This document is a Performance Work Statement (PWS) for the Remedial Process Optimization (RPO) and implementation of the remedy at Site CS001 at the Former Galena Forward Operating Location (FOL) in Galena, Alaska. The key objectives are:
- Implement the remedy at Site CS001 in accordance with the Record of Decision (ROD) to successfully implement the remedy and demonstrate it is performing as designed.
- Perform RPO of existing remedies at several other sites, including hot spot excavations and in-situ injections. The Contractor will be responsible for providing all management, tools, supplies, equipment, and labor necessary to perform the contract requirements. The work must comply with all applicable federal, state, and local statutes and regulations. The PWS outlines detailed requirements for project administration, technical plans and reports, quality program, environmental requirements, media management, restoration activities, and other services. Key dates, milestones, and deliverables are specified in the PWS.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Galena Presolicitation Notice 21Jun24.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8903-24-R-XXXX
GALENA FOL, AK
ATTACHMENT 1
24 APRIL 2024
PERFORMANCE WORK STATEMENT (PWS)
FOR
SITE CS001 REMEDY AND REMEDIAL PROCESS OPTIMIZATION (RPO)
IMPLEMENTATION
AT
FORMER GALENA FORWARD OPERATING LOCATION (FOL), GALENA, ALASKA
CONTRACT NUMBER: FA8903-24-R-XXXX
PROJECT NUMBER: HPZW20247252
ATTACHMENT 1
24 APRIL 2024
TABLE OF CONTENTS
1.0 INTRODUCTION
1.1 SCOPE
1.2 APPLICABLE DOCUMENTS
1.3 WORK RAMP-UP AND TRANSITION
1.3.1 Work Ramp-Up ........................................................ Error! Bookmark not defined.
1.3.2 Transition of Work ................................................... Error! Bookmark not defined.
1.4 REMEDIAL SYSTEM COMPONENTS
1.5 GOVERNMENT FURNISHED INFORMATION (GFI)
2.0 PROJECT ADMINISTRATION
2.1 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS
2.3 CONTRACTOR’S PROGRESS, STATUS, AND MANAGEMENT REPORT (CPSMR)
2.4 MEETING AND CONFERENCE SERVICES
2.4.1 Meeting/Teleconference Support
2.4.2 Public Meetings and Hearings
2.4.3 Regulatory/Professional Interface
2.4.4 Notification Requirements
2.4.5 Site Access: Permits, Easements, and Work Site Access
2.5 WORK SITE COORDINATION
2.6 PHOTO DOCUMENTATION
2.7 CONTRACTOR DOCUMENTATION
2.8 RECORD KEEPING
3.0 GENERAL REQUIREMENTS
3.1 TECHNICAL PLANS AND REPORTS
3.1.1 TECHNICAL PLANS
3.1.2 TECHNICAL REPORTS
3.2 QUALITY PROGRAM PLAN (QPP)
3.2.1 UFP-QAPP
3.2.2 WORK PLANS (WPS)
3.2.3 HEALTH AND SAFETY PLAN (HSP)
3.2.4 CHEMISTRY REQUIREMENTS
3.2.5 QUALITY ASSURANCE
3.2.6 LABORATORY SELECTION
3.2.7 ANALYTICAL DATA MANAGEMENT
3.2.8 ENVIRONMENTAL RESOURCES PROGRAM INFORMATION MANAGEMENT SYSTEM
(ERPIMS)
3.2.9 COMPUTER-AIDED DESIGN DRAWING (CADD) AND GEOGRAPHIC INFORMATION
SYSTEMS (GIS) UPDATES
4.0 GENERAL ENVIRONMENTAL REQUIREMENTS
4.1 SITE CHARACTERIZATION
4.2 SITE PREPARATION
ATTACHMENT 1
24 APRIL 2024
4.3 CONSERVATION
4.4 ENVIRONMENTAL CONSTRUCTION
4.4.1 DELIVERY AND WARRANTY OF INSTALLED EQUIPMENT AND SYSTEMS
4.4.2 INNOVATIVE AND PROVEN TECHNOLOGIES
4.4.3 OPERATIONS AND MAINTENANCE (O&M)
4.4.4 DEMOBILIZATION AND SITE RESTORATION
5.0 ENVIRONMENTAL MEDIA
5.1 AIR QUALITY
5.2 WASTEWATER AND STORM WATER
5.3 WATER QUALITY
5.4 NATURAL AND CULTURAL RESOURCES
6.0 ENVIRONMENTAL RESTORATION
6.1 REMEDIAL ACTION (RA)
6.2 OPTIMIZATION
6.3 WELL AND SYSTEM DECOMMISSIONING
7.0 SERVICES SUMMARY
8.0 MISCELLANEOUS
GOVERNMENT POINTS OF CONTACT (POC)
SUPPLIES AND EQUIPMENT ACQUISITION
9.0 ROLES AND RESPONSIBILITIES
ATTACHMENT 1 – ACRONYMS AND DEFINITIONS
ATTACHMENT 1
1.0 INTRODUCTION
1.1 Scope
The Contractor shall provide all management, tools, supplies, equipment, and labor necessary to perform the contract requirements. This Performance Work Statement (PWS) defines the full range of environmental, construction, and optimization services necessary to conduct site restoration including maintenance of established remedies, implementation of optimization, and remediation activities to achieve performance objectives as identified in this contract.
