This performance work statement outlines requirements for replacing a 4,000 gallon water tank on a fire truck for the Department of the Army Massachusetts Army National Guard. The contractor shall remove the existing polyethylene tank, transport the vehicle to their facility, install a new 4,000 gallon polyethylene tank that meets NFPA specifications with crosswise and longitudinal baffles, cradle, and all original equipment, paint to match vehicle color, test per NFPA 1911 guidelines, and transport the vehicle back. The contractor must provide all labor, equipment, materials, and transportation. The period of performance will be determined based on quoted delivery date. Work must be completed between 0730-1630 Monday through Friday, excluding federal holidays, at the contractor's facility.
The contractor is responsible for quality control and meeting performance standards outlined in the technical exhibit such as fully replacing the tank to specifications. The government will provide quality assurance oversight. The solicitation number listed is W50S8123Q0008 for refurbishing a fire truck tank for the Department of the Army Massachusetts Army National Guard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| IMG_20230.JPG | JPG image | |
| RFQ W50S8123Q0008 Fire Truck Repair.docx | DOCX document | |
| Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ver. June 2021
PERFORMANCE WORK STATEMENT (PWS)
P-26 12L00010 4,000 Gallon Tank Replacement 10 August 2023
1.0 General:
1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform P-26 12L00010 4,000 Gallon Tank Replacement Services, as defined in this PWS.
1.1.1 Objectives: Contractor to remove and dispose of existing tank then replace with a similar tank that meets or exceeds any and all original equipment manufacturers performance requirements as well as current NFPA specifications.
1.2 Background: Existing polyethylene water tank interior baffles/structural members have broken loose causing a loss in structural integrity and severe deformation of the overall exterior of the tank. Currently, the tank is on a 2011 KME 4,000 Gallon Tanker, International 7400 chassis. VIN #:
1HTWGAZT1CJ639207
1.3 Period of Performance (PoP): TBD based on quoted delivery date.
1.4 General Information:
1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0730-1630) on Monday through Friday, except on recognized US holidays. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.
1.4.1.1 Telework: Reserved
1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented.
Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.
1.4.2 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days:
1.4.2.1 New Year’s Day: January 1st
1.4.2.2 Martin Luther King, Jr.’s Birthday
1.4.2.3 President’s Day
1.4.2.4 Memorial Day
1.4.2.5 Juneteenth National Independence Day: June 19th
1.4.2.6 Independence Day: July 4th
1.4.2.7 Labor Day
1.4.2.8 Columbus Day
1.4.2.9 Veteran’s Day: November 11th
1.4.2.10 Thanksgiving Day
1.4.2.11 Christmas Day: December 25th
1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS).
1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).
1.4.5 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
2. The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver s license, current vehicle registration, valid vehicle insurance certificate, and [insert any additional requirements to comply with local security procedures] to obtain a vehicle pass.
6. Failure to comply with these requirements may result in withholding of final payment.
1.4.5.1. For Contractors Requiring Common Access Card (CAC): Reserved
1.4.5.2 For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Air Force Instruction (AFI) 10-245, AFI 31-101 and Air Force Manual (AFMAN) 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative)
1.4.5.3 Reserved
1.4.5.4 Reserved
1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.5.6 Reserved
1.4.5.7 Reserved
1.4.5.8 Reserved
1.4.5.9 Reserved
1.4.5.10 Reserved
1.4.5.11 Reserved
1.4.5.12 Reserved
1.4.5.13 Reserved
1.4.5.14 Reserved
1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.6.1 Key Control. NOTE: All references to keys include key cards. The contractor shall establish and implement methods of ensuring that no keys/key cards issued by the Government are lost or misplaced or are used by unauthorized persons. No keys issued by the Government shall be duplicated. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The contractor shall include procedures covering key control in the QCP.
1.4.6.1.1 The contractor shall immediately report any occurrences of lost or duplicated keys/key cards to the COR.
1.4.6.1.2 In the event keys, other than master keys, are lost or duplicated, the contractor shall, upon direction by the KO, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the Government replaces or re-keys the locks, the Government will deduct the total cost of lock replacement or re-keying from the monthly payment due the contractor. In the event a master key is lost or duplicated, the Government will replace all locks and keys for that system, and will deduct the total cost from the monthly payment due the contractor.
1.4.6.1.3 The contactor shall prohibit the use of the Government issued keys/key cards by any persons other than the contractor’s employees. The contractor shall prohibit the opening of locked areas by contractor employees to permit entrance of persons other than contactor employees engaged in the performance of services in those areas, or personnel authorized entrance by the KO.
1.4.7 Reserved
1.4.8 Reserved
1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the KO, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 Reserved
1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.
1.4.12 Reserved
1.4.13 Reserved
1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.4.15 Reserved
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.
2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.2 Acronyms:
AEI Army Enterprise Infostructure AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CM Contract Manager COR Contracting Officer Representative DA Department of the Army DD254 Department of Defense Contract Security Classification Specification DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense DSCA Defense Counterintelligence and Security Agency FAR Federal Acquisition Regulation
GFP/M/E/S Government Furnished Property/Material/Equipment/Services HQDA Headquarters, Department of the Army HSPD Homeland Security Presidential Directive IA Information Assurance IS Information System(s) KO Contracting Officer NGB National Guard Bureau OCI Organizational Conflict of Interest PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SCR Service Contract Reporting SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:
3.1 Property: Not applicable
3.2 Materials: Not applicable
3.3 Equipment: Not applicable
3.4 Services: Not applicable
3.5 Utilities: Not applicable
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E)
4.1 General: The contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.
5.0 Requirements: The contractor shall:
5.1 Remove and disposal of existing tank, existing tank is polyethylene.
5.2 Install new, 4,000 Gallon tank capacity, polyethylene material, with all necessary crosswise & longitudinal baffles, in order to meet NFPA 1901 specifications for a water tank truck.
