM thru 4:30 PM, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government-directed facility closings.

B. The Contractor may request different working hours and must do so in writing to the Contracting

Officer Representative (COR). USIBWC will make final determination as to the approval of a different work schedule.

1.10 COVID-19 Requirements:

A. Contractor employees must adhere to all CDC and OSHA COVID19 requirements while on IBWC property and when participating in any type of function associated with this requirement.

B. In accordance with OSHA EM 385-1-1 03.A.06 the OSHA recommended Infectious Disease

Preparedness and Response Plan is required and must be submitted within 10 days after award.

1.11 Department of Homeland Security

In any event the staff of the US Department of Homeland Security (DHS, also known as US Customs and

Border Protection or CBP) alerts and directs any field crews to stop work for any security reasons in the area, the Contractor shall consider this as top priority and fully cooperate with the directions of DHS at all times until the security alert is cleared by the DHS. In addition, the Contractor shall contact and coordinate with the COR for any additional steps to be taken during and after the security alert.

SECTION 2

PROJECT REQUIREMENTS

2.1 General

A. The Contractor shall be responsible for providing the proposed locations of the project staging areas for compliance confirmation of the COR prior to installation of the stormwater pollution prevention

(SWPPP) measures. Staging areas shall be sited in previously disturbed areas such as unimproved roads, trails, graded areas, or areas with compacted soil that do not support vegetation.

B. Contractor operations shall be confined to the USIBWC right-of-way. Portions of the site beyond areas on which the work is to be performed are not be disturbed unless the Contractor is granted access by the landowner and/or City.

C. The project area can be accessed through public access roads. Contractor shall verify that access can be accomplished through public access roads without causing damage to adjacent properties.

D. If required, the Contractor shall be responsible for obtaining all necessary rights of entry (ROE) for all work required under this Contract. This effort includes, but is not limited to, obtaining GIS property owner information, making phone calls, sending letters to land owners, and obtaining ROE access. USIBWC will provide an example ROE template to the Contractor.

USIBWC Solicitation Page-5 of 24

E. The Contractor shall conduct a Safety Meeting with all the personnel involved in the project and

IBWC COR prior to starting the project. In addition, daily safety meetings shall be conducted at the start of each workday.

F. Temporary Water

1. The water required for all project activities including, but not limited to, dust control shall be considered as incidental and shall be provided from a metered source that is compliance confirmed by the USIBWC.

2. Water from the Rio Grande shall not be used by the Contractor at any time.

3. Water use must be in accordance with state water law.

G. The Contractor shall submit a site-specific Health and Safety Plan and Job Safety Analysis Form filled out to be reviewed by the COR.

H. The Contractor shall conduct daily Safety Meetings with all the personnel involved in the project prior to starting each workday.

I. The Contractor shall provide a work plan (Draft and Final) identifying the equipment, personnel, and methods to be used to complete the dredging work. Work can commence only after written approval of the work plan by the COR.

2.2 Work Requirements

A. The Contractor shall remove and properly dispose of existing stairway, including any associated footings, miscellaneous materials, and debris.

B. The Contractor shall repair a 30’-wide x 75’ long section of slope alongside and underneath the existing stairway:

1. Strip and windrow existing topsoil before shaping operations.

2. Fill, cut, and shape the designated section of slope to blend into the surrounding terrain.

3. Eliminate ditches except where needed to facilitate drainage.

4. Cover disturbed areas with topsoil after shaping operations. The contractor will compact soil to 95% of standard proctor density.

C. The Contractor shall place geo-textile fabric and rock rip rap to protect the repaired slope.

D. The Contractor shall install an 8” pipe drain with inlet at top of slope to capture precipitation runoff and direct it to the bottom of slope in order to prevent future erosion of the repaired slope.

E. The Contractor shall construct a new stairway with handrails and landings per OSHA standards and shall extend to the bottom of the slope.

2.3 Clean-Up and Disposal of Waste Materials

A. The Contractor shall be responsible for the cleanup and disposal of waste materials and rubbish from the site, field office(s), and staging area(s).

B. The disposal of waste materials and rubbish shall be in accordance with applicable Federal, state, and local laws and regulations and with the requirements in this Contract. Should a conflict exist in the requirements for cleanup and disposal of waste materials, the most stringent requirements shall apply.

1. All waste unless otherwise noted in these specifications shall be disposed of at a licensed landfill or waste disposal facility.

USIBWC Solicitation Page-6 of 24

2. Recyclables

a. The Contractor shall dispose of recyclable and reusable products through waste disposal only as a last option.

b. Scrap metal shall be donated or sold to scrap dealers or recycle centers whenever possible.

