PWS Power Pole ANT.pdf

PDF 866 KB Posted

Attached to
CANCELLED* USCG ANT Coos Bay Power Pole Repair
Solicitation number
70Z03326QSEAT0022
Issued by

About this file

This is a Statement of Work (SOW) for Request for Quote (RFQ) #70Z03326QSEAT0021 covering repair and modernization of electrical infrastructure at the United States Coast Guard (USCG) housing facility in Charleston, Oregon. The contract period of performance runs from October 1, 2026, through January 27, 2027. The primary objective is to safely and rapidly restore electrical service to the housing complex by structurally stabilizing a compromised utility power pole and upgrading its electrical distribution equipment to current safety codes. All physical work and electrical re-energization must be completed within a single, continuous 48-hour operational window due to an active power outage affecting housing habitability.

The contractor must provide all labor, materials, equipment, supervision, and transportation necessary to execute the following scope: straighten and plumb the existing leaning wood utility pole; structurally stabilize its base; shorten the pole top by a minimum of three feet to remove deteriorated wood; install a weather-resistant cap; provide and install a pressure-treated service backboard; install new weather-heads, weather-tight conduits, a 400-amp main safety disconnect switch in a NEMA 3R enclosure, and new Current Transformer (CT) cabinets with utility meters in NEMA 3R enclosures; and route necessary feeder wiring. The contractor must coordinate utility clearances with Pacific Power and local utility locating services, field-verify utilities before excavation, establish a safe work perimeter, remove all legacy equipment and debris, dispose of materials at certified facilities per environmental regulations, and restore ground surfaces. All work must comply with the National Electrical Code (NEC), National Electrical Safety Code (NESC), and OSHA standards. The contractor must secure and pay for all required municipal, state, and utility permits and inspections. Work may occur outside standard business hours (0800-1600 PST, Monday-Friday) as necessary. The government will provide standard electrical power (120/240V) and potable water at the job site; the contractor must provide portable sanitation facilities and all other resources needed.

View the file

Other files

File Type Posted
SF30-16c Solicitation Cancellation.pdf PDF
Power Pole 3.jpg JPG image
Power Pole 4.jpg JPG image
Power Pole 2.jpg JPG image
FIRM FIXED PRICE CLAUSES AND PROVISIONS.pdf PDF
Power Pole 1.jpg JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

RFQ # 70Z03326QSEAT0021

LAST UPDATED: 08/06/2026 PAGE 1/5

STATEMENT OF WORK (SOW)

FOR

USCG ANT Coos Bay Unit/Housing Power Pole Repair

1.0 GENERAL

1.1 BACKGROUND

The Coast Guard owned power pole located at the Charleston, Oregon housing facility is currently leaning and severely deteriorated on its top portion. To prevent catastrophic failure, structural and electrical remediation is required. Because this power pole services a Coast Guard housing complex, any power outages directly impact housing habitability. Consequently, all on-site installation and reconnection work must be executed within a strict, minimal timeframe and a strict timeline of 48 hours.

1.2 SCOPE

The Contractor shall provide all labor, materials, equipment, supervision, and transportation necessary to repair, straighten, and structurally stabilize one (1) existing wood utility power pole, and completely upgrade its associated electrical distribution equipment. This work includes, but is not limited to: shortening and capping the pole, installing a new pressure-treated service backboard, installing a new 400-amp main safety disconnect switch in a NEMA 3R enclosure, routing new weather-tight conduits, and installing new CT cabinets and utility meters. Due to an active power outage at the housing complex, all physical work and final electrical re-energization must be completed within a single, continuous 48-hour operational window. Negative Scope (Out of Scope): This PWS does not cover the complete replacement of the main utility-owned high-voltage distribution lines, nor does it include permanent repairs to internal housing unit wiring beyond the main service disconnect switch. Any work not explicitly defined in Section 5 of this PWS is considered out of scope unless authorized in writing by the Contracting Officer.

1.3 OBJECTIVE

The primary objective of this contract is to safely and rapidly restore reliable electrical service to the United States Coast Guard (USCG) housing complex. This will be achieved by structurally stabilizing a compromised utility power pole and modernizing its outdated electrical distribution equipment to current safety codes. The finalized infrastructure will eliminate existing electrical hazards, provide a stable power supply to housing residents, and simplify future utility maintenance and metering. Because the housing complex is currently experiencing a power outage, the ultimate goal is to execute these structural and electrical upgrades efficiently within a critical 48-hour window to minimize mission and quality-of-life impacts.

2.0 SPECIFIC REQUIREMENTS/TASKS

2.1 Site Preparation and Safety

2.1.1 The Contractor must coordinate with Pacific Power and the local utility locating services to obtain utility clearances prior to breaking ground.

LAST UPDATED: 08/06/2026 PAGE 2/5

2.1.2 The Contractor must field-verify underground and overhead utilities using electronic, magnetic, or physical potholing methods before executing excavation.

2.1.3 The Contractor must establish a safe work perimeter around the pole to protect residents and property from construction activities.

2.2 Structural Pole Modifications

2.2.1 The Contractor must straighten the existing compromised wood utility pole to a plumb (true vertical) position.

2.2.2 The Contractor must structurally stabilize the base of the pole to maintain the plumb position permanently.

2.2.3 The Contractor must shorten the top of the utility pole by a minimum of three (3) feet to completely remove deteriorated wood.

