PWS Irrigation Central Controller-FINAL.pdf
PDF 824 KB Posted
- Attached to
- ANC Irrigation Comptroller Upgrade Federal contract opportunity
- Solicitation number
- PANMCC-21-P-0000-018814
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ANC Irrgiation upgrade Sources Sought.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
Irrigation Central Controller Upgrades Arlington National Cemetery
1. GENERAL INFORMATION:
1.1 Description of Service: This requirement is a non-personal services contract in which the contractor shall provide all personnel, materials, equipment, supervision, and maintenance necessary to upgrade the existing irrigation system controllers to provide cemetery-wide, remote operation capability at Arlington National Cemetery (ANC) located in Arlington, Virginia. The
Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such service providers shall be accountable solely to the
Contractor who, in turn, is responsible to the Government.
1.2 Background: ANC is our nation’s most sacred shrine and the final resting place for our most revered military and political leaders. ANC receives four to six million visitors per year -including visits from the President of the United States, other heads of state, family members of the deceased, and millions of tourists from around the world. Approximately 6,000 funerals are conducted yearly – in addition to over 2,000 other ceremonies such as commemorations, wreath ceremonies, and head-of-state visits. These ceremonies and funerals often receive the intense focus of the press and other media. Due to the special significance and public attention that the cemetery receives, strict adherence to these specifications is essential. Failure to meet specifications will have a negative impact on our nation’s image.
1.3 Objective: The basic service objective is to upgrade 12 existing irrigation controllers to
Hunter ACC2 controllers with communication modules, and to install communication modules on 2 current ACC2 controllers to provide central control capability via the Hunter
Centralus operating system. The contractor shall test all systems for functionality and warranty all work for a period of 1 year following final acceptance. The contractor shall ensure complete functionality, to include electrical and communications for all systems. A detailed and 100% accurate map of all irrigation zones shall be provided at the end of the contract period.
1.4 Scope Of Work: The Contractor shall provide all labor, equipment, materials, and supervision of its employees to replace all indicated controllers with new Hunter ACC2 irrigation controllers to match the current wiring type for each system (conventional or 2-wire).
Controllers shall be installed in the same location and footprint of the existing controllers. The appropriate communications modules and antennae for each controller shall be installed in a professional and weatherproof manner, to allow communication with each system via the
Hunter Centralus operating system. The modification of existing irrigation systems is for the following sites within ANC; replace controller at Kennedy Gravesites (section 45), Taft
Gravesite (section 30), Tomb of the Unknown Soldier/Amphitheater, Coast Guard Memorial, Facility Maintenance Complex, three (3) systems at Columbaria 1-9, Millennium Area
Columbaria 10-13, Administration Building, 110 Gate, and Receiving Vault (section13). Install cellular communication modules for two (2) existing Hunter ACC2 controllers at Memorial
Avenue. (See Technical Exhibit 1: Controller Map).
The contractor shall test and troubleshoot all electrical field components, including but not limited to valves, wire connections, and communications, for proper function. The plans and specifications are intended to include everything obviously requisite and necessary for the proper installation of the work whether each necessary item is mentioned herein or not. Include all labor, overhead, materials, licensing and fees, and profit for any and all tasks associated with the installation of this project. As-programmed zone maps will be provided at the end of the project.
1.5 Period of Performance: The contract requirements shall be completed within 60 days of award.
1.6 General Information:
1.7 Quality Control: The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.
After acceptance of the quality control plan, the Contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system. Quality Control Plan shall be submitted with the Contractor’s proposal.
1.8 Quality Assurance: The Government will monitor the Contractor’s performance under this contract using the Quality Assurance Surveillance Plan (QASP). All work performed under this contract will be subject to inspection at all times by the Government.
1.9 Progress Meetings: The Contracting Officer may require the Site Manager to meet with the
Contracting Officer, Contracting Officer Representative (COR), and other Government personnel as deemed necessary. Written minutes of such meetings may be recorded by the
Government and signed by the Contractor and the Contracting Officer or COR and distributed within five (5) workdays after the meeting. The Contractor may request a meeting with the
Contracting Officer or COR when the Contractor believes such a meeting is necessary. Written minutes of such meetings may be recorded by the Contractor and signed by the Site Manager and the Contracting Officer or COR and distributed within five (5) workdays after the meeting.
In either case, if the Contractor does not concur with any portion of the minutes, recorded by the
Government or the Contractor, such non-concurrence shall be provided in writing to the
Contracting Officer within two (2) calendar days following receipt of the minutes.
1.10 Hours of Operation: The Contractor shall perform work during the hours of 6:30 AM –
4:00 PM Monday through Friday at ANC. Funerals and ceremonies occur regardless of weather conditions. The Contractor is responsible for obtaining access to all work areas during hours
ANC is open to the public. Earlier or later hours are only authorized, through exception, by the COR.