C. No excess materials shall be deposited within Government property, unless compliance confirmed by the Government.

D. The Contractor shall maintain work and storage areas free from accumulations of waste materials and rubbish and before completing the work, shall remove all temporary facilities, including, buildings, unused materials, concrete forms, and other like materials, which are not a part of the permanent work.

2.4 Warranty

A. The Contractor shall warrant that work performed under this PWS conforms to the Contract requirements and is free of any defect in equipment, material, or workmanship performed by the

Contractor or any subcontractor or supplier at any tier for a period of at least one (1) year from project acceptance.

1. The Contractor is responsible for providing warranties on items when the manufacturer's warranty is less than the time indicated in Paragraph 2.4B or when the manufacturer's warranty does not cover full repair and/or replacement as appropriate.

B. The Contractor shall obtain warranties from responsible subcontractors, suppliers, and manufacturers, within sixty (60) days after completion of the applicable item of work, but no later than the date of warranty commencement. The minimum warranty period for any item shall be one year from acceptance.

C. Starting date of warranty is date of Government acceptance of the work.

D. A warranty requires that if a warranted item fails to meet Contract requirements, it shall be repaired, replaced, or have other remedial actions taken to bring the item into compliance with the Contract requirements. Any item damaged due to failure or malfunction of item warranted under this

Contract shall be repaired or replaced at no cost to the Government.

E. The Contractor shall supply the CO with a telephone number, mailing address, email address, and contact name for the point of contact for any required warranty work.

SECTION 3

EXISTING CONDITIONS

3.1 General

A. The Rio Grande City gaging station is located on the banks of the Rio Grande and approximately

800 feet upstream of the international port of entry and can be accessed from public roads.

B. The existing stairway is constructed of metal with concrete footings and pipe handrails.

C. The adjacent private property has been graded so as to direct surface runoff toward the stairway, causing erosion of the slope adjacent and underneath the stairway.

USIBWC Solicitation Page-7 of 24

D. There is erosion at the bottom of the slope so that the stairway does not meet the bottom of the slope, there is about 3’ of separation, and therefore, the stairway will need to be extended to safely land at the bottom of the slope.

3.2 Government Furnished Utilities

A. The Government will not be furnishing any equipment, material, services or utilities for this project.

3.3 Utilities

A. The Contractors shall ensure that Texas 811 or 1-800-Dig-Tess is contacted at least forty-eight (48) hours in advance of any work to allow utility operator to check and mark locations of existing utilities within the project limits.

B. The Contractor shall ensure that all underground utilities and other improvements which may be impaired during maintenance operations shall be protected, regardless of whether or not the utilities are indicated in the Contract documents. The Contractor shall take all possible precautions for the protection of unforeseen utility lines to provide for uninterrupted service and to provide such special protection as may be necessary.

1. It is the Contractor’s responsibility to document (either by photographs or video) ALL areas where any structures or utilities are located PRIOR to conducting work around these structures and notify the COR of any existing leaks and/or damages; otherwise any leaks and/or damages detected after work is underway will be repaired and/or replaced by the

Contractor at no cost to the USIBWC.

2. When existing vegetation obscures any structures or utilities, the Contractor shall ensure that obscuring vegetation is fully removed using hand labor in order to clearly document the structure/utility and its condition.

3. Any leaks and/or damage not detected prior to the beginning work around the pipes or utilities will be repaired and/or replaced by the Contractor at no cost to the Government.

C. Government’s Right of Access

The right is reserved to the Government and to the owners of public utilities and franchises to enter at any time upon any public street, alley, right-of-way, or easement for the purpose of making changes in their property made necessary by the work of this Contract.

D. Costs of Repairs

Costs of repairing utilities, even when damage is not due to failure of the Contractor to exercise reasonable care in locating and identifying utilities, will be the responsibility of the Contractor.

1. Costs include equipment on the project which was actually working on that portion of the

Work which was interrupted or idled by repair or relocation of such utility facilities and which was necessarily idled during such work.

E. Compliance Confirmation of Repairs

All repairs to a damaged utility or improvement are subject to inspection and approval by an authorized representative of the utility or improvement owner before being concealed by backfill or other work.

F. Maintaining in Service

Unless indicated otherwise, oil and gasoline pipelines, power and telephone or the communication cable ducts, gas and water mains, irrigation lines, sewer lines, storm drain lines, poles, overhead

USIBWC Solicitation Page-8 of 24 power, communication wires, and cables encountered along the line of the work shall remain continuously in service during all the operations under the Contract.

3.4 Use of Government Land

A. USIBWC easement property is available for use as the Contractor's staging and/or storage areas, subject to the approval of the COR. The Contractor shall preserve and protect existing features, trees, and vegetation to the maximum extent practicable.

