This combined synopsis/solicitation seeks quotes for gate attendant services at Plymouth/Paradise Park, administered by the John Day Project of the U.S. Army Corps of Engineers Portland District. The solicitation includes one base year and four option years for Gate Attendant A services. Offerors must be registered in SAM and provide completed OF312 representations and certifications with their response. Quotes are requested for 94-day periods of performance from April through October each year, starting in 2024. The performance work statement details duties including operating the entrance booth, collecting and remitting fees, posting reservations, and performing campground checks. The non-personal services contract provides a campsite, supplies, and training. The combined synopsis/solicitation serves as the only solicitation document; no written solicitation will be issued.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CombinedSynopsisSolicitation 24Q0024.pdf | ||
| Wage Determination 2015-5527 Rev 21 Benton County.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
Gate Attendant Services – Plymouth/Paradise Park
John Day-Willow Creek Project
1. General Information: The contractor shall provide labor, material, and equipment and supervision as specified to perform all duties described within this Performance Work Statement (PWS).
This firm fixed priced contract is for a base plus four option years per the government’s discretion. The period of performance for the base year will be date of contract award 15 April through 15 October 2024. The following option year period of performance, if exercised, will be 1 February through 31 January of each option year. This is a non-personal services contract.
1.1 Background:
1.1.1 Plymouth is located about 30 miles south of Kennewick, Washington on the Columbia River near Plymouth, Washington (population about 200). There is a post office, but no stores at this time in the town of Plymouth. Umatilla, Oregon (population about 7,010) is less than 5 miles from Plymouth Park.
The area around Plymouth consists of irrigated cropland, floodplains and rolling hills. Vegetation includes grasses, sagebrush, cottonwoods, alders & Russian olive trees. Common wildlife includes Canada geese, mallards, pheasants, magpies and beaver.
Summers are generally hot and dry with temperatures near 110 degrees possible. The humidity is usually low, which makes the heat more tolerable.
There are 14 campsites with full hookups and 18 campsites with electric and water hookups.
The day use area has a boat ramp, docks, swimming area, picnic area, restrooms and irrigated lawn.
FEES AT PLYMOUTH PARK INCLUDE (for year 2024):
Campsites with full hookups = $35 Campsites with water & electric = $30 Walk-in tent campsites = $15 Extra vehicle = $5.00 per night Trailer dump = $5.00 Boat ramp fee = $5.00 Day Use fee = $5.00 per vehicle.
1.1.2 Paradise Park is located about 3 miles west of Plymouth. The surrounding environment and area is similar to that of Plymouth. There is one large group campsite, one vault toilet, and river access.
FEES AT PARADISE PARK INCLUDE (for year 2024):
Group campsite = $50
2. Definitions and Acronyms: The following definitions and descriptions apply wherever the word, phrase, or acronym is used in this Performance Work Statement.
Acceptance Quality Limits (AQL): A measurement of acceptable quality limits for the Performance Requirements Summary table.
Contract Discrepancy Report (CDR): A written record of unsatisfactory performance by the contractor as observed by the Quality Assurance Evaluator (QAE).
Contracting Officer (KO): The Government employee who is authorized to enter into, administer, and/or terminate contracts and make related determinations and findings.
Contracting Officer’s Representative (COR): Assigned by the Contracting Officer as the quality assurance evaluator (QAE), the COR is responsible for quality assurance guidance and ensures that contract quality requirements, provisions, standards, and thresholds are defined, practical, enforceable, necessary, and verifiable.
Defect: A service output that does not meet the standard of performance specified in the contract for that service.
The HUB: Computer software used on a daily basis to manage the reservation process and campground inventory.
Performance Requirements Summary (PRS): Identifies critical success factors for the contract. It identifies both the performance objectives for those factors and the performance threshold required for each performance objective.
The Government reserves the right to survey all services called for in the contract to determine whether or not the performance objectives and goals were met.
Quality Assurance (QA): A method used by the Government to provide some measure of control over the quality of services received.
Quality Assurance Evaluator (QAE): The Government employees responsible for checking contractor performance.
Quality Assurance Surveillance Plan (QASP): A systematic method to evaluate the services the contractor is required to furnish in accordance with the PWS and PRS.
Quality Control (QC): A method implemented by the contractor to control the quality of goods and services provided.
Quality Control Inspector (QCI): A contractor’s employee responsible for monitoring and addressing issues with the quality of goods and services provided.
Quality Control Plan (QCP): A plan developed by the Contractor which includes quality control actions necessary to meet the quality standards set forth by the contract. The plan should be in compliance with the PWS. Once approved by the Government, the plan becomes a part of the QASP.