The former Galena Forward Operating Location (FOL) is located in a remote area in the western portion of interior Alaska (AK). Several sites are being addressed following the Comprehensive
Environmental Response, Compensation, and Liability Act (CERCLA) process. The remaining sites are being addressed under the Alaska Department of Environmental Conservation (ADEC)
Contaminated Sites Program. ADEC is the lead regulatory support agency. The United States
Environmental Protection Agency (USEPA) is consulted, as needed, particularly with regard to hazardous waste and underground injection control (UIC) wells.
This contract includes implementation of the remedy at CS001 in FY25 in accordance with the
Record of Decision (ROD). The performance objective for CS001 is to successfully implement the remedy and demonstrate it is performing as designed.
This contract also includes remedial process optimization (RPO) of existing remedies in FY25 as follows:
• “Hot Spot” excavations at sites CST011 Area 2, SS016, and SS018.
• In-situ remediation optimization (injections) at sites CPL006, SS006, SS015, SS017, SS019, and ST009.
The Contractor is solely responsible for reviewing all publicly available information and forming their independent, professional conclusions/interpretation of site conditions and requirements to achieve the performance objectives of this contract.
The Contractor shall function as an integral team member in support of the United States Air
Force Civil Engineer Center (AFCEC) and Base Realignment and Closure (BRAC) mission, to include the sharing of information with other AFCEC Contractors and AF personnel, and cooperation with communities, regulators, and other government entities. Requirements such as the achievement of accurate, on-time, quality performance objectives and timely identification and solution of impediments to successful project execution are necessary to ensure efficient management of this contract. Early involvement in the process by all parties allows for the development of the most cost-effective and technically sound approach or solution. The AFCEC will rely on the Contractor’s expertise in recognizing and addressing problematic issues and successful execution of this contract. The Contractor shall perform all work in accordance with federal, state, and local statutes and regulations. Remedies shall conform to environmental permits, decision document requirements, or other legal requirements.
ATTACHMENT 1
In carrying out each work assignment issued under the contract, the Contractor shall furnish the personnel, services, equipment, materials, facilities, and other requirements necessary for, and incidental to, the performance of work set forth herein.
Primary technical services shall be performed by individuals who are credentialed members of architectural, planning, science, and engineering professions. Disciplines such as architects, landscape architects, engineering disciplines typically associated with environmental engineers and scientists (e.g., professional engineer [PE], professional geologist [PG]), planners, cost estimators, Computer-Aided Design and Drafting (CADD) technicians, publication writers/editors, technical writers, graphic artists, and Geographic Information System (GIS) analysts are included. Generally, a credentialed professional (a) is licensed (e.g., registered professional engineer) to practice in the state where a facility is located and/or (b) commands the necessary expertise, in terms of knowledge and experience, to undertake the specified task.
List of Attachments:
• Attachment 1 – Acronyms and Definitions
1.2 Applicable Documents
The Contractor shall identify and comply with all applicable federal, state, and local statutes;
Department of Defense (DoD) and AF instructions, manuals, handbooks, regulations, guidance, and policy letters (including DoD and AF policy and guidance for Environmental Restoration
Program [ERP] and Emerging Contaminants); Executive Orders (EO); American Society for
Testing and Materials (ASTM); American Petroleum Institute (API) Codes; National Association of Corrosions Engineers (NACE); National Fire Protection (NFPA); Steel Structures and
Painting Counsel (SSPC); National Electrical Code (NEC); Uniform Fire Code (UFC);
Occupational Safety and Health Administration (OSHA) regulations, and International Building
Code (IBC) including all changes and amendments in effect on the date of issuance of this contract. It is the Contractor’s responsibility to identify and comply with all applicable requirements. In addition, the Contractor shall refer to the current versions of the DoD Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and the United
States AF Construction Management Implementation Guide.
It is the Contractor’s responsibility to identify and comply with all applicable or relevant and appropriate requirements (ARARs). The Contractor shall identify and comply with all applicable documents including RODs, ROD Amendments, Explanations of Significant
Difference, and other Decision Documents, Deeds, and conveyance notices. Key base-specific documents are available on the AF Administrative Record at http://afcec.publicadmin-record.us.af.mil/Search.aspx. See Table 1 for key background documents list.
The information provided in this PWS is not intended as a substitute for complete analysis of technical data available.
http://afcec.publicadmin-record.us.af.mil/Search.aspx
ATTACHMENT 1
Table 1 - Background Documents
No. Document Title Location Date Issued
1 First Five-Year Review AR# 598192 03/01/2020
2 2023 Remedial Process Optimization
Evaluation Report
AR# 629129 08/23/2023
3 CH2M RPO Evaluation *NA NA
4 Final UFP-QAPP for Performance-based
Remediation, Revision 1
AR# 592861 08/01/2019
5 Addendum to the Uniform Federal Policy
Quality Assurance Program Plan (UFP-
QAPP) Revision 1
AR# 606879 02/01/2021
6 Addendum 2 to the Uniform Federal Policy
Quality Assurance Program Plan (UFP-
QAPP) Revision 1
AR# 621251 06/27/2022
7 Addendum 3 of the Final UFP-QAPP for
Performance-based Remediation, Revision 1 for Landfarm Operations
AR# 628837 03/14/2023
8 Addendum 4 to the Uniform Federal Policy
Quality Assurance Program Plan (UFP-
QAPP) Revision 1
AR# 629131 08/16/2023
9 2022 Performance Monitoring Report (CH2M
HILL Sites) for Sites SS005, CST014, CST011 Area 2, TU001, CG001, Southern
ST005, and ST005 Area C Former Galena
Forward Operating Location, Alaska
AR# 629108 07/20/2023
10 2022 Performance Monitoring Report for
Sites CPL006, CSS002, SS006/SS019, SS017, SS015, SS016, SS018, SS022, ST009, ST010, and FT001 Former Galena Forward Operating
Location, Alaska
AR# 628854 05/31/2023
13 Feasibility Study Report for Contaminated
Sediments (DDT Soils) (Site CS001)
AR#591684 9/1/2019
14 Record of Decision for Contaminated
Sediments (DDT Soils) (Site CS001)
AR #599076 05/01/2020
* To be provided by the AF separately as document has not been finalized
NA – Not available on AR, to be provided by the AF separately
ATTACHMENT 1
24 APRIL 2024
1.3 Work Ramp-Up and Transition. Not Applicable
1.4 Remedial System Components
The Contractor shall properly account for and manage all new and existing remedial system components including monitoring wells, as applicable, procured and utilized at the installation.