B. Housing for Contractor personnel will not be permitted on Government land.

3.5 Hazardous Materials

A. The Contractor is responsible for evaluating the existing systems to determine the presence of lead or asbestos-containing materials.

B. The Contractor shall provide a finding report to the COR to include a plan for handling and proper disposal of lead and/or asbestos-containing materials prior to the removal of the existing systems.

SECTION 4

QUALITY REQUIREMENTS

4.1 Common Product Requirements

A. Materials Certification

The Contractor shall submit a materials certification package to COR which contains a checklist and supporting documentation for all materials used on the project. The supporting documentation shall consist of a summary of all documentation practices utilized for material acceptance and explanations of any deficiencies noted on the checklist.

1. Material certifications shall ensure that all items meet the Buy American Act (41 USC 10a -

10d).

B. Source Control

1. The Contractor shall use only materials that meet the Contract requirements.

2. Unless otherwise specified or compliance confirmed, the Contractor shall use new materials for the work. Material can be reused onsite upon written approval of COR.

3. All materials installed shall be free of defects.

4. The Contractor shall secure the Government’s compliance confirmation of the proposed source of materials to be used before their delivery.

C. Slope repair can be performed using the same type of soil found at the site, which is predominantly alluvial material with mixed clays.

D. Contract shall provide material submittals for USIWBC concurrence prior to material orders and deliveries.

E. Stone rip rap shall vary in size from 12” to 18” and shall meet the following gradation requirements:

USIBWC Solicitation Page-9 of 24

In-Place Protection Riprap Gradation Requirements

Nominal Thickness of

Riprap (in)

Maximum Rock Size

(lb)

Maximum Rock Size

(in)

90% Size by Weight1

50% Size by Weight1

0 to 10% by Weight Shall be

Less than2 (lb)

From (lb)

To (lb)

From (lb)

To (lb)

12 200 14 80 180 30 75 2

1 Sand and rock dust shall be less than five percent (5%) by weight of total riprap material.

2 The percentage of this size material shall not exceed an amount which will fill the voids in larger rock.

F. Geotextile

1. The fabric shall be constructed exclusively of synthetic thermoplastic fibers and shall be woven to form a mat of uniform quality.

2. Fabric fibers may be either continuous or discontinuous and oriented in either a random or an aligned pattern throughout the fabric.

3. The fabric shall be mildew resistant, rot proof, and shall be satisfactory for use in a wet soil and aggregate environment.

4. The fabric shall contain ultraviolet stabilizers and shall have non-raveling edges.

5. The filter fabric for this project shall meet all requirements of Type 2 in the following table:

Filter Fabric Requirements

4.2 Material Placement

A. Filter Fabric

1. The Filter Fabric shall be installed in accordance with the manufacturer's recommendations.

Physical Properties Test Method

Type 2

Fabric Weight on an ambient temperature air-dried tension-free sample.

ASTM D

203 g/m2 (6 oz/yd2), minimum

Permittivity, 1/sec.

ASTM D

0.5, minimum

Flow Rate

ASTM D

75 gpm/ft2

Tensile Strength (Grab)

ASTM D

890 N

(200 lbs), minimum

Apparent Opening Size

ASTM D

80-120

Elongation at yield,%

ASTM D

20-100

Trapezoidal Tear

ASTM D

334 N

(75 lbs), minimum

Static (CBR) Puncture

ASTM D

3226 N

(725 lbs)

UV Resistance, minimum

ASTM D

70%

USIBWC Solicitation Page-10 of 24

2. The Contractor shall prepare the surface to receive the geotextile to ensure that the surface is relatively smooth and free of obstructions, depressions, debris, soft or low density pockets of material, or stone which could damage the geotextile during placement.

3. At the time of installation, the geotextile shall be rejected if it has defects, rips, holes, flaws, deterioration, or damage incurred during manufacture, transportation, or storage.

4. All wrinkles and sags shall be stretched out immediately before stone is placed on the geotextile.

5. The geotextile shall be protected from damage during placement of stone. This shall be accomplished by limiting the height of drop to less than one (1) foot, or the water surface, whichever is greater. In the event that this damages the geotextile, the graded-coarse aggregate shall be placed directly on the geotextile with zero height of drop. Before placement of rock, the

Contractor shall demonstrate that the placement technique will not damage the geotextile.

6. For adjacent rolls of geotextile fabric, sew or lap geotextile panels to form the specified widths.

7. Backfilling around the geotextile shall be done in such a manner that the material will not be damaged during the placement.

8. Seams or laps may be utilized to produce panels of geotextile large enough to cover the area required. Seams or laps shall be perpendicular to the centerline of the structure. Seams or laps shall not run parallel with the direction of the centerline.