Recreation 1 Stop (R1S) - Federal portal for payments.
3. Requirements Government:
3.1 Provide Gate Attendants with campsite that includes water, electric, and sewer hookups. Campsite will be made available to the contractor 5 days prior to the beginning of the work period and for 5 days after the completion of the work period. Such timeframe is to provide contractor time to set up and prepare for the contract and to break down and pack afterward. Campsite shall be vacated no later than 5 days after completion of the work period.
3.2 Provide a secure vault for the storage of funds.
3.3 Provide Gate Attendants with vests and name tags.
3.4 Supply all forms, pamphlets, permits, and brochures for distribution to the campers.
3.5 Supply Recreation 1 Stop computer work station, receipt printer, report printer, and till.
3.6 Supply toner and paper for printers.
3.7 Maintain grounds and other Government property used by the Gate Attendant in performance of the required duties. A refuse container for solid waste shall be provided and serviced by the Government.
3.8 Provide telephone service for the Gate Attendant booth.
4. Requirements Contractor:
4.1 The contractor may be required to provide additional (as necessary) equipment, tools, materials, vehicles, supervision and services necessary to perform Gate Attendant Services as defined in this Performance Work Statement for the positions stated in Annex A. The Contractor shall provide:
4.1.1 A mobile travel trailer, motor home or approved equal, containing sanitary facilities and all equipment necessary for habitation. (If the vehicle or trailer is something other than a traditional commercially available type, contractor shall seek and receive approval to contract award.) Tents or ‘pop-up’ style type campers are not permitted. If self-propelled units are used, they must remain on jacks or be blocked up for the duration of the contract and not be used for transportation.
4.1.2 Contractors must have a motor vehicle, at no expense to the Government, which will be used for local transportation to perform the requirements of this contract. All vehicles will comply with all local, state, federal laws and be operated on roadways at all times. The contractor shall also provide proof of valid driver’s license, vehicle registration, and vehicle insurance for vehicle use in the campground, sufficient by State requirements.
4.1.3 Contractor shall provide insurance, at its own expense, and maintain insurance during the entire performance period of this contract. This is in accordance with Clause 52.228-5, Insurance- Work on a Government Installation.
4.1.4 Contractors must provide their own medical insurance. Medical insurance and expenses shall not be covered or paid for by the U.S. Army Corps of Engineers.
4.1.5 Office supplies necessary to perform the requirements of this contract which includes but is not limited to, pens, pencils, markers, rubber bands, staples, paperclips, and tape, etc.
4.1.6 Cleaning equipment and supplies for the entrance booth necessary to perform the requirements of this contract.
4.1.7 All Contractors before initiating performance of work shall submit a surety bond for both Contractors. Army regulations require Contractors who collect fees to be fully bonded or insured to protect the Government against theft, misappropriation, or loss of Government funds under control of the Contractors. The Contractor is required to furnish to the Contracting Officer proof of such a bond in the minimum amount of $5,000.00 prior to beginning work. A surety bond is not a grant of relief nor does the USACE relinquish its rights against the bond in a non-negligent loss case. It is the sole responsibility of individuals seeking bonds to establish the soundness of the company and/or services offered by them.
4.1.8 The contractor should expect at least one on the spot fee audit per recreation season.
4.2 Training: The awarded Contractors shall attend a Post Award Conference & the computer Recreation 1 Stop/ Credit Card Training Sessions, campground policies and procedures training. The training will be used to discuss and develop an understanding of all contract requirements, sign for keys and accountable property as required, to train on the use of reservation computers, and training on the use of the Recreation 1 Stop software. The Government will give written notification of the scheduled dates for the post-award conference and the computer training within seven (7) business days after notification of award. The training will be held at each respective park and at the John Day Dam in Rufus, OR. There could be one day of training scheduled at the dam, followed by one day of training at the respective parks.
Transportation to the training site is the responsibility of the contractor. Mileage shall be reimbursed to the contractor at the rate of $0.54 per mile for one round trip from assigned park to the one day training at John Day Dam.
4.3 Recreation 1 Stop: The contractor shall perform specific daily duties to implement the Recreation 1 Stop, according to established procedures (that will be taught during pre-performance training). Duties include, but are not limited to, maintaining current records, posting reserved sites, checking site availability, processing camper registrations and receiving daily arrival reports. Contractors shall not accept phone reservations. The Recreation 1 Stop site allows and USACE and field personnel to:
Check site availability Post reserved sites Process camper registration Receive daily arrival reports Maintain records
5. Performance Standards and Requirements:
See Annex A for specific details regarding the services required Park; inclusive of all schedule requirements. Gate Attendant contract requires Two (2) individuals working as a team.