1.11 Recognized Federal Holidays: The Contractor is not required to work on the holidays listed below. Holidays occurring on weekends will be observed as directed by the published
Army calendar.
New Year’s Day 1 st
Day of January
Martin Luther King Jr.’s Birthday 3rd Monday in January
President’s Day 3rd Monday in February
Memorial Day Last Monday in May
Independence Day 4th of July
Labor Day 1st Monday in September
Columbus Day 2nd Monday in October
Veteran’s Day 11 th of November Thanksgiving Day 4th Thursday in November
Christmas Day 25 th of December
Inauguration Day As Applicable
1.12 Interface with Government Operation: Performance of work by Contractor personnel under the terms of this contract shall not interfere with regularly scheduled Government operational activities.
1.13 Place of Performance: The work to be performed under this contract will be performed at
ANC.
1.14 Contract Type: The Government will award a Firm Fixed Price Contract.
2.0 SECURITY REQUIREMENTS:
2 . 1 Contractor personnel or any representative of the Contractor entering ANC shall abide by all security rules and regulations. Contractor will coordinate with the ANC security office to ensure all Contractor employees have received the appropriate security background checks.
2 . 2 The Contractor is solely responsible for processing employees through the Department of
Homeland Security e-Verify system and should consult with that agency for any questions.
Contractor will receive additional security guidance upon award of contract.
2.3 The Contractor shall carry passes issued by ANC for all vehicles entering the Cemetery, whether company-owned or employee-owned private vehicles. The Contractor shall maintain a current list of all vehicles and individuals issued such passes.
2.4 The Contractor shall ensure all names and social security numbers or Alien Registration
Numbers of Contractor personnel performing under this contract are provided to ANC security personnel within 5 days of contract award. The ANC security office will perform a criminal records check on all proposed contractor employees and provide an approval or disapproval to the contractor within 7 business days. After contract award, the Contractor shall provide the names and social security numbers or Alien Registration Numbers of new/replacement personnel to the ANC security office for approval prior to the proposed new/replacement hire performing on the contract. Changes of the Contractor personnel list shall be submitted within 24 hours of the change taking place.
2 . 5 All Contractor employees shall have on them, at all times, positive, photographic identification.
2.6 The Contractor shall safeguard all Government property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.
2.7 Search and Seizure: Contractor personnel and property shall be subject to search and seizure upon entering the confines of ANC and upon leaving the confines of ANC.
2.8 Gate Access: The Contractor shall establish and implement methods of ensuring that all gate access codes are not revealed to unauthorized persons. The Contractor shall notify the COR when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the Contractor’s Quality Control Plan.
2.9 Key/Lock Control and Reporting: The Contractor shall be responsible for keys/locks provided by the Government. Keys/locks shall not be duplicated by Contractor personnel, nor used by unauthorized Contractor personnel. The Contractor shall develop and implement procedures to insure that keys/locks issued to the Contractor by the Government are safeguarded. The Contractor developed procedures covering key/lock control shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys/locks by personnel who no longer require access to locked areas. NOTE: All references to keys include codes.
2.9.1 The Contractor shall report any occurrence of duplicated, misplaced, or lost keys/locks to the Contracting Officer and COR within 24 hours after discovery of occurrence, and submit a written report to the Contracting Officer by close of business the next workday. The written report shall provide complete details relating to duplication, misplacement, or loss.
2.9.2 In the event a key is duplicated, misplaced, or lost, all locks and keys for that system will be replaced at the discretion of the Government. The Contractor shall reimburse the
Government for replacement of locks or rekeying required as a result of keys being duplicated, misplaced, or lost by the Contractor or Contractor personnel. The Contractor shall also reimburse the Government for any government property lost or stolen as a result of unauthorized key duplication, misplaced key, or loss of key by the Contractor or Contractor personnel.
2.9.3 The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
2.9.4 The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the Contractor’s
Quality Control Plan.
2.10 Antiterrorism Training: Contractor will ensure all personnel receive Antiterrorism (AT) awareness training prior to contract performance. The Contractor may use its own training materials, provided the materials are reviewed and approved by the ANC security office prior to training being conducted; the Government will not be responsible for the cost of developing
AT awareness training materials. Contractor-developed training will include information on identifying and reporting suspicious activity based on the Army's iWatch program. The
Contractor may receive training materials and presentations from the ANC security office;
however, it is the Contractor's responsibility to ensure all personnel receive the training. The
Contractor will provide the Government with a report of training completed within 5 days from contract award. New employees will receive training prior to performing on this contract, and their training completion will be reported to the ANC security office within 5 days of their starting performance on this contract.
PART 3. PERSONNEL:
3.1 The Contractor shall provide a work force possessing the skills, knowledge, and training to satisfactorily perform the services required by this contract. Personnel performing work under this work statement shall remain employees of the Contractor and will not be considered employees of the Government.