5.2.1 Ensure tank is installed per manufacture’s installation specifications.
5.2.2 Remove and replace the existing cradle, ensuring there is an isolator between the newly installed cradle and the newly installed tank, in accordance with the manufacturer’s instructions.
5.2.3 Ensure to have a fireman’s friend installed in the tank at fill locations.
5.2.4 Installation to meet NFPA requirements.
5.2.5 New tank is to have all the same features of the existing tank to include but not limited to (Attachment A: KME Operation and Warranty Manual provided for reference only):
Fill tower with hinged lid 6.0” overflow vent pipe with screen 2.0” overflow vent pipe extension 1.5” pass through pipe 2.5” FNPT tank fast fill with diffuser 4.0” FNPT tank suction Suction/tank fill pipe .75” tapped FNPT Tank gauge port 10” enhanced dump mount Dump Chute
Dump house Sump with 3.0” FNPT Clean out Ladder Sleeve, through tank Flush Tank Lid Hose Bed Walls with wire channel/support Eye bolt lifting system Internal tank mount
5.2.6 New tank is to tie into existing pumps, gauges, water level indication, and remote/manual controls for operation of the water tank. Vehicle and water tank shall be fully functional upon completion and meet all NFPA, federal laws and regulations.
5.2.7 Tank to be painted to match existing chassis color, red. Any damage to truck paint due to installation of the new tank, that truck is painted to match color, red.
5.3 All work and service to meet the Pump Test Per NFPA 1911 Apparatus Guidelines of Latest Edition 2017.
5.3.1 Provide a minimum of two (2) day notice prior to testing of the truck, in order to provide an opportunity for the subject matter expert to be present, if possible.
5.3.2 Submit documentation recording test and test results prior to vehicle leaving work site location.
5.4 The contractor shall transport the vehicle to their facility to complete the work and back to the location that the vehicle was picked up at before Government acceptance.
5.5 Provide manufacture standard warranty.
6.0 Applicable Publications: Publications applicable to this PWS are listed below:
Publication (Chapter/Page)
Date of Publication
Mandatory or
Advisory
Website
Federal Acquisition Regulation https://www.acquisition.gov/?q=browsefar Defense Federal Acquisition
Regulation Supplement http://www.acq.osd.mil/dpap/dars/dfarspgi/current/i ndex.html or https://www.acquisition.gov/dfars Joint Travel Regulation (JTR) https://www.defensetravel.dod.mil/site/travelreg.cf m DoDM 1000.13-M-V1
DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b)
01/23/2014 (Change 1:
07/28/2020) http://www.esd.whs.mil/Directives/issuances/dodm
Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors
(paragraph 9)
August 2013 http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.20 1-2.pdf
DoDM 5200.2 Procedures for the DoD Personnel Security Program
(PSP)
04/03/2017 https://www.esd.whs.mil/Directives/issuances/dodm
DoDI 5200.46 DoD Investigative and Adjudicative Guidance for Issuing the Common
Access Card (CAC)
09/09/14 (Change 1:
05/04/2018) https://www.esd.whs.mil/Directives/issuances/dodi/
Homeland Security Presidential Directive (HSPD)-12
Policy for a Common Identification Standard for Federal Employees and
Contractors
08/27/2004 https://www.dhs.gov/homeland-security-presidential-directive-12
DoDI 5400.11 Department of Defense Privacy and
Civil Liberties Programs
01/29/2019 https://www.esd.whs.mil/Directives/issuances/dodi/
DoD 5400.11-R Department of Defense Privacy
Program
05/14/2007 https://www.esd.whs.mil/Directives/issuances/dodm
DoDD 8140.01
Cyberspace Workforce Management
10/05/2020 https://www.esd.whs.mil/Directives/issuances/dodd/
DoD 8570.01-M
Information Assurance Workforce Improvement Program
12/19/2005 (Change 4:
11/10/2015) https://www.esd.whs.mil/Directives/issuances/dodm
DoD 5220.22-M National Industrial Security Program
Operating Manual (NISPOM)
02/28/2006 (Change 2:
05/18/2016) https://www.esd.whs.mil/Directives/issuances/dodm
AFI 10-245
Antiterrorism
03/28/2013 (Certified current 03/30/2017) https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&seri es=-1&modID=449&tabID=131
AFI 31-101
Security Forces Standards and
Procedures
08/18/2020 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&seri es=-1&modID=449&tabID=131
AFMAN 31-113
Security Forces Standards and
Procedures
03/05/2013 Change 1:
12/02/2015 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&seri es=-1&modID=449&tabID=131
AFPD 17-1
Information Dominance Governance and Management
04/12/2016 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&seri es=-1&modID=449&tabID=131
AFMAN 17-1301
Computer Security (COMPUSEC) 02/12/2020 https://www.e-publishing.af.mil/Product-
Index/#/?view=pubs&orgID=10141&catID=1&seri es=-1&modID=449&tabID=131
AFI 10-701
Operations Security
7/24/2019 (Change 1:
06/09/2020) https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&seri es=-1&modID=449&tabID=131
TECHNICAL EXHIBIT 1
Performance Requirements Summary (PRS)
This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
Performance Objective
Performance Standard Acceptable Quality Levels (AQL)
Surveillance Method / By Whom
The contractor shall replace tank per paragraph 5.0
The contractor shall provide 100% replacement of the
4,000 gallon tank and ensure it is fully operational.
100% completion. COR – 100% inspection