9. All seams shall be sewn using thread meeting the requirements for plastic yarn specified in

ASTM D883. Seam strengths shall meet the requirements of Error! Reference source not found..

10. When lapping is required, it shall be in accordance with the manufacturer's recommendations or a minimum of thirty six (36) inch overlap whichever is more stringent.

a. Lapping shall be placed uphill over downhill and upstream over downstream.

b. One hog-tie shall be installed along the geotextile lap every ten (10) linear feet of lap.

c. The fabric shall be laid out smooth without wrinkles or folds on the prepared subgrade in the direction of the construction traffic.

d. On curves, the fabric may be folded or cut to conform to the curves.

11. Damaged areas shall be repaired by overlaying the area with sufficient material to overlap on all edges by at least two (2) feet.

B. Stone Riprap

a. Riprap shall be placed in such a way that filter fabric on the slope surface will not be damaged by the riprap construction. Any damage to filter fabric by riprap construction shall be repaired by the Contractor at no additional cost to the USIBWC.

b. Place riprap to its full thickness in a single operation.

c. Ensure that the entire mass of stones in their final position is free from objectionable pockets of small stones and clusters of larger stones.

USIBWC Solicitation Page-11 of 24

d. Do not place riprap in layers.

e. Do not place riprap at the top of the slope and then push it down from the top of the slope or use any method likely to cause segregation of the various sizes.

f. Place stone for riprap on the bedding material to produce a reasonably well-graded mass of riprap with the minimum practicable percentage of voids.

g. Obtain the desired distribution of the various sizes of stones throughout the mass by selective loading of material at the quarry or other source or by other methods of placement that will produce the specified results.

h. Rearrange individual stones by mechanical equipment, or by hand if necessary, to obtain a reasonably well-graded distribution of stone sizes.

i. Use spalls and small stones lighter than twenty five (25) pounds to fill open joints and voids in stone riprap, and place to a tight fit.

2. A tolerance of plus six inches (+6 in) and minus zero inches (-0 in) from the slope line and grades is allowed in the finished surface of the riprap.

C. Quality Control / Quality Assurance of Materials

1. Source Limitations

To the greatest extent possible for each item of work, the Contractor shall provide materials of a singular generic kind from a single source.

2. Compatibility of Options

Where more than one choice is available as options for Contractor's selection of a product, material, or equipment, the Contractor shall select an option which is compatible with other products, materials, or equipment. Compatibility is a basic general requirement of product, material, and equipment selections.

3. Field Measurements

Verify field measurements, lines, grades, locations, and details at the jobsite prior to fabrication. It shall be the Contractor's responsibility to conform to and satisfy actual field conditions, for accuracy of dimensions, proper fit, and for adequacy of use intended.

4. The Contractor shall correct or remove materials that fail to meet Contract requirements or that do not produce satisfactory results. The Contractor shall reimburse the Government for cost incurred if additional quality assurance sampling and testing is required by a change of source.

5. Materials not meeting Contract requirements will be rejected, unless the Government approves corrective actions in writing. Upon rejection, the Contractor shall immediately remove and replace rejected materials. Should the Contractor fail to comply with the removal of rejected materials, the Government may remove and replace defective material and the cost of testing, removal, and replacement will be deducted from the Contractor’s final payment.

D. Hazardous Materials

The Contractor shall use materials that are free of hazardous materials. The Contractor shall notify the Government immediately when a visual observation or odor indicates that materials in required material sources or on sites owned or controlled by the Government may contain hazardous materials.

USIBWC Solicitation Page-12 of 24

E. Surplus Materials

1. The Contractor shall take ownership of surplus materials unless otherwise indicated in the

Contract documents.

2. The Contractor shall remove and dispose of materials in accordance with Paragraph 2.33 of this PWS.

F. Storage and Protection

1. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area to minimize waste due to excessive materials handling and misapplication.

2. Store and protect products in accordance with manufacturers' instructions.

3. Store with seals and labels intact and legible.

4. Prevent contact with material that may cause corrosion, discoloration, or staining.

5. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

6. The Contractor shall store and handle materials to preserve their quality and fitness for the work and shall store materials so that they can be easily inspected and retested. When required by the Government, the Contractor shall protect the material with cover, on wooden platforms, or on other hard, clean surfaces as necessary.

SECTION 5

TEMPORARY ENVIRONMENTAL CONTROLS

5.1 General

A. The Contractor shall provide and maintain methods, equipment, and temporary construction as necessary to provide controls over environmental conditions in the work areas, adjacent areas, temporary work areas and all Project Specific Locations and shall remove physical evidence of the temporary facilities at the completion of work.

