About this file

This document is a Performance Work Statement (PWS) for a service contract to un-install and re-install two EOS M100 and M290 metal additive manufacturing machines that are being relocated to a new facility at Aberdeen Proving Grounds (APG). The objective is to have the contractor provide labor, documentation, supplies, tools, and calibration services to prepare the government-owned machines for moving and then re-install and re-calibrate them at the new location per the original equipment manufacturer's specifications. The government will be responsible for packing, transporting, and confirming the new facility is ready to accommodate the re-installation before contacting the contractor. The contract requires compliance with access and security requirements for the APG installation. The PWS is attached to Solicitation Number W911QX24Q0133, issued by the Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground, for a service contract to support this machine relocation effort.

View the file

Other files

File Type Posted
Provisions and Clauses_Phillips.doc DOC document
Combination Synopsis-Solicitation for Commercial Purchases_Phillips.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement (PWS) Phillips Service Agreement for Moving EOS Machines 4/25/2024

C.1 Background Metal additive manufacturing (AM) enables complex manufacturing and novel materials research for the Army. The metal AM team within the Manufacturing Sciences and Technology Branch (MSTB) within the Science of Extreme Materials Division (SEMD) is moving all metal AM equipment to a new facility to establish a metal AM center of excellence at Aberdeen Proving Grounds. There is a need to establish a contract with Phillips Inc. to move the EOS M100 and M290 machines to the new facility for research to support DEVCOM Army Research Laboratory mission. This includes un-installing and preparations for moving the machines, re-installing, and re-calibrating the machines.

C.2 Objective The Contractor shall provide all labor, documentation, schematics, repair and maintenance supplies, tools, calibration equipment, to visit to prepare the Government-owned EOS M100 and M290 machines to move in accordance with the Original Equipment Manufacturer (OEM) specifications as well as install at new location within OEM specifications. The objective of this service contract is to provide technical support in un-installing and reinstalling the machines and on-site calibration, of the Government-owned EOS M100 and M290, and ensure all of the components associated with the operation of the EOS machines, including the in-situ monitoring capabilities are in working condition.

The work involved in this service agreement is to maintain the Government-owned EOS Machines at APG in working condition. If the EOS machines are found to be in an inoperable state after the move, the contractor shall make necessary repairs to the equipment so that it is restored to operable condition.

C.3 Requirement The contractor shall un-install both EOS M100 and M290 machines in buildings B4600 and L1032 at the Governments scheduled date once a mutually agreeable date is determined. The Government is responsible for the packing and transport of both machines to their new location in building B463 at Aberdeen APG. The Government will then contact EOS via MyEOS (online service portal) when the new facility is prepared to accommodate re-installation of the machines and the Government has provided EOS with a new, signed Site Readiness form prior to scheduling re-installation.

C.4 AT-OPSEC

Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Arm controlled installation, facility, or area. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identify Verification of contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility ort installation change, the Government may require changes in contractor security matters or processes.

C.5 Distribution Statement A Contractor format for the above listed reports is acceptable. All reports/documents must be marked with the following distribution statement:

DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.