(Contract Data Requirements List [CDRL] A001)
The AF is responsible for providing utilities (electricity) for all remedial systems under this contract. The Contractor is responsible for providing all other materials, supplies and equipment, not already installed or incidental to the place of performance, required to meet the objectives specified in this contract. All AF owned equipment used for remediation purposes is as-is, where-is and must be maintained by the Contractor in accordance with applicable operations and maintenance (O&M) plans, manufacturer specifications, or other documentation. The Contractor is responsible for proper return or disposal of excess or unserviceable equipment, supplies, or materials as required during the duration specified in this contract. Note that the Government does not own the Brown Bear tiller used for landfarm operations. The Contractor is required to provide a Brown Bear (or comparable) tiller for use at the Galena landfarm.
The Contractor is required to provide secure storage for all remedial system components, as applicable, until such time it is, disposed of or transitioned to other AF contract efforts supporting the associated system at the end of the Period of Performance (POP), whichever comes first, as specified in this contract. In addition to storage, the Contractor is responsible for acquiring office space (current contractor rents the MedAide building from the City of Galena) and the utilities (electricity) for both the office rental and storage.
1.5 Government Furnished Information (GFI)
GFI is provided in the AF Administrative Record (AR); see http://afcec.publicadmin-record.us.af.mil/Search.aspx. GFI not available in the AR and required for this contract will be provided to the Contractor via DoD SAFE.
2.0 PROJECT ADMINISTRATION
2.1 Management, Planning, and Reporting Requirements
The Contractor shall implement a full range of environmental restoration services as specified in this contract and in accordance with all applicable documents. The Contractor shall supply all labor, equipment, and materials necessary to accomplish the work. The Contractor shall perform management and planning functions, including performance measurement through the course of this effort.
2.2 Performance Milestones and Payment
ATTACHMENT 1
24 APRIL 2024
The Contractor shall prepare and submit a Milestone Payment Schedule (MPS) for approval, as applicable. Milestones are based on the completion of a definable and measurable step considered integral and necessary to the achievement of the objectives specified in this contract and demonstrate that payment is appropriate. AF acceptance of the documentation supporting the completion of the milestone is required for payment. Where regulatory acceptance/concurrence is required for this documentation, AF approval will occur following regulatory acceptance/concurrence. For milestones where regulatory acceptance/concurrence is required and regulatory acceptance/concurrence cannot be obtained, the AF will evaluate the
Contractor’s documents to determine if they are legally and technically acceptable to warrant payment for achieving that milestone. (CDRL B001, B003)
2.3 Contractor’s Progress, Status, and Management Report (CPSMR)
The Contractor shall prepare and submit a monthly CPSMR. The CPSMR shall be used to review and evaluate the overall progress of this contract, along with any existing or potential problem areas. The CPSMR shall include a summary of the events that occurred during the reporting period, discussion of performance, identification of problems, proposed solutions, corrective actions taken, outstanding issues, and projected tasks such as field work, reporting, et cetera, occurring in the next 90 days. (CDRL B001, B003)
2.4 Meeting and Conference Services
2.4.1 Meeting/Teleconference Support
The Contractor shall participate in post-award meetings and periodic contract status, technical review, and/or Project Management Review (PMR) meetings/teleconferences with the AF.
The Contractor shall also attend and/or support meetings and teleconferences to discuss technical or regulatory issues and progress and status with the AF and regulatory agency representatives as required, including Technical Planning Team (TPT)) meetings, and other periodic meetings/teleconferences.
The AF will be present for all technical meetings with the regulatory agencies; however, the
Contractor shall coordinate the meeting, provide logistical support (e.g., facilities, audio/visual), presentation materials, agendas, meeting minutes, and lead technical discussions. The
Contractor shall prepare, and submit for AF review not less than five (5) working days prior to the meeting (unless otherwise approved by the AF), presentation materials for meetings and an agenda. The Contractor shall prepare summaries/minutes for all meetings attended and submit for AF review not less than 10 working days after the meeting has occurred. (CDRLs B006, B007, B008)
The Contractor shall provide support for one (1) kick-off teleconference involving the CO, COR, and all AF Points of Contact (POCs) and technical support to include meeting minutes and/or presentation slides.
ATTACHMENT 1
24 APRIL 2024
The Contractor shall provide support for biweekly technical contract status teleconferences throughout the duration of this contract as necessary with the COR, AF POCs, and technical support and other stakeholders as deemed appropriate to discuss technical aspects of the activities and progress included as part this contract.