The Contractor shall perform to the standards in the contract and comply with all local, state, and federal regulations during the services performed. The following information shall apply for the 2024 -2029 Park Gate Attendants
The Contractor shall:
5.1 General:
5.1.1 Perform campground management duties in this section. Contractors will be trained on specific details of duties before first scheduled day of operation. The training day will be a paid workday. A manual is present in the entrance booth for reference.
5.1.2 Staff the gate house with at least one contractor at all times during park hours, as detailed within the contract. This ensures that one contractor is available for visitors, to answer phone calls, and check that incoming vehicles have valid permits while the other contractor performs rounds in the park or assists visitors in line to speed up the registration process.
5.1.3 Know and follow all rules, regulations, policies, and procedures as well as inform and encourage visitor compliance of all rules and regulations.
5.1.4 Provide their work attire:
5.1.4.1 Maintain a clean and neat appearance when dealing with the public.
5.1.4.2 Wear the vest and nametag provided by the government during duty hours and when making contact with the public. Nametag shall be worn on the vest.
5.1.4.3 Wear a shirt with collar and sleeves, such as a “polo style”, “golf shirt” or blouse.
Shirt shall be worn buttoned.
5.1.4.4 Dress in a neat fashion in properly fitting, clean, wrinkle free clothing that is in an acceptable condition.
5.1.4.5 No holes, patches, or signs of “wear” such as fading, missing buttons, broken zippers, stains or fraying or signs of former patches or nametags.
5.1.4.6 Bermuda-style shorts or similar may be allowed, but excessively short and/or tight pants and skirts, swimwear, undershirts, tank tops, halter tops, cutoff shirts, open toed shoes, or similar attire shall not be allowed.
5.1.5 Exercise responsible customer service, courtesy, professionalism, tact and diplomacy while dealing with the public and government personnel. The parks are available to anyone without regard to sex, race, creed, color, or national origin. More than three (3) legitimate complaints from the public regarding mentioned behavior, rudeness, favoritism, discrimination, bad language or violations of policies and procedures shall be considered grounds for termination of contract.
5.1.6 Submit written feedback to the park ranger regarding the specifications, gate attendant duties or any other aspect of the gate attendant program. This will be submitted with the contracts final invoice.
5.1.7 Not post any signs, decorations, or pictures without approval or direction from COR or designee.
5.1.8 Establish and implement a method of control for all keys issued to the contractor by the government to ensure keys are not lost, misplaced, duplicated, or used by unauthorized persons.
The contractor shall prohibit the use of keys issued by the government by any persons other than the contractor. The contractor shall not open locked areas to permit entrance of persons other than contractors engaged in performance of contract work requirements in those areas. The contractor shall not duplicate any keys issued by the government. The contractor shall immediately report to the Quality Assurance Evaluator (QAE) and Contracting Officers Representative (COR), any occurrences of lost or duplicate keys.
5.1.8.1 In the event keys are lost or duplicated, the contractor may be required, upon written request of the COR, to re-key or replace the affected lock(s) without cost to the government. The government may, however, at its option, replace the affected lock(s) or perform re-keying and deduct the cost of such from the monthly payment due the contractor. If such instance occurs, prior approval of methods and sources used must be obtained by the contractor from the COR. In the event a master key is lost or duplicated, the government shall replace all locks and keys for that system and the total cost deducted from the monthly payment due to the contractor.
5.2 Gate House:
5.2.1 Operate the gate houses in accordance with this Performance Work Statement. Work assigned workdays which includes federal holidays during the contract. Remain in the campground “on call” as required during assigned work days.
5.2.2 Utilize Recreation 1 Stop and computer to carry out daily park operations. Initial training and manuals will be provided by the government.
5.2.3 Perform duties relating to reservations including but not limited to: processing check-ins, check- outs, walk-ins, creating permits, posting permits, checking site availability for visitors, maintaining current on site records, processing recreation fees, and maintaining a status of the campground to show occupancy and availability of campsites, assigning campsites to campers and ensuring only designated campsites are to be used.
5.2.3.1 Not take reservations over the phone, issue campsite permits for campsites that are nonexistent, already reserved, or occupied. Do not create unofficial reservation systems or hold sites for customers. Contractor shall not grant any camping extensions over 14 days in any 30 day period limit. The contractor shall not assign campsites for use by anyone not camping (picnickers, etc.).
5.2.3.2 Educational, non-profit, and special event groups shall be advised to make special camping arrangements with the park ranger.
