This document is a Performance Work Statement (PWS) for the FY24 Lookout Point Powerhouse & Dam Asbestos Abatement project. The PWS details the requirements for the complete removal of asbestos-containing thermal system insulation (TSI) from various cooling water piping systems within the Lookout Point Powerhouse. The primary CLIN requires the removal of approximately 165 linear feet of TSI, with four optional CLINs for additional piping systems ranging from 33 to 42 linear feet. The contractor must comply with all local, state, and federal regulations during the asbestos abatement work. The work is subject to 100% inspection by the Contracting Officer's Representative, and the contractor is responsible for developing a Quality Control Plan. The period of performance is expected to be 60 days after contract award. This PWS is associated with the federal contract opportunity W9127N24Q0102, a 100% set-aside for Woman Owned Small Businesses under NAICS Code 562910 - Remediation Services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
FY24 LOOKOUT POINT POWERHOUSE & DAM ASBESTOS ABATEMENT
1.0 GENERAL STATEMENT:
This requirement is for OSHA “Class I asbestos work” pertaining to the complete removal of Asbestos Containing Building Material (ACBM) Thermal System Insulation (TSI) within a regulated work area at Lookout Point (LOP) Powerhouse & Dam. Access to the workspace is limited and at the pipes being abated are located anywhere from zero to 15 feet above floor level within the LOP Powerhouse. Contract Line Item Number (CLIN) 0001 is the primary work to be performed under this contract with optional CLINs 1001-1004 providing to opportunity to execute additional work should funding become available.
CLIN 0001. HVAC Room Cooling Water Piping. Remove all ACBM TSI from the identified section of water pipes, approximately 165 LF combined. See attached drawings and pictures.
Optional CLIN 1001. Station Service Air Compressor Room Cooling Water Piping.
Remove all ACBM TSI from the identified pipes, approximately 41 LF.
Optional CLIN 1002. Main Unit 1 Cooling Water Piping. Remove all ACBM TSI from the identified pipes, approximately 34 LF.
Optional CLIN 1003. Main Unit 2 Cooling Water Piping. Remove all ACBM TSI from the identified pipes, approximately 42 LF.
Optional CLIN 1004. Main Unit 3 Cooling Water Piping. Remove all ACBM TSI from the identified pipes, approximately 33 LF.
Contractor shall complete a site visit prior to quote submission. Access to work site will be from 0630-1700 hrs, Monday – Thursday. Personnel background investigation and full escort is required while inside the powerhouse. Contractor and all associated sub-contractors’ employees shall comply with background adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), and applicable facility access/local security policies and procedures via a service provider of choice. Submit results of background checks via official transmittal for review/approval to the COR and Project Security Office, NLT 30 calendar days prior to site mobilization. Work will be performed at the US Army Corps of Engineers, Willamette Valley Project, Lookout Point Dam, 40386 West Boundary Rd. Lowell, OR 97452
Building Occupancy: Approximately 15 powerhouse maintenance personnel report to work at the LOP Powerhouse from 0630-1700 hrs, Monday – Thursday. There are also as many as 4 control room operators present in the powerhouse 24 hours a day, 7 days a week schedule with intermittent requirement to access the rest of the facility in performance of their duties.
Other than the control room operator, the rest of the workforce is flexible in relocating to other areas of the powerhouse during abatement work. The Contractor will prominently post notifications at all building entry points and must also use signs, barriers, enclosures, etc. to restrict access to the work areas.
The expected period of performance shall be 60 days after contract award.
2.0 DEFINITIONS:
Throughout this PWS terms are defined as follows:
Acceptable Quality Level (AQL): Acceptable Quality Level equals the performance standards listed in Section 6.0. The Contractor must re-perform all unsatisfactory work unless excused by the COR.
Contracting Officer (KO): The Government employee who is authorized to enter into, administer, and/or terminate contracts and make related determinations and findings.
Contracting Officers Representative (COR): An individual designated in accordance with subsection 201.602-2 of the Defense Federal Acquisition Regulation Supplement and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract.
Contract Discrepancy Report (CDR): A written record of unsatisfactory performance by the Contractor as observed by the COR.