The Contractor shall prepare and submit for approval presentation materials, agendas, and minutes for all meetings, at the request of the COR. (CDRLs B006, B007, B008)
The Contractor shall not contact, nor take direction from, any regulatory agency without prior notification and approval by the AF. In situations of imminent health or safety risks, regulators may direct the AF and their contractors to stop work.
2.4.2 Public Meetings and Hearings
At the direction of the AF, the Contractor is responsible to support all community involvement requirements to meet CERCLA and other regulatory requirements including public meetings
(e.g., Proposed Plan meetings), public notices, public comment periods, and responsiveness summary preparation. The contractor shall contact the COR to coordinate with the AF Public
Affairs (PA) and the assigned BRAC Public Affairs Officer (PAO) for all “external” materials that will be released.
At the direction of the AF, the Contractor shall support and attend estoration Advisory Board
(RAB), and other periodic public meetings/teleconferences as necessary. Provide supporting presentation materials for two (2) RAB meetings per year. Any stand along public meeting requirements include meeting logistics (e.g., facilities, audio/visual), newspaper notices, radio announcements, agendas, presentations, handouts, and meeting summaries/minutes, and transcripts where specified. (CDRLs B006, B007, B008)
At the direction of the AF, the Contractor shall research and support coordination and response for short-notice internal and external requests for information such as congressional inquiries and media requests. These inquiries require the Contractor to provide the AF factual and responsive information. (CDRL A001)
2.4.3 Regulatory/Professional Interface
The Contractor shall develop and prepare verbal/written interaction with interested parties related to the project. Forums may include administrative proceedings, judicial proceedings, formal meetings, or informal meetings. The Contractor shall provide all required support including preparation of presentation materials, agendas, minutes, publications, news releases, public notices, and the maintenance of mailing list(s). (CDRLs A001, B006, B007, B008)
The Contractor shall conduct project technical review, analysis, and discussions to integrate comments from interested parties on programs and related data and studies. The Contractor shall develop recommendations for responses and prepare report(s) to communicate government priorities to regulatory agencies and other interested parties. (CDRL A001)
ATTACHMENT 1
The Contractor shall conduct review and interpretation of new and proposed statutory and regulatory requirements and make recommendations for government planning and policy integration as it applies and as specified in this contract. (CDRL A001)
The Contractor shall provide on-site support for two (2) TPT meetings with regulators and other stakeholders annually, to be held concurrently with semiannual RAB meetings.
The Contractor shall prepare and submit for approval presentation materials, agendas, and minutes for all regulatory/professional interface meetings, at the request of the COR. (CDRLs
B006, B007, B008)
2.4.4 Notification Requirements
The Contractor is required to notify the CO and COR of critical issues that may affect the contract performance and/or human health and the environment. The types of issues that require notification include, but are not limited to, health risks, spills, Notices of Violation (NOV)
(received or anticipated), and changes in key personnel, and finding unexploded ordnance
(UXO). On critical issues, verbal notification shall be made immediately, followed by written notification within three working days. (CDRL A003)
If unanticipated UXO is discovered during field activities, the Contractor shall immediately stop work, report the discovery to the CO and COR, and implement the appropriate safety precautions. Field activities cannot continue until clearance is received from the CO.
The Contractor shall follow the 3Rs (Recognize, Retreat, and Report) Explosives Safety
Education Program; see https://www.denix.osd.mil/uxo.
In the event of a dispute with or enforcement action from a regulatory agency arising from performance of work covered as specified in this contract, regardless of whether the AF is a named party, the Contractor shall notify the CO or COR within 24 hours. If the AF is a named party in the dispute or enforcement action, the Contractor shall provide support to the AF as required to resolve the dispute or enforcement action. If the AF is not a named party in the dispute or enforcement action, the Contractor shall provide its proposed response to the dispute or enforcement action to the AF for review and comment prior to submission. Contractor support typically includes preparing a briefing, point paper, and summary of technical data to support the AF position. (CDRL A001)
2.4.5 Site Access: Permits, Easements, and Work Site Access
At the direction of the AF, the Contractor shall develop, coordinate, apply for, pay fees for, comply with, and/or modify all federal, state, local, and other applicable permits required to meet the objectives specified in this contract. The Contractor shall maintain a library of these documents and maintain copies at the installation where applicable. (CDRL A001) https://www.denix.osd.mil/uxo
ATTACHMENT 1
24 APRIL 2024
Pursuant to CERCLA (42 U.S.C. 9621(e)), no federal, state, or local permits shall be required for onsite CERCLA removal or remedial actions. The Contractor must consult with the AF prior to obtaining environmental permits for onsite CERCLA activities. For non-CERCLA restoration sites, the Contractor shall comply with all applicable permit conditions, including implementation of the permits and payment of permit fees. If the Contractor has any question whether a particular permit may or may not be required, the Contractor shall consult with the AF prior to obtaining the permit.
The Contractor shall be responsible for reviewing and responding to requests to provide mapping information for all onsite remediation systems, and other dig/utility locate related requests, requiring the identification of subsurface appurtenances and utilities associated with new and existing remediation systems included in this contract. In accordance with individual state requirements, the Contractor shall subscribe to the requisite utility locator service(s). Utility location requests will be sent to the Contractor via utility notification service (i.e. dig safe, etc.)
and the Contractor will be required to review, respond, and address all location requirements.
The Contractor shall maintain all records pertaining to location requests.