5.2.4 Collect and Remit campsite fees, day-use fees, and annual pass fees using Recreation one stop, computer, and till. Only accept US currency, credit cards, personal checks, or traveler’s checks payable by a US bank. No Canadian or other foreign currency or travelers checks are to be accepted. The contractor shall be held accountable for all money collected. Funds that cannot be accounted for shall be deducted from the contract amount. All funds shall be stored securely.
5.2.4.1 Accept checks for payment provided that: it is from US bank, a first party check, made payable to “Recreation 1 Stop” with specific campground id number, made out for the exact amount of the fee, has the campers home address, driver’s license number and the state of issue. No starter checks or unnumbered checks shall be accepted.
5.2.4.2 The contractor shall not issue refunds. Refund requests will be submitted through the “Recreation 1 Stop” and reviewed by the park ranger for approval.
5.2.4.3 Accept and process the appropriate America the Beautiful Passes. The bearer of such passes shall be entitled to a reduction in the prescribed user fee. Examples of acceptable passes and policies will be explained during training.
5.2.4.4 Count and remit self-registration honor vault fees with a park ranger using the Recreation 1 Stop site.
5.2.5 Process monies in accordance with Corps policies and procedures to be gone over during training.
5.2.5.1 Create a deposit for submission at the end of each 5 day work cycle and any time the value of the deposit reaches $1,500 cash.
5.2.5.2 Guidance on preparing the deposits will be provided during training.
5.2.5.3 Pay for cashier’s check or money order fees. The contractor shall NOT be reimbursed for these expenses. These expenses are estimated to be $50.00 to 100.00 for the season. Deposit for submission shall be turned into the appointed park ranger for submission.
5.2.5.4 Provide and maintain an adequate change fund of $60.00 minimum.
5.2.6 Prepare user permits for reserved campsites. The contractor shall issue camping and vehicle permits to all paid campers and vehicle permits to all paid day users. The contractor shall instruct the visitors on how to properly display the permits. All vehicles and occupied campsites must have the proper permits.
5.2.6.1 Sell and issue Corps of Engineers Annual pass permits and America the Beautiful passes. A standard operating procedure explaining eligibility for passes will be available at gate houses. The contractor shall be issued passes at the beginning of the season. The contractor shall report to a park ranger when more passes are needed throughout the season. The contractor will be responsible for passes once they have been issued by a park ranger. Any unsold passes and copies of issued pass recipes will be returned to a park ranger at the end of the season.
5.2.7 Distribute approved items relating to recreation including but not limited to; brochures, maps, comment cards (when applicable), and water safety items. Distribution items must be approved by the park ranger prior to distribution.
5.2.7.1 Provide information and assistance and answer phone calls. Contractors shall inform campers and visitors about the camping regulations. Do not enforce regulations nor attempt to apprehend violators.
5.2.8 Report any equipment breakdown or facility problems by completing a repair request form with a description of the condition and turn it in to the park ranger. If it is an emergency contact the park ranger immediately.
5.2.8.1 Promptly, accurately and completely report to the park ranger all accidents, incidents, and situations that could adversely affect the health and safety of the visitors, or potentially result in a law suit against the government.
5.2.9 Report all non-routine communications with local law enforcement officers to the park ranger as soon as practical.
5.2.10 Report all disturbances and violations of campground rules to the park ranger on duty in the event of an emergency. Obtaining descriptions of vehicles, violators, and license plate numbers shall only be done when safe to do so. This may be coordinated with local law enforcement.
Report and safely observe all after hours disturbances in accordance with local policies. Policies shall be discussed at training and detailed in the gate attendant manual.
5.2.11 All reports above shall be sent to the COR as well, if there may be an impact of any portion of the contract. Report all issues, incidents, questions, or concerns which may change, modify, or impact any working condition contained within the contract to the COR.
5.2.12 Be responsible for keeping the entrance booth neat, clean, and organized. The contractor shall not alter or repair anything in or around the entrance booth.
5.2.13 Only allow other contractors (gate attendants), properly identified and authorized Corps employees inside the entrance booth. Pets, visitors and smoking are not allowed in the entrance booth.
5.2.14 Work together in cooperation with the other contractors and employees. The contractor shall record all pertinent information to include but not limited to observances out of the norm, visitor complaints, and maintenance issues in the log book to ensure a smooth and informative transition between shifts. All contractors must read the log book at the start of the shift.
5.2.15 Specific work hours are detailed in Annex A and are subject to change at the discretion of the Government. Any changes shall be communicated by the COR.