3.2 Conflict of Interest: The Contractor shall not employ any person who is an employee of the United States Government or the Department of Defense, either military or civilian, if such employment would create a conflict of interest or be contrary to the policies contained in Department of Defense (DOD) Joint Ethics Regulation (JER), DOD 5500.7-R.
3.3 Conduct of Personnel: The Contracting Officer may require the Contractor to remove from the job site any employee working under this contract for reasons of misconduct, security, or found to be under the influence of alcohol, drugs, or other incapacitating agents.
Contractor employees shall be subject to dismissal from the premises upon determination by the Contracting Officer that such action is necessary in the interest of the Government. In accordance with (IAW) Joint Ethics Regulations, DOD 5500.7-R, and 18 U.S. 1382 (1972), the cemetery Executive Director (who has authority such as an installation commander) has the authority to bar individuals from the cemetery. The removal from the job site or dismissal from the premises shall not relieve the Contractor of the requirement of providing sufficient personnel to perform the services as required by this contract.
3.4 Key Personnel: The Government considers the following positions to be key personnel:
Site Manager. Projected replacement of key personnel must be submitted in writing to the
COR and Contracting Officer for approval 30 days prior to a replacement. Contractor will provide a for each key personnel position.
3.4.1 Site Manager: The Contractor shall provide a Site Manager who shall be responsible for the performance of the work. The Site Manager shall have a minimum of 7 years’ experience in installing landscape irrigation systems. The Site Manager shall have extensive knowledge and experience in installing Hunter Irrigation controllers, as well as expertise in the Hunter ACC2 controllers. The name of this person and an alternate who shall act for the
Contractor when the Site Manager is absent shall be designated in writing to the Contracting
Officer. The alternate Site Manager shall have similar qualifications as the Site Manager.
The Site Manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract, and either the Site Manager or his/her alternate will be on job site when work is being performed. This Site Manager – and in his or her absence, an alternate – shall have a cellular phone so that the COR can call him or her at any time, and shall also have an e-mail address which shall be checked for information from the Cemetery prior to 7:00 each day. The Site Manager is to report daily with the COR prior to 7:00 AM when any work is being performed.
3.5 Post Award Conference/Period Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings, the Contracting Officer will apprise the
Contractor of how the Government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the
Government.
3.6 Contracting Officer Representative (COR): The COR will be nominated by the requiring activity and appointed by the Contracting Officer by separate letter. A copy of the COR’s appointment letter will also be sent to the awarded Contractor, identifying the designated duties and limitations of the COR. The COR’s designated duties will describe the level of responsibility (inspection only – or inspection and acceptance) and what technical or administrative aspects of the contract are to be monitored. The COR’s oversight responsibilities are not limited to the QASP. Since all listed contract requirements or tasks are expected to be met by the contractor at all times, the COR is authorized to conduct oversight on any and all tasks or requirements and report observations to the Contracting Officer. The COR is not authorized to change any terms or conditions in the contract that pertain to cost, schedule, performance, quality, quantity, or other legal aspects of the resulting order.
3.7 Identification of Contractor Employees: All Contractor personnel attending meetings and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by the Contractor are suitably marked as Contractor products or that Contractor participation is appropriately disclosed
3.8 CONTRACTOR MANAGEMENT REPORTING (CMR) (Only applies to Army
Customers): The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report ALL
Contractor manpower (including subcontractor manpower) required for performance of this contract. The Contractor shall completely fill in all the information in the format using the following web address https://Contractormanpower.army.pentagon.mil. The required information includes: (1) Contracting Office, Contracting Officer, Contracting Officer’s
Technical Representative (COTR) or also know as the Contracting Officer’s Representative
(COR); (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor's name, address, phone number, e-mail address, identity of Contractor employee entering data; (5) Estimated direct labor hours
(including sub-Contractors); (6) Estimated direct labor dollars paid this reporting period
(including sub-Contractors); (7) Total payments (including sub-Contractors); (8) Predominant
Federal Service Code (FSC) reflecting services provided by Contractor (and separate predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10)
Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring
Activity (the Army Requiring Activity is responsible for providing the Contractor with its UIC for the purposes of reporting this information); (11) Locations where Contractor and sub-
Contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website);
(12) Presence of deployment or contingency contract language; and (13) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by country). As part of its submission, the Contractor shall provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period shall be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by
31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s system to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.
PART 4. GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND
SERVICES
4.1 General Information: The Government will provide the property and services listed below.
The Contractor shall not use the property or services provided by the Government for any purpose other than in the performance of this contract. All requests for Government furnished property and services shall be approved by the COR and Contracting Officer in writing.
4.2 Facilities: No facilities for the storage of materials or equipment will be provided.
4.3 Utilities: Water will be available at freeze hydrants and fill stations as designated by the
COR through in-ground water sources throughout the cemetery.