2.2.4 The Contractor must install a weather-resistant protective cap on the newly cut top of the pole to prevent water intrusion.

2.3 Electrical Infrastructure Installation

2.3.1 The Contractor must provide and install a new pressure-treated service backboard at the base of the pole.

2.3.2 The Contractor must provide and install new weather-heads/masts and weather-tight conduits.

2.3.3 The Contractor must provide and install a 400-amp main safety disconnect switch housed in a NEMA 3R rated enclosure.

2.3.4 The Contractor must provide and install new Current Transformer (CT) cabinets and utility meters housed in NEMA 3R rated enclosures.

2.3.5 The Contractor must route and terminate necessary feeder wiring connecting the weather-heads, CT cabinets, meters, and main disconnect switch.

2.4 Execution and Testing

2.4.1 The Contractor must complete all physical prep work and post-installation cleanup during standard business hours.

2.4.2 The active electrical power outage required to execute the pole modifications and electrical cutover must not exceed a single, continuous 48-hour window. The Contractor must coordinate the exact scheduling of this 48-hour outage window with the COR, Pacific Power, and the KO at least fifteen (15) business days in advance.

2.5 Site Demobilization and Disposal

2.5.1 The Contractor must remove legacy electrical equipment, debris, and refuse generated during the execution of this contract from the Coast Guard installation.

2.5.2 The Contractor must transport and dispose of removed materials at a certified off-base disposal or recycling facility in accordance with local and state environmental regulations.

2.5.3 The Contractor must restore the ground surface around the base of the pole to its original pre-construction condition.

LAST UPDATED: 08/06/2026 PAGE 3/5

3.0 QUALIFIED PERSONNEL

The Contractor must provide qualified personnel to perform all requirements specified in this

SOW.

3.1 CONTINUITY OF SUPPORT

The Contractor must ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor must ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor must provide e-mail notification to the Contracting Officer’s Representative (COR) prior to employee absence. Otherwise, the Contractor must provide a fully qualified replacement.

4.0 OTHER APPLICABLE CONDITIONS

4.1 Hours of Operation and Access

4.1.1 Due to the critical 48-hour continuous operational window, the Contractor is authorized to perform work outside of standard government business hours, including nights, weekends, and federal holidays, until the project is complete.

4.1.2 The Contractor must coordinate with the Contracting Officer's Representative (COR) and Base Security at least 48 hours prior to mobilization to ensure uninterrupted, 24-hour base access for personnel and equipment during the scheduled work window.

4.2 Government-Furnished Property and Information (GFP/GFI)

4.2.1 The Government will not provide any tools, materials, equipment, or vehicles for this project.

4.2.2 The Contractor must provide all necessary resources, including temporary lighting or generators if required for their own construction activities during the power outage.

4.3 Industry Standards and Code Compliance

4.3.1 The Contractor must perform all electrical and structural work in strict accordance with the latest editions of the National Electrical Code (NEC) and the National Electrical Safety Code

(NESC).

4.3.2 The Contractor must comply with all applicable Occupational Safety and Health Administration (OSHA) standards for construction and high-voltage electrical work.

4.4 Permits, Fees, and Utility Coordination

4.4.1 The Contractor must secure and pay for any municipal, state, or utility (e.g., Pacific Power) permits, fees, or inspections required to legally perform the work and re-energize the system.

4.5 PERIOD OF PERFORMANCE

LAST UPDATED: 08/06/2026 PAGE 4/5

The period of performance for this contract is 10/01/2026-01/27/2027.

4.6 PLACE OF PERFORMANCE

The place of performance will be United States Coast Guard ANT Coos Bay 63584 Boat Basin Drive Charleston, OR 97420.

4.7 HOURS OF OPERATION

Contractor employees must generally perform all work between the hours of 0800-1600 PST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees must be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.

4.8 TRAVEL

Contractor travel is not required for this requirement.

4.9 POST AWARD CONFERENCE

The Contractor must attend a Post Award Conference with the Contracting Officer and the COR no later than 05 business days after the date of award. The purpose of the Post Award Conference, which will be chaired by the Contracting Officer, is to discuss technical and contracting objectives of this contract and review the Contractor's draft project plan. The Post Award Conference will be held via TEAMS teleconference.

4.10 PROJECT PLAN

The Contractor is not required to provide a draft Project Plan at the Post Award Conference for Government review and comment, but is encouraged.

4.11 PROGRESS MEETINGS

The Project Manager must be responsible for keeping the COR informed about Contractor progress throughout the performance period of this contract, and ensure Contractor activities are aligned with DHS objectives.

5.0 GOVERNMENT FURNISHED RESOURCES

5.1 The Government will provide access to standard electrical power (120/240V) and a potable water connection at the job site for the Contractor's use during construction.

5.2 The Government will not provide bathroom facilities. The Contractor must provide and maintain their own portable sanitation facilities (e.g., portable toilets) on-site for the duration of the project.

5.3 The Contractor must coordinate the physical location of any portable sanitation facilities with the COR prior to delivery.

LAST UPDATED: 08/06/2026 PAGE 5/5

6.0 CONTRACTOR FURNISHED PROPERTY

The Contractor must furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in

SOW 5.0.