5.3 Rounds:
5.3.1 Perform duties while making rounds through the campground including but not limited to:
assure all users have valid permits that are displayed correctly, check that vehicles are parked in designated areas only, provide information, assistance, answer questions, inform campers and visitors about the camping regulations, check on the status of sites (occupied, unoccupied) and keep an updated list of site availability.
5.3.1.1 Rounds shall be made at regular intervals throughout the day and when the contractor feels necessary to check on the status of the campground. No less than four (4) rounds shall be made each day. There shall be a round at the beginning and end of each shift.
5.3.2 Post reservation permits on site posts at least 2 days prior to the incoming reservation or other time frame established by COR.
5.3.3 Stock self-registration envelopes and pencils at designated boxes by fee vaults daily.
5.3.3.1 Place a self-registration fee envelope on the windshield of vehicles at the boat ramp that entered the park before the entrance booth was opened.
5.4 Rules:
5.4.1 Shall be expected to work together with volunteers to assist with helping the public, but at no time shall the contractor assign jobs to the volunteers. The contractor may refer possible volunteers to the park ranger; but shall not enter into agreements or direct volunteers.
5.4.1.1 Volunteers will be directed by the park rangers. If a problem comes up with a volunteer the contractor is to notify the park ranger or designated representative.
5.4.2 Not attempt to turn off, on or adjust utilities (electricity, water or irrigation controllers) without express permission from the park ranger. Nor allow anyone who is not properly identified as an appropriate Corps employee access to utility valves, switches or other control devices at any time.
5.4.2.1 Any unidentified or unauthorized individual working on or tampering with utilities should be reported to a park ranger.
5.4.3 Not allow any camper to stay beyond 14 days in any 30 day period. (CFR title 36 Section 327.7b)
5.4.4 Report visitors who do not comply with park rules to the park ranger as soon as possible.
5.4.5 Not solicit, advertise, sell or offer to sell any unauthorized goods or services to campers or visitors on public property. (CFR Title 36, Section 327.18)
5.4.6 Not provide to the public nor apply themselves pesticides or chemicals of any sort in any area unless prior approval has been given by the park ranger.
5.4.7 Not order anyone to leave the campground.
5.4.8 Not accept any gratuities.
5.4.9 Not carry firearms.
5.4.10 All vehicles used on Corps property must be licensed and street-legal and must otherwise comply with all local, state and federal laws. Alternative electric modes of transportation may be used by the contractor within the campgrounds while performing daily operational duties. These alternative modes of transportation shall not be furnished by the Corps.
5.4.11 Not be under the influence of intoxicating beverages, drugs or controlled substances while on duty or on call.
5.4.11.1 Not be in possession or under the influence of illegal substances.
5.4.12 Not make personal long distance phone calls at the government expense. The government furnished phone line shall be reserved for incoming and outgoing calls by others. The phone line and satellite link shall not be used for personal internet access by the contractor or the general public.
5.4.13 Maintain safe and sanitary conditions around living quarters at all times. No tarps or storage tents shall be used. No pens, corrals or similar facilities for pets or the raising of animals shall be located on government property. All pets shall be attended at all times and kept on a leash.
5.4.14 Do not plant flowers, vegetable gardens, or other plants in government land. All plants are restricted to pots.
5.4.15 Have any personal visitors stay within their living quarters, otherwise they shall pay the regular camping fee and occupy the site for which they are registered.
5.4.15.1 Not allow visitors to access the contractor’s hook-ups or park additional recreational vehicles at or near the contractor’s designated living area.
5.4.15.2 Know that the park ranger may limit the number of visitors and length of stays.
Visitors shall not be allowed in the vicinity of the entrance booth, except when they are registering or paying fees, and shall receive no preferential treatment regarding fees, site assignment or Corps policies.
5.5 Invoices: Invoices shall be submitted within the first 5 days of the month for the previous month’s period of performance. At a minimum, invoice will contain the following information:
Name and address of contractor Invoice date and number and period of performance Contract number (to include order number and/or CLIN) Description, quantity, unit of measure, unit price, extended price of supplies delivered, or service performed. (Number of days worked or miles traveled for initial training.)
Shipping and payment terms, including shipment number, date, and any discounts.
Name and address of contractor official to whom payment is to be sent.
Name, title, phone number, and mailing address of person to notify in the event of a defective invoice.
Taxpayer ID Electronic funds transfer banking information Any other additional information or documentation that is written in the contract.