PART 5: CONTRACTOR FURNISHED ITEMS AND SERVICES
5.1 General Information: The Contractor shall furnish all supplies, equipment, and services required to perform work under this contract that are not listed under Section 2 of this PWS.
The Contractor shall also provide transportation and permits necessary to perform the requirements of this contract. This includes removal of all waste and trash from the cemetery.
5.2 Equipment Guidelines: The Contractor’s equipment shall be commercial grade equipped with protective and safety features that is in good repair, and clean IAW the requirements indicated in EM 385-1-1 Safety and Health Requirements. The Contractor shall submit, to the
Contracting Officer, an equipment list which includes, but is not limited to, quantities and descriptive data for all equipment prior to its use on ANC grounds. The Contractor shall inform the Contracting Officer, in writing, of any equipment list changes prior to implementing the changes. The equipment and supplies the Contractor uses shall not cause damage to turf areas, headstones, monuments, walkways, trees, or any other part of the landscape. It is expected that the Contractor will take preventative measures when entering soft ground with equipment, such as the use of boards, to prevent ruts.
5.3 Vehicles: The Contractor shall provide vehicles for the performance of services on this contract. Contractor and Contractor employees shall abide by all speed limitations while operating a vehicle at ANC. The speed limit at ANC is 25 mph on cemetery roads and 10 mph when passing pedestrians.
5.4 Communication Devices: The Contractor shall provide and maintain wireless communication devices for all Contractor furnished vehicles and key Contractor personnel performing services on this contract. The devices shall have a wireless area coverage capability that is reliable, to the maximum extent possible, within the Continental United
States. All cost related to providing wireless communication devices are the responsibility of the Contractor.
PART 6. SPECIFIC CONTRACTOR TASKS
6.1 Replace Existing Irrigation Controllers: The Contractor shall provide all labor, equipment, materials, and supervision of its employees to provide a comprehensive replacement of the indicated irrigation systems control and communication components with Hunter ACC2 controllers. The work includes the installation of communication modules in 14 irrigation controllers. When necessary, the contractor shall provide temporary power should there be a lapse in power during work (generator or temporary power line).
6.1.1 The contractor shall ensure that new controllers wiring and programming zones match the previous zone numbering.
6.1.2 The contractor is responsible for ensuring the proper operation of all electrical components in the field including, but not limited to, master valves, flow sensors, wiring, solenoids, and decoders.
6.1.3 The contractor shall ensure communication connectivity is established for each system sufficient for proper operation by the Hunter Centralus operating system. Testing will be conducted by programming and operating each new controller remotely.
6.1.4 Install twelve (12) controllers in accordance with manufacturer's written instructions at the following locations and specified wiring type:
Tomb of the Unkown Soldier/Amphitheater- 2-wire
Taft Gravesite (section 30)- 2-wire
Kennedy Gravesites (section 45)- 2-wire
Columbaria 1-9 systems (3)- all 2-wire
Facility Maintenance Complex- Conventional
Receiving Vault (section 13)- 2-wire
Millennium Area (Columbaria 10-13) - 2-wire
110 Gate- 2-wire
Administration Building- the 2 current conventional systems (side-by-side) will be routed into one new conventional controller. Use solid conduit to re-route the wires to the new controller.
Coast Guard Memorial- 2-wire
6.1.5 Contractor shall re-route conventional wires from second controller at Administration
Building into location for the single, new controller using solid, weatherproof conduit.
6.1.6 Contractor shall install modules, antennae, fittings, and accessories in accordance with manufacturer's instructions, except as otherwise indicated.
6.1.7 All wiring from the controller to the antennae shall be installed in a weatherproof fashion.
Contractor shall ensure the complete protection of the controller, as well as any structure the wire must pass through, from the elements. Contractor shall seek approval from the COR when planning to run wire through an existing structure in the Cemetery.
6.1.8 The contractor shall install the following specific communication modules at the locations indicated:
Tomb of the Unkown Soldier/Amp -LTE/Cellular
Taft Gravesite (section 30) -LTE/Cellular
Kennedy Gravesites (section 30) -LTE/Cellular
Columbaria 1-9 systems (3)-all Wi-Fi
Facility Maintenance Complex-Wi-Fi
Receiving Vault (section 13) -LAN
Millennium Area Columbaria 10-13 -LAN
110 Gate-LAN
Administration Building -LAN
Coast Guard Memorial -LTE/Cellular
Memorial Avenue (2)-LTE/Cellular (These are already ACC2 controllers and only need the cellular modules installed).
6.2 Controller Wiring: The contractor shall:
6.2.1 Connect each remote control valve to one station on a controller, in the order it was previously connected/programmed, except as otherwise indicated.
6.2.2 Connect any existing master valve, flow sensor, ground, and rain sensor wires to the proper respective ports in the controller.
