PWS - Hangar 2 Electronic Acoustic System.pdf

PDF 180 KB Posted

Attached to
Hanger 2 Electronic Acoustics Systems
Solicitation number
FA706026R0005
Issued by

About this file

This is a Performance Work Statement for the installation of an L-Acoustics Ambiana electronic acoustic system in the Concert Band rehearsal studio (Hangar 2) at the United States Air Force Band located at Anacostia-Bolling, Washington, DC.

The contractor must decommission and remove approximately 84 loudspeakers from the existing defunct LARES system, including drywall patching and preparation for repainting of 32 speakers removed from vertical surfaces. The contractor will then design and install a new L-Acoustics Ambiance system in coordination with L-Acoustics designers to enable performers to receive acoustical feedback, simulate concert hall acoustics, provide voice lift for commanders calls, and support audio input for distributed sound playback. The system design must minimize interference with theatrical lighting fixtures and projectors, incorporate 9 microphones on servo reelers (contractor provides 6 reelers; USAF Band provides 3 existing reelers), and include operator presets for novice users. The minimum equipment list specifies 59 L-Acoustics 5XT loudspeakers, 12 SB10i subwoofers, various amplifiers and processors, 20 Schoeps microphones, 6 servo reelers, and QSC control system components. All installation must be completed within 365 days of contract award.

The contractor must be an L-Acoustics Certified Provider for a minimum of 10 years, maintain at least 2 technicians trained in L-ISA Technology, Loudspeaker Systems, Preproduction, Mixing, and Soundvision, be located on the East Coast with 4-business-hour service call response capability, and maintain specific backup equipment inventory. The contractor must provide onsite technical training, a continuity binder, and two years of onsite warranty and technical support from client handover. Bid submissions require an approval letter from L-Acoustics, a complete equipment list, and a narrative of qualifications and previous installations. Work hours are 8 AM–4 PM Monday through Friday, excluding federal holidays and government facility closings.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

FOR

The United States Air Force Band

Hangar 2 Electronic Acoustic System

BACKGROUND:

The USAF Band requires an electronic acoustics system to enhance the acoustics in the Concert Band rehearsal studio. The room currently houses a defunct LARES system which will be removed as part of this statement of work. The USAF Band has determined that an L-Acoustics Ambiance System is the only option to meet the needs of the members of the USAF Band.

SCOPE:

Contractor will decommission and remove approximately 84 loudspeakers from the existing LARES system. 32 loudspeakers will be removed from vertical surfaces and will require drywall patching and prep for repainting. Contractor will remove all cabling and hardware from existing speaker install.

Contractor will then work with L-Acoustics designers to design and install an L-Acoustics Ambiance system to meet the needs defined in this SoW.

OBJECTIVES:

Remove current LARES system, hardware and patch walls. Install a new L-Acoustics Ambiance system per L-Acoustics design which will allow for performers to receive acoustical feedback from the playing of their instruments as well as simulate the acoustics of a concert hall. The system shall also provide voice lift for use in commanders calls and allow for audio input for distributed sound as needed for audio playback.

TASKS:

- Contractor shall provide detailed drawings, equipment lists, wiring schematics, and timelines during the planning phase. Multiple drawings showing installation plans shall be approved prior to the installation.

-Contractor shall remove existing sound system components consisting of speakers, mounting brackets, cabling, etc. Any holes in structure shall be patched by a drywaller and prepped for painting.

-Contractor shall install all system components including racked equipment, cabling, speakers, control panels, etc. Contractor be responsible for all costs associated with pulling cable throughout the campus.

-Contractor will provide onsite technical training for the new system’s operation and a continuity binder and training aides for future personnel.

-Contractor shall provide a two-year onsite installation warranty and technical support service from the date of client handover.

-Contractor shall be responsible for any equipment required to install the system to include aerial lifts, equipment lifts, etc.

-Contractor shall use 5/8” or ¾” inch plywood or OSB in all locations inside of the rehearsal studio where a lift is to be used to protect the flooring.

-Contractor will be responsible for protecting all fixtures including drapes, electronics, instruments, etc.

from any dust created from construction.

REQUIREMENTS:

-The system shall be designed and built per L-Acoustics specifications. An L-Acoustics Ambiance specialist shall be consulted and present during all pre installation meetings and design work. The specialist shall be on site for the commissioning and training portion of the installation.

-The system shall be designed and installed to minimize the interference with theatrical lighting fixtures and projector located in the rehearsal studio. 9 Microphones shall be installed on servo reelers as needed to be retracted during special events. Contractor shall provide 6 reelers and the USAF Band shall provide 3 existing reelers for re-use.

-Contractor shall create presets selectable by novice operators to operate the system when trained personell are not present.

-Contractor must have a minimum of 2 technicians on staff trained in the following courses:

• L-ISA Technology

• L-ISA Loudspeaker System

• L-ISA Preproduction

• L-ISA MIXING

• Soundvision

-Contractor must have been an L-Acoustics Certified Provider for a minimum of 10 year

-Contractor must be located on the East Coast and able to respond to a service call in person within 4 business hours

-Contractor must have the following equipment in their rental inventory in case a failure occurs:

1 L-ISA Processor II 1 LA-7.16i Amplified Controller 4 5XT Loudspeakers

MINIMUM EQUIPMENT LIST:

59 L-Acoustics 5XT Loudspeakers 59 L-Acoustics ETR5 U Bracket mount 12 L-Acoustics SB10i Ultra compact subwoofer 10 L-Acoustics SB10i-onCW on wall or ceiling mount for SB10i 5 L-Acoustics LA7.16i 16 channel amplified controller for install 1 L-Acoustics L-ISA processor 5 L-Acoustics P1 digital processor 2 L-Acoustics LS10 10 port AVB Switch 1 L-Acoustics LS10 Rack Shelf 1 Apple 15 inch M3 Mac Book Air with USB-C hub 1 L-Acoustics UPG Ambiance L-Isa upgrade for 32 microphones 1 L-Acoustics UPG 16TO64 L-ISA Live license upgrade from 16 to 64 outputs 35 C Clamp mounts for ceiling speakers 1 Lot of cabling

6 servo microphone reelers 20 Schoeps Colette series MK21 small diaphragm condesnor mics 20 Delvcam Vgrip-2 multi arm clamp mount for mics 1 QSC Q-SYS Core 8 flex 1 QSC POE Touch Screen 1 Q-Sys Core 8 flex Nano USCI deployment software license 1 Q-Sys Core 8 Flex Nano scripting license

PLACE OF PERFORMANCE:

The USAF Band, 201 McChord Street Anacostia-Bolling, Washington, DC 20032

PERIOD OF PERFORMANCE:

All equipment shall be installed within 365 days of contract award.

BID SUBMISSION REQUIREMENTS:

Contractors must submit a letter from L-Acoustics approving of their qualifications to install an Ambiance system at this location. Any bids without this paperwork will be immediately disqualified. A complete equipment list along with a narrative of their qualifications as highlighted above in the requirements section as well as previous installs shall also be included in the bid package.

SPECIAL QUALIFICATIONS:

Contractor must be qualified by L-Acoustics to install and maintain Ambiance Systems.

SECURITY REQUIREMENTS:

Contractor shall be responsible for safeguarding all government equipment, information, and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

GENERAL INFORMATION

RECOGNIZED HOLIDAYS:

Contractor is not required to work on federally recognized holidays.

HOURS OF OPERATION:

The contractor is responsible for conducting business, between the hours of 8 AM-4PM Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar government directed facility closings. For other than firm, fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons.

CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

The Contractor shall furnish materials, supplies, and equipment necessary to meet the requirements under this SOW.