6. Performance Requirements Summary: It is intended to ensure that the Government receives the services for which it contracted. The Government will only pay for services received. The Performance Requirement Summary (PRS) determines if the contractor meets the performance standards of the contract, as well as provides guidelines for how and when surveillance will be performed. The PRS ensures timeliness, effectiveness, and that the contractor is delivering the results specified in the contract. Government contract quality assurance will be performed at such times and/or places as may be necessary to determine the services conform to contract requirements.
6.1 Quality Assurance Surveillance Plan (QASP): The table below summarizes the criteria against which the performance will be evaluated. Work shall be considered not to have been performed when any one of the Performance Standards does not meet the acceptable quality limits (AQL). The Quality Assurance Surveillance Plan (QASP) is a document that communicates to the contractor the surveillance methods that will be used to measure its performance against the standards in the contract and provides means by which the Government monitors and documents performance. Quality Assurance (QA) is the Government process that ensures the contractor delivers quality service. The surveillance methods identified in the QASP together with the contractor’s QCP will help determine whether the contractor delivers the performance agreed to in the contract. The Government reserves the right under the Contract Terms and Conditions— Commercial Items (FAR 52.212-4) to inspect and test the services called for by the contract, to the extent practicable at all times and places during the term of the contract. Non-conforming services shall be rejected.
Performance Objective
Performance Standard AQL Validated Complaints
Customer Service The contactor must be professional, courteous, diplomatic, tactful and not discriminatory with the public and government personnel.
No more than 3
Documented Customer Complaints
Campground Entrance Station
The Entrance Station is observed to be clean, orderly, and well stocked with supplies. The Contractor requests additional supplies well before they run out.
90% Periodic Inspection
Campground Reservation System
The Contractor enters data into the NRRS database promptly and accurately, without assistance. Reports and reconciliation are done at the end of each Duty day as per Recreation 1 Stop manual.
100% 100% Inspection of Reports
Federal Fee Collection
All monies are accounted for and secured. 100% 100% Inspection of Reports
Remitting Fees Remittances are completed at the end of each Shift and whenever total collected exceeds $5,000.
100% 100% Inspection of Reports
Campground Checks
Campground checks are performed according to the required schedule (minimum 4 times per duty day).
90% Periodic Inspection
Posting Reservations and Notices
Reservations and notices are posted timely, as described in the Gate Attendant Handbook. The occupied site list from NRRS matches observed occupancy in the campground.
90% Periodic Inspection
Campground Checks Incident handling/reporting
Incidents and violations are handled timely and professionally and reported to the appropriate authorities. The Entrance Station reports are complete and current.
100% 100% Inspection of Log Book
6.2 Quality Control by Contractor: The contractor, not the government, is responsible for quality control actions necessary to meet the quality standards set forth by the contract. The contractor shall develop and submit their Quality Control Plan (QCP) for government approval after award in compliance with the Performance Work Statement prior to work commencing. Once accepted, the QCP shall be used by the contractor to ensure that they deliver quality service.
6.3 Surveillance: Periodic surveillance by the COR, in addition to complaints from project personnel and/or visitors areas under this contract, will serve as the surveillance method. If the COR discovers deficiencies and/or receives complaints, the COR will pass them on to the contractor's Quality Control Inspector (QCI) for correction.
6.4 Unacceptable Performance: When performance is determined unacceptable, as defined in the Performance Requirements Summary, the Quality Assurance Evaluator (QAE) will inform the contractor’s on-site representative that performance is unacceptable and provide written documentation by use of the form DD 2772, Contract Discrepancy Report, Attachment 1. By initialing and dating the form, the contractor is only acknowledging notification of unacceptable performance. Disputes in surveillance should be referred to the contracting officer.
6.4.1 If the Contractor fails to perform at any time and the work is deemed critical by the COR, Government personal may be assigned to perform the work. If this occurs, the Contractor shall be required to reimburse the Government for the full costs of the work performed including labor, materials, transportation, and supervision.
6.4.2 The QAE will notify the COR and the Contracting Officer of less than acceptable performance. If any of the services do not conform to contract requirements, the government may require the Contractor to perform the services again in conformity with the contact requirements, at no increase in contract amount. Daily cleaning/sanitation are not considered re-performable work, and shall result in a deduction for non-performance of work. When the defect(s) in services cannot be corrected by re-performance, the government may:
a. Require the Contractor to take necessary action to ensure future performance conforms to contract requirements.
b. Reduce the contract price to reflect the reduced value of the services performed.
c. If the Contractor fails to promptly re-perform the services, or to take the necessary action to ensure future performance in conformity with contract requirements, the government may:
i. By contract or otherwise, perform the services and charge to the Contractor any cost incurred by the government that is directly related to the performance of such service or
ii. Issue Cure Notice
iii. Terminate the contract for government convenience
iv. Terminate the contract for Cause.