6.2.3. Label all wire in each controller with numbered stick on wrap around band labels. Include labels for extra wires.
6.2.4 Connect remote control valves for each controller to a common ground wire system, independent of all other controllers.
6.2.5 Make wire connections to remote control electric valves and splices of wire in the field, using waterproof wire connectors and sealing cement in accordance with manufacturer's recommendations, dry splices will not be accepted.
6.2.6 Any wire run above ground, or that is not direct burial rated shall be run in solid conduit.
6.2.7 All materials and methods of installation shall conform to local electrical codes.
6.3 Testing and field troubleshooting. The contractor shall:
6.3.1 Perform system testing upon completion of each individual system to ensure proper input from any sensors, and proper manual electric activation of all valves from the newly installed controller. Make necessary repairs and retest repaired sections as required.
6.3.2 Test for sufficient electrical grounding of each controller. Repair as required.
6.3.3 Repair or replace any broken or faulty electrical components in the field of each system to include but not limited to wiring, decoders, solenoids, grounding rods/plates, and sensors.
6.4. Test and demonstrate controller functionality by successfully operating all automatic programs, including programming initiated remotely through the Hunter Centralus operating system.
6.5 Provide Zone Maps: The contractor shall deliver electronic and hard copy zone maps for each irrigation system controller.
PART 7. MATERIALS
7.1 General: The contractor shall provide only new materials, without flaws or defects. All controllers, modules, decoders, and solenoids shall be from Hunter to insure ease of maintenance and replacement. All irrigation components installed shall be compatible with existing irrigation system and compatible with Hunter ACC2 controllers and the Hunter Centralus operating system. The contractor shall provide the manufacturer’s data on all materials and supplies.
7.2 Controllers, communication modules, decoders, and solenoids:
7.2.1 Controllers shall be Hunter ACC2 that fit in the footprint of the previous Hunter controllers, and in the current strongboxes if located as such.
7.2.2 Communication modules shall be of Hunter make, compatible with ACC2, and of communication medium indicated for each site under the Installation section (LAN, wifi, or
LTE).
7.2.3 Decoders and solenoids will be of Hunter make and of proper model for each system.
7.2.4 Any mounting brackets or weatherproofing materials will hold secure under all weather conditions and be approved by the COR.
7.3 Plastic pipe, fittings, and connections:
7.3.1 Polyvinyl chloride pipe: rigid, un-plasticized PVC, extruded from virgin parent material.
Provide pipe homogeneous throughout and free from visible cracks, holes, foreign materials, blisters, wrinkles, and dents.
i. 2.5” diameter and under: Schedule 40 or greater, Bell end PVC.
ii. Over 2.5" diameter: gasket PVC SDR 21with lockable fittings rated to
7000 PSI. Lockable fittings are to be of the same material and from the same manufacturer as PVC pipe.
7.3.2 PVC pipe fittings to 2.5”: Schedule 40 PVC molded fittings suitable for solvent weld connections. Fittings made of other materials are not permitted. Saddle and cross fittings not permitted.
7.4 Valves and associated equipment:
7.4.1 Control Valves: Shall be electrically operated globe valves of proper sizing, dictated by the line it will be installed on. Valves will be manufactured by Hunter Industries, and have full compatibility with the systems they are incorporated into.
7.4.2 Two Wire Systems : Low voltage communication wire (2 wire path for Decoder Controller wire): Hunter Jacketed Decoder Cables shall be 12AWG – 2 conductor, twisted pair, rated for
600 volts, Polyvinyl Chloride Jacket impregnated polyethylene gauge UL/UF, direct burial, blue in color or pre- approved equal. All wire shall be looped from the controller along all mainline piping. Include lightning protection per manufacturer’s recommendation. Use only manufacturer’s recommendations on wire splices.
7.4.3 Non-Two Wire or Conventional Wiring: Voltage control wire for conventional controller shall be single conductor insulted wires 14AWG – 1 gauge UL/UF, suitable for direct burial rated for 600 volts, insulation, Colors: RED: Valve power; WHITE: Valve common; BLUE:
spares. All wire splices below grade shall be made water proof with correctly sized wire splice connectors made for direct burial and rated for minimum of 600 volts. Four feet of extra wire to be installed at each valve and splice.
7.4.4 Wire shall be color-coded. White is to be used for common, red is to be used for control, blue for extra, green for stub-out and yellow for sensor. Any deviation shall be replaced at contractor’s expense.
7.4.5 Wire Splice Waterproof connectors, UL listed for direct burial, rated at 600
Volts shall be used.
7.4.6 Valve Boxes: Provide box sizes that are suitable and adjustable for valve used. Lid color shall be green unless other color is requested.
PART 8. DELIVERABLES.
8.1 Controllers: Contractor shall deliver 12 properly installed and functioning Hunter ACC2 irrigation controllers with tested, repaired, and fully functioning fields at the locations indicated.