The Contractor shall be responsible for identifying and obtaining access to the worksite (including site access badges, rights of entry, access agreements, notifications, encroachment permits, etc.)
through coordination with the AF, county, municipal, airport, landowner, tenant, and other stakeholders to ensure access to all areas necessary to conduct activities as specified in this contract. (CDRL A001)
2.5 Work Site Coordination
The Contractor shall coordinate worksite activities with all applicable personnel and/or agencies to ensure the protection of human health and the environment; the prevention of damage to property, utilities, materials, supplies, and equipment; and the avoidance of work interruptions.
The Contractor shall ensure all work areas are secure and appropriate measures have been taken to eliminate any risk to the public on active environmental sites, as appropriate. The Contractor shall perform emergency response for situations arising from project activities. The Contractor shall perform emergency repairs to facilities, systems, improvements, or utilities damaged in the course of conducting work specified in this contract. The Contractor must comply with OSHA safety and health regulations and local safety office requirements. The Contractor is required to provide the CO copies of any OSHA report(s) submitted during the duration of this contract as specified in this contract. (CDRL A004)
All on-site workers (Contractor and subcontractor) performing hazardous operations, including working with hazardous materials, must have completed the OSHA 1910.120 Hazardous Waste
Operations and Emergency Response (HAZWOPER) training and/or other applicable training, plus annual refresher courses. The Contractor shall maintain documentation supporting training records in accordance with applicable OSHA reporting requirements and have the site-specific
Health and Safety Plan (HSP) on site, available for workers, AF, and/or regulatory review.
The Contractor shall be responsible for any damage caused to property by the activities of the
Contractor under this contract and shall exercise due diligence in the protection of all property
ATTACHMENT 1
24 APRIL 2024
located on the premises against fire or damage from any and all other causes. Any property damaged or destroyed by the Contractor incident to the exercise of the privileges herein granted shall be promptly repaired or replaced by the Contractor to a condition satisfactory to the COR or reimbursement is made by the Contractor sufficient to restore or replace the property to a condition satisfactory to the COR.
2.6 Photo Documentation
The Contractor shall prepare digital photographic documentation, as required to meet the objectives specified in this contract. The Contractor shall include photographic documentation of site(s) and building(s) under investigation, field activities, and sample locations. The
Contractor shall provide photo documentation to the AF as appropriate, as part of other deliverables, or at the request of the CO and/or COR.
2.7 Contractor Documentation
The Contractor shall create and maintain a Master Document List (MDL) for all documents, whether the document is a deliverable or not, which are prepared during the course of this contract. The MDL and its documents shall be readily available for submittal to the government.
A project website may be used to maintain all or portions of the document repository. The
Contractor shall maintain the MDL and project documents for the duration of the contract as specified in this contract and transfer custody to the AF within 90 calendar days prior to POP expiration. For project documents produced in the final 90 calendar days of the POP, the
Contractor shall submit an updated MDL and copies of subject writable and PDF documents as specified in this contract POP expiration. (CDRL A001)
The Contractor shall maintain a document repository for all documents generated during this contract. The repository is intended to be a single access point repository for all documentation.
The Contractor shall at the request of the COR be able to provide all writable files associated with project work such as reports, supporting data tables, figures, trend analyses, graphs, data, logbooks, field notes and any other documentation utilized in managing and maintaining the environmental program at the installation. The Contractor shall support coordination efforts with other contractors working onsite who may require access to these files. The Contractor shall prepare metadata sheets and consolidated report documentation including regulatory letters for applicable deliverables and submit electronic and/or hard copies as requested by the CO/COR to the AF administrative record (AR) management team for loading to the AR. At close-out, all repository documents will be transferred to DVD media and delivered to the COR.
Original documents such as software versions, GIS files (including layers), CADD files, modified PDFs, spreadsheets, and databases or other supporting data/files/information including figures, drawings, etc. utilized in managing and maintaining the environmental program at the installation shall be provided regularly at the request of the COR and shall also be included in the close-out DVD. The Contractor shall support coordination efforts with other contractors working onsite who may require access to this data.
ATTACHMENT 1
24 APRIL 2024
2.8 Record Keeping
The Contractor shall create and maintain in one location written (in bound, numbered logbook) and electronic records sufficient to recreate each sampling, analytical, testing and monitoring event, and shall make these records available to the AF upon request. The Contractor shall maintain records of, and derived from, all activities outlined in the appropriate portion of the
Quality Program Plan (QPP) supporting the generation of these sampling and analysis records.
The Contractor shall also retain written calculations using information obtained from sampling, analysis monitoring, and testing activities, to include all raw data. All information shall be provided to the AF upon request. (CDRL A001, A001D)
3.0 GENERAL REQUIREMENTS
The Contractor shall perform a full range of activities to meet all environmental construction and optimization services requirements, as specified in this contract.
3.1 Technical Plans and Reports
The Contractor shall provide technical plans and reports, as well as various other deliverables.
The Contractor shall complete these documents according to the most appropriate industry standard.
Deliverables are required as specified in this contract to demonstrate performance objective and milestone are met and for approval of payment. Most of these documents must be submitted for initial AF review followed by submittal to one or more regulatory agencies. The AF review of a document should not be construed as final approval or an indication that regulatory agencies will agree with the AF position.
The Contractor shall submit all plans, reports, and other deliverable documents in Working
Copy, Draft, Draft Final, and/or Final versions as appropriate for that specific document. Not all documents will require submittal of all versions. Multiple versions of documents may be generated by the Contractor including:
• Working Copy (or Internal Review) Documents – Working Copy documents are considered
“drafts” only in the sense that they have not been reviewed and approved by the AF. In all respects, Working Copy documents shall be complete; substantively correct and consistent with applicable laws, regulations, DoD/AF policies; in proper format; and free of grammatical and typographical errors.