6.5 Correction of Non-Performance of Work: The Contractor shall employ an adequate quantity of personnel to insure that any area found to be not in compliance and therefore not acceptable, shall be made acceptable by the performance or re-performance of the work, where such re-performance is possible, during the first business day after noncompliance has been observed by or reported to and verified by the
COR.
6.6 Standard: Recurring defects are not permitted for any of the above service items. For example, if the COR determines that the contractor financial packets / deposits are not processed weekly, both in timeliness and accuracy, in accordance with the Project policy, the contractor is required to correct the defect through re-performance. Additional defects are recorded against the contractor's performance.
However, if this same situation occurs again during the contract period, the additional defect will be recorded and reported to the Contracting Officer for appropriate action in accordance with FAR 52.212.4, Contract Terms and Conditions-Commercial Items (May 1997).
6.7 Verification of Work: If the Contractor performs work other than at the scheduled time, the Contractor Shall notify the COR and receive approval prior to completion of work in order to secure any payment.
Work performed at times other than posted on the schedule and not coordinated with the COR shall be considered not completed.
6.8 Damages Caused by the Contractor: The Contractor shall be held accountable and liable to the Government for any damages to government facilities, fixtures, furnishings, equipment, or grounds caused by the Contractors or their employees.
6.9 Interference with Government Operations: The Contractor and the Contractor’s employees shall perform all work in such a way as to not interfere with regularly scheduled Government operational activities.
6.10 Services during Repair Activities: It is expected that during the period of this contract that occasional repairs may have to be made by electricians, plumbers, carpenters, or other maintenance personnel within the project.
All large debris generated by such activities shall be removed by the Government personnel, who shall also clean up the affected area by sweeping with brooms and depositing such collected matter into wastebaskets.
The Contractor shall thereafter accomplish the janitorial services as specified to restore such areas to their original cleanliness.
6.11 Lost and Found: It is the responsibility of the Contractor to instruct his employees that all articles of possible personal or monetary value, found by the Contractor’s employees, must immediately be turned in to the COR or Rangers upon the next physical meeting at the contractor’s respective park.
6.12 Other Contracts at the Contract Site: The Government may undertake or award other contracts for additional work and the Contractor shall fully cooperate with such other contractors and Government employees and carefully fit his own work to such additional work as may be directed by the Contracting
Officer. The Contractor shall not commit or permit any act which shall interfere with the performance of work by any other contractor or by Government employees.
7. Safety and Environmental Regulations:
7.1 The Contractor shall follow all safety regulations as set by OSHA, Corps of Engineers Safety Manual EM 385- 1 and project safe clearance procedures. Where conflicts in safety regulations occur, the COR shall designate the applicable regulation to be followed. In accordance with EM 385-1-1, the Contractor shall prepare a Job Safety Activity Hazard Analysis for approval by the COR prior to commencement of work.
7.2 The Contractor shall determine those areas and activities in which possible safety hazards exist during the on- site visit of the John Day-Willow Creek Project and note such information on the Activity Hazard Analysis Form, Attachment 2. When completed, the Contractor shall identify hazards in each phase of services performed, what preventative measure the contractor proposes to take to prevent such accidents and then return to the COR to retain on file.
7.3 The COR and the Project’s Environmental Compliance Coordinator shall approve all cleaning products.
The contractor shall use only environmentally friendly cleaning products. Cleaning product shall remain in original packaging or containers so that all information of the chemicals are readily available. Cleaning products shall not be mixed or transported into other containers.
7.4 Accidents:
7.4.1 The Contractor or the Contractor’s employees shall report any circumstances of needed repair of the facility or unusual soiling of any area, which may affect the performance of the work, and unhealthful or hazardous conditions or any delays or interference with the work caused by the employees to the park rangers and COR.
7.4.2 In the event that an accident or injury occurs to contractor personnel, the contractor shall first notify the park ranger on duty and then notify the COR.
7.4.3 Accident Reports: The Contractor shall make a written report of each separate case of an injury or accident. The report shall include, but not be limited to; location, nature of the injury or accident, authorities notified, and the action taken along with any other pertinent information. The report shall be accompanied by sketches, graphs/drawings, and photographs as needed and forwarded to the COR within 24 hours.
7.5 Security Requirements: The Contractor, before initiating the performance of work, shall provide the COR with a list of all employees who shall perform work under this contract, not later than 7 days prior to training dates. The list shall include the full name, aliases, social security number, and work assignment of each employee. The Contractor shall notify the COR in writing of any addition, deletion or change in work assignment within one day of such change. Upon completion or reassignment individuals are required to return access cards/keys to the designated
COR.