8.1.2 Contractor will deliver and install 2 properly installed and functioning LTE/cellular communication modules installed in the Hunter ACC2 controllers on Memorial Avenue, along with a tested and fully functional field from each controller.
8.2 Zone Maps and as-builts: Contractor shall deliver AutoCAD maps of the zoning of each system as programmed in the new controllers, as well as as-builts for any new or modified electrical routing or plumbing repairs. Maps will be made in such a way that the zones are clearly numbered and delineated to allow for a clear understanding of location when operating the system remotely. Contractor shall submit 3 hard copies and in electronic file format.
8.3 Operations and Maintenance Manuals: Contractor shall submit a hard copy of the written operating and maintenance instructions for each type of product specified, and a copy of each in electronic file format.
PART 9. ACCEPTANCE.
9.1 Contractor shall test and demonstrate to the COR the satisfactory operation of each system, fourteen (14) in all, from their respective controllers.
9.2 Contractor shall test and demonstrate to the COR the satisfactory operation of programming each system, fourteen (14) in all using the Hunter Centralus operating system from a remote location.
9.3 The contractor shall Instruct the government’s designated personnel in the operation of the system including programming from the clock and using the Centralus operating system. This service is not to begin until 100% acceptance of that system by owner has occurred.
9.4 Final acceptance will be based on adherence to specifications. In any area where specification is not met, contractor will correct all deficiencies at contractor’s expense.
PART 10. GUARANTEE
10.1 The contractor shall guarantee all workmanship, covered by the specifications to be free of defects for a period of one 1 year from date of final acceptance of the project. Contractor shall replace any part or parts found to be defective within the period of guarantee at no cost to the owner, except repairs or replacement necessitated by damage by others. Material, fixtures, and equipment is to be warranted for 1 year from installation date.
PART 11. OTHER CONTRACTOR RESPONSIBILITIES
11.1 Safety: The Contractor shall safeguard and maintain all Government property, as well as provide for the safety and well-being of personnel employed in the administration of this contract. The Contractor is solely responsible and liable for following all applicable Federal, Department of Army, and State of Virginia laws, regulations, mandates, and guidelines; and ensuring safe work and otherwise safe actions, behavior, and conduct of employees while at
ANC.
11.2 Disclosure of Information:
11.2.1 Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others. Neither the Contractor nor Contractor employees shall divulge or release data or information developed or obtained under performance of this work statement, except to the authorized Government personnel upon written approval of the Contracting Officer. The Contractor shall not use, disclose, or reproduce proprietary data which bears a restrictive legend, other than as specified.
11.2.2 Disclosure of information regarding operations and services of the activity to persons not entitled to receive it, or failure to safeguard any classified information that may come to the
Contractor (or any persons under the Contractor’s control) in connection with work under this work statement, may subject the Contractor, Contractor’s agent, or employees to criminal liability under Title 18, Sections 793 and 798 of the United States Code. Neither the Contractor nor its employees shall disclose nor cause to be disseminated any information concerning the operations of the activity that could result in the possibility of a breach of the activities’ security or interrupt the continuity of its operation.
11.2.3 The Contractor shall direct to the Contracting Officer all inquiries, comments, or complaints arising from matters observed, experienced, or learned as a result of, or in connection with, the performance of this contract. The resolution of such inquiries, comments or complaints may require the dissemination of official information.
11.2.4 Inquiries received by the Contractor for work performed under this contract shall be referred to the Government for evaluation under the Freedom of Information Act of 1975, Public
Law 93-502, 5 U.S.C. Section 552. The determination of whether records will be released will remain with the Government. Contractor shall be responsible for search and submission of records upon request by the Government.
11.2.5 The Contractor shall not release any information (including photographs, files, public announcements, statements, denials, or confirmations) on any part of the subject matter of this contract or any phase of any program hereunder without the prior written approval of the
Contracting Officer. All documentation showing individuals’ names or other personal information shall be controlled and protected. The provisions of the Privacy Act of 1974, Public
Law 93-579, 5 U.S.C., Section 552a, shall apply.
11.3 Liability and Responsibility for Damage To Property:
11.3.1 Damage To Government Property: The Contractor shall be held liable for damage or destruction of Government property (e.g. buildings, vehicles, sidewalks, headstones, etc.) caused by the Contractor, Contractor personnel or representatives of the Contractor in the performance of services in this contract. The Contractor shall be aware that Government property - beyond standard structures and equipment - also includes headstones, monuments, trees, beds, and turf
(for example, wounded trees or damaged turf - as well as headstones - shall be repaired or replaced). The Contractor shall take corrective action in a reasonable amount of time to repair damages or replace destroyed property. If the Contractor fails to take the required corrective action, the Government retains the right to exercise other rights or remedies available to the
Contracting Officer.