3.0 THE GOVERNMENT WILL FURNISH:
The Government shall furnish, without cost to the Contractor, the following items to be used only in connection with the performance of the work:
a. USACE responsible for ensuring equipment is under adequate hazardous energy control in accordance with the CENWP-OD Standing Safety Procedure 385-1.
b. Adequate access to the work zone including access to necessary water/electric.
c. Schedule a time to meet contractor on-site to review scope of work and associated drawings.
4.0 THE CONTRACTOR SHALL FURNISH:
The contractor shall provide all personnel, equipment, and materials to abate asbestos in accordance with this Performance Work Statement (PWS). The Contractor shall perform to the standards in the contract and comply with all Local, State, and Federal regulations during the services performed.
a. The Contractor shall furnish all labor, equipment, and materials necessary to properly abate asbestos within the defined primary and option areas at LOP.
b. The Contractor shall insure that all employees can demonstrate adequate knowledge of tools, equipment, instrumentation, supplies and techniques necessary to competently perform the work.
c. Contractor shall supply all necessary training and inspection records for personnel and equipment that will be used during the service period. This includes certificates of completion for the First Aid/CPR and Fall Protection qualification.
Contractor to supply their personnel with all applicable Personal Protective Equipment
(PPE).
Completed Asbestos Survey, photograph, and Chain of Custody Form Contractor generated hazardous waste from this work are the sole responsibility of the
Contractor to manage and dispose of in compliance with all federal, state and local regulatory requirements.
Contractor shall provide completed ASN4 Asbestos Waste Shipment Reporting Form address to Bonara Tan 211 E. 7th St., Suite 480, Eugene OR 97401.
5.0 PERFORMANCE STANDARDS AND REQUIREMENTS.
5.1 Task 1 –Primary: (HVAC Room Cooling Water Piping): remove approximately 165 LF of asbestos-containing thermal system insulation from the identified pipes. It covers 2 horizontal water pipes of various sizes running from North to South, and 2 running West to East. Access to the removal area is limited and above floor.
a. Assess work access restrictions during pre-bid visit and determine access and containment methods with Project Environmental Health and Safety and Contracting Officer Representative.
b. Provide scaffolding or determine access system for work areas. Fall protection requirements will be met in accordance with EM 385-1-1 (2024) and addressed in the Accident Prevention Plan (01 35 29.1028).
c. Usage of enclosures or glove bags is required.
d. File the appropriate notifications if necessary to Oregon Department of
Environmental Quality at least 10 days prior to commencement of work (01 57
20.00 28 Part 1.2.2).
e. Conduct periodic air monitoring as required to ensure the safety of employees.
f. Decontaminate all work sites after asbestos removal.
g. Dispose of Thermal System Insulation, debris, and other contaminated materials per
Federal and Oregon State regulations.
5.2 Task 2 – Option 1 (SS Air Room Cooling Water Piping): remove approximately 41 LF of asbestos-containing thermal system insulation from the identified pipes. It covers 2 horizontal pipes of 3/4 inch and 1 1/4 inch.
a. Assess work access restrictions during pre-bid visit and determine access and containment methods with Project Environmental Health and Safety and Contracting Officer Representative.
b. Provide scaffolding or determine access system for work areas. Fall protection requirements will be met in accordance with EM 385-1-1 (2024) and addressed in the Accident Prevention Plan (01 35 29.1028).
c. Usage of enclosures or glove bags is required.
d. File the appropriate notifications if necessary to Oregon Department of
Environmental Quality at least 10 days prior to commencement of work (01 57
20.00 28 Part 1.2.2).
e. Conduct periodic air monitoring as required to ensure the safety of employees.
f. Decontaminate all work sites after asbestos removal.
g. Dispose of Thermal System Insulation, debris, and other contaminated materials per
5.3 Task 3 – Option 2 (MU1 Cooling Water Piping): remove approximately 34 LF of asbestos-containing thermal system insulation from the identified pipes. Access to the removal area is limited and above floor.
a. Provide scaffolding or determine access system for work areas. Fall protection requirements will be met in accordance with EM 385-1-1 (2024) and addressed in the Accident Prevention Plan (01 35 29.1028).
b. Usage of enclosures or glove bags is required.
c. File the appropriate notifications if necessary to Oregon Department of
Environmental Quality at least 10 days prior to commencement of work (01 57
20.00 28 Part 1.2.2).