B. The Contractor shall, at their own expense, obtain all required permits for environmental controls unless otherwise specified.

C. Contractors shall be responsible for knowing about applicable environmental laws and regulations.

5.2 Water Pollution

A. The Contractor shall ensure that all work activities are performed by methods that will prevent entrance, or accidental spillage, of solid matter, contaminants, debris, or other pollutants or wastes into the Rio Grande or associated watersheds of the project limits.

B. All discharges into "Waters of the United States" shall meet the requirements of the Clean Water

Act (CWA).

C. The Contractor shall meet all requirements of the Texas Pollutant Discharge Elimination System

(TPDES) requirements for discharges associated with maintenance activities including but not limited to preparation of a SWPPP.

D. The Contractor shall meet all the requirements of the SWPPP during maintenance activities.

USIBWC Solicitation Page-13 of 24

E. The Contractor shall provide secondary containment systems capable of containing twice the volume of the storage tank as well as appropriate spill cleanup materials onsite for any material that is toxic or is harmful to flora, fauna, or the environment.

5.3 Air Pollution

A. The Contractor shall ensure compliance with applicable federal, state, and local laws and regulations and with the requirements of the Contract documents concerning the prevention and control of air pollution and for pollutant emissions from all vehicles and equipment onsite. Should a conflict exist in the requirements for abatement of air pollution, the most stringent requirement shall apply. The Contractor shall utilize such methods and devices available to prevent, control and otherwise minimize atmospheric emissions or discharges of air contaminants including dust.

B. The Contractor shall ensure that equipment and vehicles that show excessive emissions of exhaust gases are not operated until corrective repairs or adjustments reduce such emissions to acceptable levels.

5.4 Dust Abatement

A. The Contractor shall, during the performance of the work required by the Contract documents, or any operations appurtenant thereto and whether within the maintenance limits of this project or elsewhere, comply with applicable federal, state, and local laws and regulations regarding the prevention, control and abatement of dust pollution. Should a conflict exist in the requirements for dust abatement, the most stringent requirement shall apply.

B. The Contractor shall be ultimately responsible for controlling objectionable dust caused by the operation of vehicles and equipment, clearing, or for any reason whatever. Dust shall be controlled at all times, including Saturdays, Sundays, and holidays, during both working and nonworking hours.

C. The Government has the authority to stop any maintenance activity contributing to dust levels which are excessive or are in violation of federal, state, or local laws. Dust control measures shall be maintained at all times to the satisfaction of the COR, in accordance with the requirements of the

Government.

D. All costs resulting from such work stoppage shall be the responsibility of the Contractor and

Contract time extensions will not be provided.

E. The Contractor shall reference dust control requirements in SWPPP under the Environmental

Protection Agencies (EPA's) general construction permit.

5.5 Noise Pollution

A. The Contractor shall ensure that noise is minimized throughout all phases of the Contract and shall exercise particular and special efforts to avoid the creation of unnecessary noise impact on adjacent noise sensitive receptors in the placement of non-mobile equipment such as air compressors, generators, pumps, etc. The Contractor shall ensure that mobile and stationary equipment is placed to cause the least disruption of normal adjacent activities.

B. The Contractor shall ensure compliance with the applicable federal, state, and local laws and regulations, regarding the prevention, control, and abatement of harmful noise levels. Should a conflict exist in the requirements for noise abatement, the most stringent requirement shall apply.

USIBWC Solicitation Page-14 of 24

C. All vehicles and equipment shall be such as to minimize noise to the greatest degree practicable.

Noise levels shall conform to the latest Occupational Safety and Health Administration (OSHA) and local agency standards.

D. All equipment associated with the work must be equipped with components to suppress excessive noise and these components must be maintained in their original operating condition considering normal depreciation. Noise attenuation devices installed by the manufacturer such as mufflers, engine covers, insulation, etc. must not be removed nor rendered ineffectual nor be permitted to remain off the equipment while the equipment is in use.

5.6 Oils

A. Oil means oil of any kind or in any form, including, but not limited to: fats, oils, or greases of animal, fish, or marine mammal origin; vegetable oils, including oils from seeds, nuts, fruits, or kernels; and, other oils and greases, including petroleum, fuel oil, sludge, synthetic oils, mineral oils, oil refuse, or oil mixed with wastes other than dredged spoil.

1. Petroleum oils include, but are not limited to, crude and refined petroleum products, asphalt, gasoline, fuel oils, mineral oils, naphtha, sludge, oil refuse, and oil mixed with wastes other than dredged spoil.

2. Synthetic oils are used in a wide range of applications, including as heat transfer fluids, engine fluids, hydraulic and transmission fluids, metalworking fluids, dielectric fluids, compressor lubricants, and turbine lubricants. Synthetic oils are created by chemical synthesis rather than by refining petroleum crude or extracting oil from plant seeds.