11.3.2 Damage To Privately Owned Property: The Contractor shall be held liable for damage or destruction of privately owned property (e.g. privately owned vehicles), as defined in this PWS, caused by the Contractor, Contractor personnel or representatives of the Contractor in the performance of services in this contract. The Contractor shall take corrective action in a reasonable amount of time to repair damages or replace destroyed property.
11.3.3 Damage Reports: The Contractor shall submit a damage report to the Contracting Officer and designated representative within two (2) workdays of damage or destruction to Government property or privately-owned property caused by the Contractor, Contractor personnel or representatives of the Contractor. The damage report shall detail the facts and the extent of damages or destruction and the corrective action taken by the Contractor to repair damages or replace destroyed property.
11.4 Contractor Conduct and Recognition of Ceremonies:
11.4.1 The Contractor is responsible for ensuring that work does not cause any funeral, ceremony, procession, or visitation to be delayed, altered, or otherwise impacted in such a way that the dignity or security of the event is compromised. The Contractor is responsible for staying abreast of all such upcoming events. A list of scheduled ceremonies will be provided, and a list of scheduled funerals will be provided on a daily basis. The Contractor shall communicate not less than daily with the COR, to ask questions and ensure he or she understands the off-limit areas which will vary depending upon the event. (As a rule-of-thumb, any work, especially with power equipment, within 1000 feet of a funeral or ceremony is not acceptable). The Contractor can thus assign tasks accordingly throughout the rest of the Cemetery so that productive use of labor and equipment is assured, and down-time is avoided. If the Contractor fails to re-direct employees away from an event in a timely fashion, the COR may then do so. The Contractor shall also visit with the COR on other issues of common Cemetery etiquette, such as conduct with next-of-kin and when processions pass by.
11.4.2 The Contractor shall ensure all contract employees behave with appropriate decorum, courtesy, and respect while within the Cemetery or at its perimeter or entrances. Shouting, cursing, angry outbursts, sleeping, intoxication, and violence or criminal acts of any kind will not be tolerated and is cause for immediate removal from the Cemetery and/or prosecution.
11.5 Smoking: The Contractor shall comply with AR 600-63, Army Health Promotion, which establishes uniform policies governing the use of tobacco products on Government real property.
11.6 Conservation of Utilities: The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves.
PART 12. ATTACHMENT/TECHNICAL EXHIBIT LISTING:
12. Attachment/Technical Exhibit List:
12.21 Attachment 2/Technical Exhibit 2 – Irrigation Controller Map
12.2 Attachment 2/Technical Exhibit 2 – Performance Requirements Summary.
12.3 Attachment 3/Technical Exhibit 3 – Deliverables Schedule.
TECHNICAL EXHIBIT 1
Irrigation Controller Map
TECHNICAL EXHIBIT 2
Performance Requirements Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective
Standard Performance Threshold
Method of
Surveillance
PRS # 1.
The Contractor shall Replace Existing
Irrigation Controllers IAW PWS 6.1 thru 6.2.7
Provide a comprehensive replacement of the indicated irrigation systems control and communication components with Hunter
ACC2 controllers.
Ensure that new controllers wiring and programming zones match the previous zone numbering.
Ensure the proper operation of all electrical components in the field including, but not limited to, master valves, flow sensors, wiring, solenoids, and decoders.
Ensure communication connectivity is established for each system sufficient for proper operation by the Hunter Centralus operating system.
Re-route conventional wires from second controller at Administration Building into location for the single, new controller using solid, weatherproof conduit.
Install modules, antennae, fittings, and accessories in accordance with manufacturer's instructions, except as otherwise indicated.
All wiring from the controller to the antennae shall be installed in a weatherproof fashion.
Zero deviation from standard 100%
Inspection
PRS # 2
The contractor shall install the following specific communication modules at the locations indicated:
Tomb of the Unkown Soldier/Amp -
LTE/Cellular
Taft Gravesite (section 30) -
Kennedy Gravesites (section 30) -
Columbaria 1-9 systems (3)-all Wi-Fi
Facility Maintenance Complex-Wi-Fi
Receiving Vault (section 13) -LAN
Millennium Area Columbaria 10-13 -
LAN
110 Gate-LAN
Administration Building -LAN
Coast Guard Memorial -LTE/Cellular
Memorial Avenue (2)-LTE/Cellular
(These are already ACC2 controllers and only need the cellular modules installed).
IAW PWS 6.1.8
Specified communication modules installed and fully functional
Zero deviation from standard
PRS # 3
The contractor shall install control wiring IAW PWS Paragraph 6.2
Each remote control valve is connected to one station on a controller, in the order it was previously connected/programmed, except as otherwise indicated.
All existing master valves, flow sensors, grounds, and rain sensor wires are connected to the proper respective ports in the controller.
Each controller is labeled with numbered stick on wrap around band labels. Include labels for extra wires.