• Draft and Draft Final Documents –Draft documents are the initial version of documents that have undergone AF review and are submitted to the appropriate regulatory agencies for review. However, some documents may initially be submitted to the regulatory agencies as
Final with any comments being incorporated into subsequent documents as appropriate. A
Draft Final document incorporating regulatory comments and submitted for regulatory agency review may also be required prior to Final document preparation.
ATTACHMENT 1
• Final Documents – At least one electronic copy of the Final document consisting of original productivity software files and all quality control data, drawings, and GIS-type information, shall be provided to the AF. Electronic copies should be compatible with the current AFCEC
Microsoft™ Office Suite and GIS software versions. All figures shall be delivered in original application files GIS format. In addition, an electronic version of the final document shall be submitted in a single portable document file (.pdf) format complete with electronic bookmarks.
3.1.1 Technical Plans
The Contractor shall be required to prepare technical plans such as:
• Uniform Federal Policy Quality Assurance Project Plan (UFP-QAPP) Addendum (CDRL
A007)
• Remedial Action-Operation (RA-O) WP(s) (Technical Memoranda or Letters) (WPs)
(CDRL A007)
• RPO WP(s) (Technical Memoranda or Letters) (WPs) (CDRL A007)
• CS001 Remedial Action (RA) WP /Remedial Design (RD) (CDRL A007)
3.1.2 Technical Reports
The Contractor shall be required to prepare technical reports (CDRL A001) such as:
• RPO Report (Technical Memoranda; include operations of CS001, hot spot removal and injections)
• CS001 Remedial Action Completion Report (RACR)
3.2 Quality Program Plan (QPP)
The QPP shall include a UFP-QAPP Addendum, and WPs in various formats (including addenda) Health and Safety Plan (HSP) (as required by 29 Code of Federal Regulations (CFR)
1910.120). Existing plans may be utilized where practicable and appropriate, and updated as specified in this contract.
3.2.1 UFP-QAPP
The Contractor shall prepare a UFP-QAPP addenda for the work to be performed under this contract. The current UFP-QAPP utilizes the Optimized UFP-QAPP Worksheets (USEPA, March 2012 or most recent version) and USEPA Guidance on Systematic Planning Using the
Data Quality Objectives (DQO) Process, February 2006 (or most recent version) and/or as specified by state regulations if necessary. (CDRLs A007)
3.2.2 Work Plans (WPs)
ATTACHMENT 1
24 APRIL 2024
The Contractor shall prepare WPs in various formats (including addenda) to comply with DoD, AF, USEPA, state, and local regulations regarding the proposed work effort. Existing WPs may be utilized where practicable and appropriate, and updated as specified in this contract. (CDRL
A007
3.2.3 Health and Safety Plan (HSP)
The Contractor shall prepare an HSP to comply with AF, OSHA, USEPA, state, and local health and safety regulations regarding the proposed work effort. The Contractor shall utilize, to the fullest extent possible, any existing related HSP, tailored specifically to the current effort. The
Contractor shall use OSHA guidelines for designating the appropriate levels of protection needed at the site(s) as applicable. The Contractor shall maintain written certification that the approved
HSP has been reviewed with all personnel that work at the project site prior to their mobilization.
(CDRL A008)
3.2.4 Chemistry Requirements
The Contractor shall provide an analytical laboratory accredited by the DoD Environmental
Laboratory Accreditation Program (ELAP). The Contractor shall maintain and be capable of achieving the most current version of the analytical laboratory requirements identified by the
DoD Quality Systems Manual (QSM) for Environmental Laboratories and the General Data
Validation Guidelines in the UFP-QAPP throughout the POP for the methods and matrixes required throughout the contract period. The selected laboratory(s) will have analytical capabilities to achieve adequate throughput capacity to handle the project’s analytical workload and turnaround times during all field activities while attaining QSM requirements.
The Contractor shall be responsible for the quality of all required chemistry services performed.
The Contractor shall be responsible for ensuring decisions are made with technically defensible data of known and documented quality. The Contractor shall ensure that all chemistry-related tasks are conducted in accordance with the UFP-QAPP.
The Contractor shall identify a Project Chemist as one of the key personnel in the UFP-QAPP.
The Project Chemist will act as a POC on all chemistry related issues and shall be responsible for ensuring that all DQOs are met and ensure decisions are made with technically defensible data of known and documented quality. Decisions shall be made with analytical results from DoD
ELAP accredited laboratories as specified in the UFP-QAPP.
3.2.5 Quality Assurance
The Contractor shall develop project specific DQOs consistent with the AF policy and objectives, and designed to ensure data of adequate quality are collected to support project decisions. DQOs shall be developed in consensus with the restoration project team and in accordance with UFP-QAPP and USEPA Guidance on Systematic Planning Using the Data
Quality Objectives (DQO) Process, February 2006 (or most recent version), and documented in the specific project WP, and/or as specified by state regulations if necessary.
ATTACHMENT 1
24 APRIL 2024
The AF will determine when the UFP-QAPP addendum and WPs are approved to proceed with field activities including sample collection and analysis. The Contractor shall ensure that all requirements specified in the UFP-QAPP and project WPs are met. If not met, the Contractor may be required to re-accomplish sampling at the Contractor’s expense. Data validation shall be performed by an independent, qualified, and experienced data validator in accordance with DoD
General Data Validation Guidelines and any applicable Modules. The Data Validation Standard
Operating Procedure shall be included in the WPs. (CDRL A007)
The Contractor shall provide Data Quality Assessment Reports (DQARs) to be included as an integral part of the applicable technical reporting efforts (no separate CDRL is required for this as it is included as part of the data review process for technical reporting and documented in the applicable A001) for all analytical data analyzed under this contract using the DoD General Data
Validation Guidelines. DQARs will include elements such as identifying the contract, delivery order number, and the laboratory, the number of samples analyzed, and any QC failures and corrective action as part of the back-up to the analytical reports. DQARs are required annually.