B. Oils shall not be stored within the 100-year floodplain.

C. All stored oils must have a secondary containment system capable of containing twice the volume of the storage tank. Appropriate spill cleanup materials must be available onsite at all times during maintenance.

1. Storage tanks shall have a capacity of 1,320 gallons or less or shall be properly licensed by the state where the tank is located.

D. A Spill Prevention, Control, and Countermeasure (SPCC) Plan shall be prepared if any of the following apply:

1. Have a stored oil capacity of 1,320 gallons or more.

2. Can reasonably expect that accidental discharge of oil will reach navigable waters or adjoining shorelines in quantities that may be harmful.

E. SPCC plans shall be provided with the Contractor's SWPPP.

F. The Contractor shall ensure that all equipment shall be cleaned (pressure washed and/or steam cleaned) of external oil, grease, dirt and mud, and all leaks repaired prior to arriving at the project site.

1. Any leaks or accumulations of grease shall be immediately corrected.

2. A written log of inspections and maintenance must be completed and maintained throughout the project period.

G. The Contractor shall ensure that all equipment, both onsite and at all Project Specific Locations, is maintained in good working order to prevent drips and leaks.

1. Leaking equipment shall not be used.

USIBWC Solicitation Page-15 of 24

2. Leaking equipment shall be red tagged by the COR. This equipment must be removed from the site until all leaks have been corrected.

H. The Contractor shall ensure that all equipment (heavy equipment, chainsaws, ATVs, other hand power tools, etc.) be fueled outside of adjacent riparian areas and wet areas and at least one hundred

(100) feet from any surface water. Specific fueling areas may be approved and designated by the

COR.

I. The Contractor shall ensure that any soil contaminated by oil shall be removed from the site and disposed of according to state requirements.

5.7 Mud from Vehicles

A. The Contractor shall ensure that a means of removing mud from vehicles prior to entering public roads is provided.

B. The Contractor shall ensure that a maintenance program for removing dust, debris, and mud from public roadways that may be tracked from work site is established and effective.

5.8 Migratory Birds

A. Bird species that are protected under the Migratory Bird Treaty Act (MBTA) may nest in areas containing trees or other suitable habitat within the project limits.

1. When possible, maintenance activities should be scheduled to occur outside of the migratory bird nesting season (from March 1 through August 31).

2. However, if maintenance activities must occur during the nesting season of birds protected under the MBTA, then the areas proposed for disturbances shall be surveyed and flagged for any nesting birds prior to maintenance to avoid inadvertent destruction of active nests and eggs.

3. If nesting birds are found during this survey, the birds and any related eggs must be relocated or mitigated at the Contractor's expense prior to starting maintenance.

B. US Fish and Wildlife (FWS) regulations do not allow for the collection or transport (dead or alive) of any migratory birds nor removal of their nests without a permit issued by the FWS Regional Bird

Permit Office. If birds or nest removal is required, the Contractor shall call the COR. The COR will coordinate with a USIBWC biologist so that they identify, coordinate, and acquire a temporary permit to collect the bird(s).

a. The Contractor shall notify the COR of any dead birds found on the project site.

5.9 Noxious Weeds

A. To prevent the potential spread of noxious weeds into work areas, Contractor shall be required to use weed-free equipment.

B. The Contractor shall ensure that all equipment is pressure washed to remove dirt and vegetation before bringing onsite to limit introduction of noxious weeds.

C. All subsequent move-ins of maintenance equipment shall be treated in the same manner as initial move-in.

USIBWC Solicitation Page-16 of 24

5.10 Restricted Activities

A. The Contractor shall ensure that disposal areas, stockpiles, or haul roads are not located in any wetland, water body, or streambed unless specifically allowed in the Contract documents.

B. The Contractor shall ensure that temporary crossings are not installed in or across any water body without the prior compliance confirmation of the appropriate resource agency and the Government.

C. The Contractor shall ensure that no equipment repairs shall occur on or in the floodplain/channel of the Rio Grande.

D. The Contractor shall ensure that unless compliance confirmed by the COR, all equipment shall be parked at the staging area or at the stockpile site at the end of each work shift.

E. The Contractor shall implement the provisions of USACE 404 permit. A copy shall be provided to the Contractor by the COR.

F. The Contractor shall submit the SWPPP to the COR for review and compliance confirmation.

5.11 Controls

A. Contractor shall ensure that the following are provided as required:

1. Stabilized Exits / Entrances

When tracking conditions exist, prevent traffic from crossing or exiting the maintenance site or moving directly onto a public roadway, alley, sidewalk, parking area, or other ROW areas other than at the location of stabilized exits. The COR will require the use a street sweeper, blade, water truck, or other equipment if other methods of track out control fail to prevent buildup of mud or dust on the roadway.