d. Conduct periodic air monitoring as required to ensure the safety of employees.
e. Decontaminate all work sites after asbestos removal.
f. Dispose of Thermal System Insulation, debris, and other contaminated materials per
5.4 Task 4 – Option 3 (MU2 Cooling Water Piping): remove approximately 42 LF of asbestos containing thermal system insulation from the identified pipes. Access to the removal area is limited and above floor.
a. Provide scaffolding or determine access system for work areas. Fall protection requirements will be met in accordance with EM 385-1-1 (2024) and addressed in the Accident Prevention Plan (01 35 29.1028).
b. Usage of enclosures or glove bags is required.
c. File the appropriate notifications if necessary to Oregon Department of
Environmental Quality at least 10 days prior to commencement of work (01 57
20.00 28 Part 1.2.2).
d. Conduct periodic air monitoring as required to ensure the safety of employees.
e. Decontaminate all work sites subsequent to asbestos removal.
f. Dispose of Thermal System Insulation, debris and other contaminated materials per Federal and Oregon State regulations.
5.5 Task 5 – Option 4 (MU3 Cooling Water Piping): remove approximately 33 LF of asbestos-containing thermal system insulation from the identified pipes. Access to the removal area is limited and above floor.
a. Provide scaffolding or determine access system for work areas. Fall protection requirements will be met in accordance with EM 385-1-1 (2024) and addressed in the Accident Prevention Plan (01 35 29.1028).
b. Usage of enclosures or glove bags is required.
c. File the appropriate notifications if necessary to Oregon Department of
Environmental Quality at least 10 days prior to commencement of work (01 57
20.00 28 Part 1.2.2).
d. Conduct periodic air monitoring as required to ensure the safety of employees.
Decontaminate all work sites after asbestos removal.
e. Dispose of Thermal System Insulation, debris, and other contaminated materials per
6.0 PERFORMANCE REQUIREMENTS SUMMARY:
6.1 To ensure that the Government receives the services for which it contracted, the
Government will only pay for services received. The Performance Requirements Summary (PRS) determines if the Contractor meets the performance standards of the contract, as well as provides guidelines for how and when surveillance will be performed. It ensures timeliness, effectiveness and that the Contractor is delivering the results specified in the contract. Government contract quality assurance will be performed per the PRS surveillance schedule.
6.2 Performance Requirements Summary Table. These are the criteria against which the performance will be evaluated. Work shall be considered not to have been performed when any one of the following conditions exists in accordance with the Quality Assurance Surveillance Plan (QASP).
PERFORMANCE REQUIREMENTS SUMMARY
Required Services
Performance Standards Acceptable
Quality Levels
Surveillan ce
Validated Complain ts
5.1 – 5.5 Tasks
Compliance with requirements to properly Abate identified Asbestos
Zero deviation from PWS.
100% Inspection
1 per contract
6.3 Surveillance. 100% inspections by the COR will serve as the surveillance methods.
If the COR discovers deficiencies and/or receives complaints, the COR will alert them to the contractor for correction.
6.4 Quality Control. The Contractor, not the government, is responsible for quality control actions necessary to meet the quality standards set forth by the contract. The contractor shall develop and submit a Quality Control Plan (QCP) for Government approval within ten (10) calendar days after award. Once accepted, the QCP will be incorporated into the QASP. The QASP is not a contractual instrument and may be changed at the COR’s discretion. The contractor shall use the QASP to guide and document the implementation of the required management and quality control actions to achieve the specified results. The Government reserves the right under the Contract Terms and Conditions--Commercial Items (FAR 52.212-4) to inspect and test the services called for by the Task Order, to the extent practicable at all times and places during the term of the Task Order. The Government will reject non-conforming services.
6.5 Unacceptable Performance. When performance is determined unacceptable, as defined in the Performance Requirements Summary, the COR will inform the contractor that performance is unacceptable and provide written documentation by use of the Form DD 2772, Contract Discrepancy Report. By initialing and dating the form, the contractor is only acknowledging notification of unacceptable performance.
Disputes in surveillance should be referred to the Contracting Officer.