The Contractor shall ensure that all hard copy and electronic data deliverables supplied by the laboratory are complete and adequate to support the quality and usability of the data. Data packages shall meet federal and state standards and include all information required to re-create the analysis, including correspondence with the laboratory regarding Quality Assurance and
Quality Control (QA/QC) exceedances and documentation of corrective actions.
All laboratory services shall be conducted in accordance with the UFP-QAPP. Samples shall not be submitted for analysis until the UFP-QAPP addendum is approved by AFCEC.
The Contractor shall ensure that all requirements specified in the UFP-QAPP are met. If not met, the Contractor may be required to re-accomplish sampling at the Contractor’s expense. The
Contractor shall conduct audits, verify, and validate data, and perform corrective actions in accordance with the UFP-QAPP.
3.2.6 Laboratory Selection
The Contractor shall select a DoD ELAP accredited laboratory. This effort shall take into consideration any applicable state regulations as required. The laboratory(s) must be capable of maintaining and achieving accreditation to the most current version the DoD QSM throughout the period of performance for the methods and matrixes required in the UFP-QAPP.
3.2.7 Analytical Data Management
The Contractor shall ensure that all hard copy and electronic data deliverables supplied by the laboratory are complete and adequate to support the quality and usability of the data. Validated data packages shall be submitted to AFCEC and, if applicable the regulators, within 60 days of the sampling event, as required and communicated by the AF. Drinking water data (finished or non-finished) will be provided to the AF within 60 days by format defined by the AF. Data packages shall meet federal and state standards and include all information required to re-create
ATTACHMENT 1
24 APRIL 2024
the analysis, including correspondence with the laboratory regarding QA/QC exceedances and documentation of corrective actions. (CDRLs A011, A012)
3.2.8 Environmental Resources Program Information Management System (ERPIMS)
The Contractor shall submit an ERPIMS Data Submission Schedule which will be used to establish the framework for ERPIMS data submissions. (CDRL B005A)
The Contractor shall record and enter field and laboratory data and submit these data as specified in the latest ERPIMS Data Loading Handbook (DLH) using the latest version of the ERPIMS software utility (ERPTools). The AFCEC website offers the latest DLH, ERPTools client software, ERPIMS policy, Help Desk contact info, data submission requirements, ERPTools training schedules, and more (https://www.afcec.af.mil/What-We-
Do/Environment/Restoration/ERPIMS/Registration-Process/). Data submissions shall be error-free, pass all validation checks and fully comply with the ERPIMS DLH. The Contractor shall ensure that any required corrections are accomplished within both the POP and funding and specific requirements will be specified in this contract. The Contractor shall utilize the latest version of the ERPTools software to input/submit data for validation, import and submission.
Questions with regard to ERPTools software and training can be addressed to the ERPIMS Help
Desk. (CDRL B005B)
3.2.9 Computer-Aided Design Drawing (CADD) and Geographic Information Systems
(GIS) Updates
All products associated with this contract that provide a map/geospatial representation of the natural and built features (historical, existing, or planned) including installation maps, site plans, area development plans, walls-out as-built depictions, or other related overhead (plan) views of an installation (partial or entire) shall adhere to the following requirements:
All maps and associated data shall comply with latest published guidance and AF Adaptation version of the Spatial Data Standards for Facilities, Infrastructure, and Environment (SDSFIE).
The AF Adaptation of SDSFIE will determine file and feature class identification and definition, minimum attribution and valid domain values in accordance with official AF documents included in the Adaptation Release Package. GIS deliverables shall comply with AFCEC GIO published guidance in the “Data Dictionary”, the latest version of the AFCEC/CIB Master
BRAC Geospatial Guidance control document, and Federal Geospatial Data Committee (FGDC) metadata standards per the ArcGIS 10.x template. CADD data shall comply with the latest version of the AF Adaptation of SDSFIE for GIS data and A/E/C 5.0. Any future updates to the
Master BRAC Geospatial Guidance will be provided to the Contractor by AFCEC/CIB as they are developed.
Geospatial data shall be delivered in a geo-referenced GIS format (with one-to-one cardinality between spatial records and attribute records in accordance with the latest AF Adaptation version of SDSFIE) using the Environmental Systems Research Institute’s (ESRI) geospatial file database formats. All attribute data as specifically outlined in the contract shall be included https://www.afcec.af.mil/
ATTACHMENT 1
24 APRIL 2024
either in the GIS data file or as a separate table with an AF Adaptation of SDSFIE identified primary/foreign key used to relationally join the separate table with the associated GIS geodatabase file. All geospatial data shall be delivered in the World Geodetic System of 1984
(WGS84) reference system using, geographic coordinates (latitude/longitude) or, projected to the appropriate zone of the Universal Transverse Mercator (UTM) Grid System, using feet or metric coordinate units per the coordinate system used. The preferred AF standard is WGS84. Further guidance on mapping units, coordinate systems and projections can be made available by the
COR.