2. The Contractor shall ensure that oil drip pans are set under any vehicle left parked overnight or being repaired within USIBWC’s ROW to prevent oil drips from contaminating the soil.

5.12 Environmental Commitments

A. The Contractor shall ensure that all equipment is power washed prior to using onsite.

1. If equipment is demobilized and then returned to the project, it shall be power washed again.

2. Haul trucks are exempt from this requirement unless they are only used onsite.

B. Leaking or dripping equipment is not allowed to be operated on this worksite. The Contractor shall ensure that all equipment is in sound working order.

C. Equipment with oil seeps may require periodical power washing to ensure that oil is not deposited within USIBWC ROW.

D. The Contractor shall ensure that maintenance operations incorporate any environmental commitments identified in the project’s environmental documents referenced herein.

E. The Contractor shall include permission for Government access in arrangements for private lands used as staging areas, quarries, aggregate sources, borrow sources, etc. Government access to the private land shall be to identify cultural resources and conduct appropriate inspections.

USIBWC Solicitation Page-17 of 24

SECTION 6

DELIVERABLES

6.1 General

A. Deliverables include, but are not limited to:

1. Project Contractor shall provide work plans identifying the equipment, personnel, and methods to be used to complete the work within 14 calendar days of award of contract.

Licenses and Certifications

a. The Contractor shall submit all Licenses and Certifications required to perform this project specified in this PWS.

b. USIBWC will review the draft work plans and provide comments to the Contractor within 10 calendar days of receipt of the work plans.

c. The Contractor shall submit final work plans within 10 calendar days of receiving comments from USIBWC.

d. Work can commence only after written approval of the work plan by the COR.

2. Work plans shall address the following work elements

a. Slope repair

b. Drainage pipe and inlet installation

c. Construction of new stairway

3. Work plans shall include, but not be limited to the following:

a. Stormwater Pollution Prevention Plan

b. Health and Safety Plan and Job Safety Hazard Analysis

4. Kickof-Off Meeting Minutes

a. The Contractor shall submit the kick-off meeting minutes per Section 7.

5. Schedule

a. The Contractor shall submit a schedule per Section 9.

6. Monthly Progress Reports

a. Contractor shall prepare and submit to the USIBWC a monthly update report by the fifth of every month on the work performed the previous month. The report shall include major accomplishments for the reported period, significant problems and proposed solutions, and any issues with contractual requirements. The report, along with an updated schedule, shall be submitted by e-mail no later than the fifth day of the following month.

SECTION 7

PROJECT COORDINATION & ADMINISTRATION

7.1 General

A. The Contractor shall provide all materials, equipment, labor, and services required by this

Performance Work Statement to perform the work for the Contract sum and within the Contract period of performance.

USIBWC Solicitation Page-18 of 24

B. The Contractor shall be responsible for ensuring that all its suppliers, manufacturers and subcontractors have reviewed all applicable documents relative to their work. The Contractor shall provide all labor, material, equipment, and services not provided by the Contractor’s suppliers, manufacturers, fabricators, and/or subcontractors.

7.2 Security

The Contractor is responsible for securing the work site, equipment, and materials from vandalism and theft.

7.3 Safety

A. The Contractor is solely responsible for worksite safety while performing work or inspections on

Government property. The Contractor shall implement a safety program that protects the lives and health of personnel in the project area, prevents damage to property, and avoids work interruptions.

B. The Contractor is responsible for being cognizant of and ensuring compliance with the requirements set forth. Such responsibility shall apply to both the Contractor’s operations and those of the Contractor’s subcontractors.

C. The Contractor shall comply with all provisions of all applicable regulations of the Occupational

Safety and Health Administration (OSHA), 29 CFR 1910, Occupational Safety and Health

Standards, and 29 CFR 1926, Construction Standards.

1. The OSHA 29 CFR 1910 and 29 CFR 1926 can be accessed at http://www.osha.gov or http://www.gpo.gov/fdsys/.

D. The Contractor’s personnel shall be required to use appropriate personal protective equipment such as, but not limited to hard hats, safety goggles, welding shields, face shields, protective footwear, protective gloves, and hearing protection.

E. The Contractor shall perform daily housekeeping. The Government will not provide trash dumpsters.

7.4 Coordination

A. Contract operations shall be coordinated to ensure efficient and orderly progress of each part of the work. In addition to a Project Manager, the Contractor shall provide other administrative and supervisory personnel as required for proper coordination and administration of the work.