Control valves for each controller are connected to a common ground wire system, independent of all other controllers.
Wire connections to remote control electric valves and splices of wire in the field, are made using waterproof wire connectors and sealing cement in accordance with manufacturer's recommendations, dry splices will not be accepted.
All wires run above ground, or that is not direct burial rated are run in solid conduit.
Zero deviation from standard
PRS # 4
The contractor shall Test and Field
Troubleshoot each system IAW PWS
Para 6.3.
Perform system testing upon completion of each individual system to ensure proper input from any sensors, and proper manual electric activation of all valves from the newly installed controller. Make necessary repairs and retest repaired sections as required.
Test for sufficient electrical grounding of each controller. Repair as required.
All broken or faulty electrical components in the field of each system to include but not limited to wiring, decoders, solenoids, grounding rods/plates, and sensors are repaired.
Demonstrate each controller is fully functional by successfully operating all automatic programs, including programming initiated remotely through the Hunter Centralus operating system.
Zero deviation from standard
PRS# 5.
The contractor shall provide Zone
Maps
IAW Para PWS 6.5.
Accurate electronic and hard copy zone maps for each irrigation system controller is provided.
Zero deviation from standard
Inspection.
PRS#6.
Materials meet requirements
IAW PWS Part 7
All materials are new, without flaws or defects. All controllers, modules, decoders, and solenoids are from
Hunter to insure ease of maintenance and replacement.
All irrigation components installed are compatible with existing irrigation system and compatible with Hunter
ACC2 controllers and the Hunter
Centralus operating system.
Controllers are Hunter ACC2 and fit in the footprint of the previous Hunter controllers, and in the current strongboxes if located as such.
Communication modules are of
Hunter make, compatible with ACC2, and of communication medium indicated for each site under the
Installation section (LAN, wifi, or
LTE).
Mounting brackets or weatherproofing materials hold secure under all weather conditions and be approved by the COR.
Polyvinyl chloride pipe meets the following: Rigid, un-plasticized PVC, extruded from virgin parent material.
Provide pipe homogeneous throughout and free from visible cracks, holes, foreign materials, blisters, wrinkles, and dents.
i. 2.5” diameter and under:
Schedule 40 or greater, Bell end PVC.
ii. Over 2.5" diameter: gasket
PVC SDR 21with lockable fittings rated to 7000 PSI. Lockable fittings are to be of the same material and from the same manufacturer as PVC pipe.
PVC pipe fittings to 2.5” meet the following: Schedule 40 PVC molded fittings suitable for solvent weld connections. Fittings made of other materials are not permitted. Saddle and cross fittings not permitted.
Control Valves Meet the following:
Shall be electrically operated globe valves of proper sizing, dictated by the line it will be installed on. Valves will be manufactured by Hunter
Industries, and have full compatibility with the systems they are
Zero deviation from standard incorporated into.
Two Wire Systems meet the following : Low voltage communication wire (2 wire path for
Decoder Controller wire): Hunter
Jacketed Decoder Cables shall be
12AWG – 2 conductor, twisted pair, rated for 600 volts, Polyvinyl
Chloride Jacket impregnated polyethylene gauge UL/UF, direct burial, blue in color or pre- approved equal. All wire shall be looped from the controller along all mainline piping. Include lightning protection per manufacturer’s recommendation.
Use only manufacturer’s recommendations on wire splices.
Non-Two Wire or Conventional
Wiring meet the following: Voltage control wire for conventional controller shall be single conductor insulted wires 14AWG – 1 gauge
UL/UF, suitable for direct burial rated for 600 volts, insulation, Colors:
RED: Valve power; WHITE: Valve common; BLUE: spares. All wire splices below grade shall be made water proof with correctly sized wire splice connectors made for direct burial and rated for minimum of 600 volts. Four feet of extra wire to be installed at each valve and splice.
Wires are color-coded. White is used for common, red is used for control, blue for extra, green for stub-out and yellow for sensor.
Wire Splice Waterproof connectors are UL listed for direct burial, rated at
600 Volts are used.
Valve Boxes provided are box sizes that are suitable and adjustable for valve used with green lids.
PRS#7.
The Contractor shall test and demonstrate to the COR the satisfactory operation of each system, fourteen (14) in all, from their respective controllers.
IAW PWS Part 9
Test and demonstrate to the COR the satisfactory operation of each system, fourteen (14) in all, from their respective controllers.
Test and demonstrate the satisfactory operation of programming each system, fourteen (14) in all using the Hunter Centralus operating system from a remote location.
Instruct the government’s designated personnel in the operation of the system including programming from the clock and using the Centralus operating system.
Zero deviation from standard
TECHNICAL EXHIBIT 3
DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit To
12 properly installed and functioning
Hunter…
This is the start of the file's text. The full file is on GovTribe.