It is the responsibility of the Contractor to collect all geospatial data using mapping-grade or survey-grade Global Positioning Systems (GPS) or comparable traditional survey methods. In the case of contracts involving utility construction, location and attribute data will be obtained at the time of excavation. Specific precision requirements shall be established at the contract level.
Source data and product data remain the property of the AF. It is the Contractor’s responsibility to be prepared to explain and demonstrate the company’s process for protecting all geospatial data, including geometry, attributes, metadata, topologies, and relational database schemas and operations used in association with this PWS. The Contractor shall sign a non-disclosure agreement for a specific contract before source data are released, if required. Information about security and nondisclosure requirements will be provided by the COR for the contract.
Installation map data, source and/or product, may be qualified by the Government to be
“sensitive, but unclassified”, as required in this contract. The intent of this language is to prevent intentional or unintentional dissemination of “sensitive, but unclassified” information to include unauthorized access to the source and product data by any entity wishing to do harm to the AF or
United States Government while the data resides on the Contractor’s computer network. The
Contractor is not authorized to release this information to any third party without the explicit consent of the CO, COR, and AFCEC/CIB if required, and dissemination shall be in accordance with established AF policy and guidance. All source information qualified as “sensitive, but unclassified” shall be returned to the Government POC or destroyed with written concurrence from the COR upon completion of this project. (CDRLs A005, A006)
4.0 GENERAL ENVIRONMENTAL REQUIREMENTS
The Contractor shall perform a full range of environmental restoration activities to meet the objectives specified in this contract.
The Contractor shall execute environmental restoration projects in accordance with applicable federal, state and local laws and regulations. The Contractor shall evaluate, complete, and modify designs as necessary, and plan, install, construct, test, and decommission any site as required to achieve the performance objectives of this contract. The Contractor shall document all activities as stated herein.
The Contractor shall perform incidental support such as designing, planning, programming, scoping, studying, investigating, evaluating, and consulting on environmental engineering and construction efforts. The Contractor shall also provide training to AF and other contractor personnel regarding the O&M of equipment, systems, and facilities during equipment
ATTACHMENT 1
24 APRIL 2024
shakedown periods. The Contractor shall perform O&M of equipment, systems, and facilities prior to acceptance by the AF.
The Contractor shall incorporate green and sustainable remediation (GSR) techniques to the extent practicable. GSR considers the environmental impact of remedial activities during the remedy selection process. Incorporating GSR into an environmental restoration project includes evaluating activities and selecting a remedy that minimizes the environmental impact from the remedy yet provides the maximum environmental benefit to the cleanup over the entire life of the remedial project.
4.1 Site Characterization
The Contractor shall perform scoping, field investigation, and sampling/analysis that characterizes environmental conditions as required to achieve the performance objectives of the site. The Contractor shall identify specific site characterization activities proposed to achieve the performance objectives. (CDRL A001)
4.2 Site Preparation
The Contractor shall perform site work as necessary to prepare sites for restoration activities.
Security and access controls shall be implemented to prevent unauthorized entry to sites and to protect wildlife from site exposure, where applicable. The Contractor shall survey existing utilities to determine adequacy and need for modifications to support site activities. The
Contractor shall obtain appropriate approvals and shall build connections or new systems for electrical power, water, sewer, gas distribution, telephone, and other utilities, as required, to meet the objectives specified in this contract. The Contractor shall be responsible for the provision and cost of utilities with implementation of existing and proposed remedies, including activities such as installation of primary and temporary power and individual meters for necessary utilities.
Due to the lack of a state utility locating service at Galena, geophysical surveys are required for all subsurface work in addition to hand digging where appropriate to avoid damaging underground utilities. (CDRL A001)
4.3 Conservation
Activities shall be planned and implemented in a manner that protects existing site utilities, structures, surface features, service operations, monitoring and other types of wells, and the general site environment. This includes the protection of prehistoric and/or historic sites identified in the base Integrated Cultural Resources Management Plan; endangered/threatened wildlife species and their potential habitats; exemplary natural areas as defined in the base
Integrated Natural Resources Management Plan; and trees, shrubs, and other vegetation not in the affected zone from dust damage, soil compaction, and physical contact with machines and equipment. Work activities shall be coordinated with the AFCEC COR and BRAC
Environmental Coordinator (BEC) to ensure compliance with these requirements. The
Contractor shall conduct all operations and activities with the intent of reducing the amount of pollution generated. Specific areas to be focused on are generation of solid waste, use of hazardous materials, use of ozone depleting chemicals, generation of hazardous waste, and use of
ATTACHMENT 1
24 APRIL 2024
energy and water. During site work the Contractor shall plan, construct, operate, maintain, optimize, and decommission systems necessary to control storm water run-on and run-off; and transport surface water drainage to a treatment plant, discharge location, or any other appropriate destination. (CDRL A001)
4.4 Environmental Construction
The Contractor shall perform construction, restoration, repair, maintenance, and demolition of utilities, real property systems, and infrastructure in support of environmental restoration requirements as specified in this contract. Construction activities will be in conformance with state, federal, and local standards and regulations. The Contractor shall erect or install support buildings, equipment enclosures, and storage facilities for construction materials and contaminated material awaiting disposal as specified in this contract.
The Contractor shall conserve topsoil that is verified to be uncontaminated by removal, storage, or redistribution during environmental remediation activities, and as such, is the responsibility of the Contractor to ensure impacts to this contract are limited by employing these practices. All reasonable measures shall be taken to minimize and suppress fugitive emissions of dust, vapors, and other site materials during site work.
4.4.1 Delivery and Warranty of Installed Equipment and Systems
The…