B. The Contractor’s Project Manager shall be available to the Government during business hours, as well as in emergencies. Other coordination responsibilities and activities required to be provided by the Contractor includes the following:

1. The Contractor shall be responsible for ascertaining the nature and extent of any simultaneous, collateral, and essential work by others. The Government, its workers and Contractors and others, shall have the right to operate within or adjacent to the project site to perform such work.

2. It is the Contractor’s sole responsibility to coordinate with landowners, and utility owners, who are affected by the Contractor’s activities for access, schedule, and progression of work throughout the project duration in order to provide continuous access to the affected owners and obtain uninterrupted access within the project areas.

http://www.osha.gov/ http://www.gpo.gov/fdsys/

USIBWC Solicitation Page-19 of 24

C. After award of the Contract, the Contractor shall not remove, or exchange personnel identified in their proposal unless employment with the Contractor ceases, they are unavailable due to a medical emergency, or they are requested to be replaced by the Government. Replacement can only take place after written approval from the CO.

D. The Contractor shall notify the maintenance inspector and the COR within twenty-four (24) hours of any personnel changes in the Project Superintendent, Project Manager, any Field

Superintendents, the Quality Control Manager, or any Safety and Health Officers.

7.5 Stakeholders

A. The Contractor shall coordinate as necessary with all stakeholders to include utilities (water districts, railroads, electric, gas, potable water, etc.), federal agencies, DHS, state, counties, and municipalities and any other entities affected by this Contract.

B. Coordination will be documented by submission of approval letters to the Government from each affected agency and or utility with responsible party signatures.

SECTION 8

PROJECT MEETINGS

8.1 General

A. The Contractor, the COR, or the CO may schedule project meetings at any time.

B. When USIBWC schedules a meeting, the COR shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The COR shall prepare the meeting agenda and distribute to all invited attendees.

C. When the Contractor schedules a meeting, the Contractor shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The

Contractor shall prepare the meeting agenda and distribute to all invited attendees.

D. The following meetings are anticipated, and the Contractor shall identify them in the Schedule:

1. Kickoff Meeting

2. Progress Meetings

8.2 Kickoff Meeting

A. After award of the Contract, the COR will coordinate with the Contractor to schedule a Kickoff

Meeting. The meeting shall take place prior to the beginning of any Contract work.

B. The purpose of the meeting is to introduce project personnel and to review responsibilities and procedures.

C. The Contractor shall reach an understanding with the Government regarding the project requirements as stated is this Performance Work Statement. This understanding shall be documented in writing and approved by the CO after the Kickoff Meeting.

USIBWC Solicitation Page-20 of 24

D. Attendees include, but are not limited to:

1. Contractor's Project Manager

2. CO

3. COR

4. Water Accounting Division Representative

5. It is recommended that Contractor's engineers, inspectors, subcontractors, suppliers, and other concerned parties also attend the conference. The Contractor may invite anyone they wish to this meeting.

6. All participants at the conference shall be familiar with the project and authorized to conclude matters relating to the work.

E. Agenda

Discussion of items of significance that could affect the work and project, including the following:

1. Introduction/designation of key personnel and their duties.

2. Review of the current phasing, critical work sequencing, and long-lead items.

3. Review of minimum project requirements.

4. Review of procedures for handling and processing modifications, RFIs, deliverables, and applications for payment.

5. Preparation of deliverable documents.

6. Use of site.

7. Work restrictions.

8. USIBWC and other's occupancy requirements.

9. Safety and first aid.

10. Security.

11. Maintenance of project site.

12. Working hours.

F. Meeting Minutes

The COR will record the discussions of the meeting and distribute the minutes to all attendees for review prior to finalizing.

8.3 Progress Meetings

A. If needed, the COR will schedule progress meetings once the Contractor has mobilized onsite. The

COR will conduct and issue minutes of the meetings. Meeting minutes will become official

Contract correspondence.

B. The Government may call other meetings on an "as needed" basis.

C. The purpose of these meetings shall be to analyze the progress of the work, resolve conflicts, and in general coordinate the operation of all organizations active at the project site.

SECTION 9

PROJECT SCHEDULE

USIBWC Solicitation Page-21 of 24

9.1 Description / Purpose

A. The Contractor shall prepare a project schedule which shall reflect completion of all work under this

Performance Work Statement.

B. Project schedule submittal shall include an electronic pdf file.

1. All abbreviations shall be defined.

2. Each project schedule shall show a revision date.

C. Baseline Schedule Preparation

1. A complete baseline schedule shall be submitted within seven (7) calendar days after the

Notice to Proceed is issued. The Government will review the project schedule and submit comments and required revisions within fourteen (14) calendar days of receipt.

a. Failure to include any work item required for performance…