8. Security Requirements:
8.1 AT Level I Training. All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the Contracting Officer, if a COR is not assigned, within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:
https://atlevel1.dtic.mil/at.
8.2 Access and General Protection/Security Policy and Procedures. All Contractor and all associated sub‐contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
8.3 For contractors who do not require CAC, but require access to a DOD facility or installation.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
8.4 Suspicious Activity Reporting Training (iWATCH, CorpsWatch, or See Something, Say Something). The Contractor and all associated sub‐contractors shall brief all employees on the local iWATCH, Corps Watch, or See Something, Say Something program (training standards provided by the requiring activity Anti-Terrorism Officer (ATO)). This local developed training shall be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after contract award.
8.5 For contracts that require OPSEC training. Per AR 530‐1, all new Contractor employees shall complete Level I OPSEC training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. Access to OPSEC training shall be coordinated through the COR.
8.6 Prescreen candidates using E-Verify Program. The Contractor must pre‐screen Candidates using the E‐verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E‐verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
9. Walsh-Healey Public Contracts Act or the McNamara-O'Hara Service Contract Act (SCA) (if applicable):
Every employer performing work covered by the Walsh-Healey Public Contracts Act or the McNamara-O'Hara Service Contract Act (SCA) is required to post a notice of the compensation required (including, for service contracts, any applicable wage determination) in a prominent and accessible location at the worksite where it may be seen by all employees performing on the contract. A copy of the poster is available in two versions at the following DOL website:
http://www.dol.gov/whd/regs/compliance/posters/sca.htm
ANNEX A
PLYMOUTH / PARADISE PARK GATE ATTENDANT SERVICES
The following information shall apply for the 2024-2029 Park Gate Attendant at Plymouth/Paradise Park. There is One (1) Park Attendant position that shall be open for bid. This position requires Two (2) individuals working as a team. This is a non-personal services contract. This firm fixed priced contract is for a Base Year plus Five (5) option year per the Governments discretion.
A.1 Specific Duties: The contractor shall provide all equipment, tools, materials, vehicles, supervision, and other items and services necessary to perform Gate Attendant Services as defined in this Performance Work Statement for the Gate Attendant “B” at Plymouth/Paradise Park. The Contractor shall perform to the standards in the contract and comply with all local, state, and federal regulations during the services performed.
A.1.1 Open the day use gate at 9:00 am and close it at 7:00 pm from April 15th – October 15th.
A.1.2 Duty days are five days on/five days off alternating with Plymouth/Paradise Park Gate Attendant “A”. Gate attendant must remain in the campground as required on duty days.
A.1.3 Hours of entrance booth operation shall be from 0800 to 1900 on Sunday through Thursday, and from 0800 to 2000 on Fridays and Saturdays.
A.1.3.1 The contractor is responsible for notifying a Ranger and the COR if there is a variance in standard work hours due to emergency or unforeseen circumstances.
A.2 Schedule: The Contract shall run from the Date of Award until between the date range of 1 October 2024 to 15 October 2024 for the Base Year. The Contract shall run from 1 February through 31 January for each option year. The work schedule for each year of the contract shall be as shown below:
CLIN 0001: Base year - 2024 Plymouth/Paradise Park work period ranging from 15 April
2024 through 15 October 2024, including two (2) training days TBD; minimum of 86 days to a maximum of 94 days based on official park opening and closing dates/schedule.
CLIN 1001: 1st Option Year – 2025 Plymouth/Paradise Park work period ranging from 15
April 2025 through 15 October 2025; minimum of 86 days to a maximum of 94 days based on official park opening and closing dates/schedule.
CLIN 2001: 2nd Option Year - 2026 Plymouth/Paradise Park “B” work period ranging from 15 April 2026 through 15 October 2026; minimum of 86 days to a maximum of 94 days based on official park opening and closing dates/schedule.
CLIN 3001: 3rd Option Year - 2027 Plymouth/Paradise Park “B” work period ranging from
15 April 2027 through 15 October 2027; minimum of 86 days to a maximum of 94 days based
CLIN 4001: 4th Option Year - 2028 Plymouth/Paradise Park “B” work period ranging from
15 April 2028 through 15 October 2028; minimum of 86 days to a maximum of 94 days based
A.3 List of Attachments: To be used per Performance Work Statement (PWS), Section 6.4 and 7.2 (to be provided after contract award).
Attachment 1: Contract Discrepancy Report
Attachment 2: Activity Hazard Analysis Attachment 3: Repair Request Form