The COR will notify the Contracting Officer of unacceptable performance. If any of the services do not conform to contract requirements, the Government may require the contractor to perform the services again in conformity with contract requirements, at no increase in contract amount. When the defect(s) in services cannot be corrected by re-performance, the Government may:
a. Require the Contractor to take necessary action to ensure future performance conforms to contract requirements.
b. Reduce the contract price to reflect the reduced value of the services performed.
c. If the Contractor fails to promptly re-perform the services, or to take the necessary action to ensure future performance in conformity with contract requirements, the Government may:
i. By contract or otherwise, perform the services and charge to the Contractor any cost incurred by the Government that is directly related to the performance of such service;
ii. Issue Cure Notice;
iii. Terminate the contract for Government convenience; and / or
iv. Terminate the contract for Cause.
6.6 Correction of Non-Performance of Work. Contractor shall employ an adequate quantity of personnel to ensure that any services found to be not in compliance and therefore not acceptable, shall be made acceptable by the performance or re-performance of the work, where such re-performance is possible, during the first business day after non-compliance has been observed by or reported to and verified by the COR.
7.0 GENERAL.
7.1 Security.
a. General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime
Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)).
Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
b. Antiterrorism (AT) Level I training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).
c. Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center- Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.
d. Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
e. Escorting in classified and/or sensitive areas: In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.
f. Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
7.2 Contract Changes. Changes in scope, time, or deliverables can only be authorized by the Contracting Officer. The contractor shall notify the Contracting Officer immediately if they have received direction to perform work outside the scope of the contract. Changes in scope will be negotiated and a written modification issued, before proceeding with the work.
7.3 Points of Contact.
Contracting Officer:
Contracting Officer’s Representative: Ken Duncan, 503-808-4323, Kenneth.d.duncan@usace.army.mil.
Contract Specialist:
Technical POC, Government POC, and Willamette Valley Representative is Jake Moore who will coordinate site access, security and safety requirements: Jake
Moore, (541) 349-3066, jacob.s.moore@usace.army.mil.
Willamette Valley Project (WVP) Safety POC is Bonara, Tan: 541-684-4312 (o);
Cell-541-844-6667 (c); Bonara.tan@usace.army.mil.
Mail all correspondence to EHS, 211 E. 7th Ave, Suite 480, Eugene, OR 97401 or Bonara.tan@usace.army.mil.
7.4 Invoice Submittals. Invoice(s) shall be prepared in accordance with FAR clause 52.212-4(g) and submitted electronically via email to:
Submit an Electronic PDF Invoice to the USACE Finance Center via email address:
CEFC-G2invoices@usace.army.mil
Electronic Copy to:
Willamette Valley Project: CENWP-ODV-COR@usace.army.mil POC: Quenton Chocktoot, (541) 521-0275, quenton.p.chocktoot@usace.army.mil
For Invoice receipt verification or for a vendor's Payment problem, the vendor may contact the USACE Finance Center at Phone Number (901) 873-9077.
7.5 Walsh-Healey Public Contracts Act or the McNamara-O'Hara Service Contract
Act (SCA). Every employer performing work covered by the Walsh-Healey Public Contracts Act or the McNamara-O'Hara Service Contract Act (SCA) is required to post a notice of the compensation required (including, for service contracts, any applicable wage determination) in a prominent and accessible location at the worksite where it may be seen by all employees performing on the contract. A copy of the poster is available in two versions at the following DOL website: http://www.dol.gov/whd/regs/compliance/posters/sca.htm. The rest of the content is subjective to each locations needs.
7.6 Veterans Employment Emphasis for U.S. Army Corps of Engineers
Contracts. USACE contractors and sub-contractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE Contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE Contractors in their outreach efforts:
Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance at http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act at http://benefits.va.gov/vow
Army Wounded Warrior Program at http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation – Hiring Our Heroes:
http://www.hiringourheroes.org/
Guide to Hiring Veterans:
www.whitehouse.gov/sites/default/files/docs/white_house_business_council_ -_guide_to_hiring_veterans_0.pdf
7.7 Work Scheduling. The Contractor is not required to perform services on the following recognized Federal holidays: New Year’s Day, Labor Day, Martin Luther King Day, Columbus Day, President’s Day, Thanksgiving Day, Independence Day, Christmas Day, Memorial Day, and Veteran’s Day..
8.0 FORMS.
Contractor Discrepancy Form: