NEC Ft. Leonard Wood, MO
Introduction:
The Fort Leonard Wood Network Enterprise Center (NEC) Land Mobile Radio (LMR) Towers require numerous structural repairs to meet FAA and Army safety standards.
Scope of Work Contractor shall provide all management, tools, supplies, equipment, labor, and furnish all materials necessary to perform corrective maintenance on the LMR towers located at: Building 1000, MP Hill, and Range Control on Fort Leonard Wood.
Place of Performance Fort Leonard Wood, Missouri:
Building 1000 LMR Tower
MP Hill LMR Tower
Range Control LMR Tower Work Requirements
1. Building 1000 LMR Tower Site 150’ self-supported
a. The Contractor shall
i. Repair grounding on waveguide/ice bridge
ii. Properly ground fence
iii. Provide and install RF radiation warning, and high voltage broadcast equipment signs
iv. Repair tower’s original coating
v. Repair/Replace structure/section bolts and pal/lock nuts
vi. Correct spacing on existing coax hangers and install missing line hangers
vii. Repair/Replace existing antenna mounting hardware
2. MP Hill LMR Tower Site 120’ self-supported
a. The Contractor Shall
i. Properly ground fence
ii. Provide and install RF radiation warning, and high voltage broadcast equipment signs
iii. Repaint entire tower FAA Daymark requirement
iv. Paint feedlines located on outside of tower
v. Repair/Replace bent, rusty, damaged tower diagonals
vi. Repair/Replace structural/section bolts
vii. Install safety climb device
viii. Repair/Replace missing or bent ladder rungs, climbing pegs, or sections
ix. Properly secure feedlines
x. Install lightning rod
3. Range Control LMR Tower Site 260’ Guyed-support
a. The Contractor Shall
i. Install missing buss bars
ii. Properly ground anchor heads
iii. Repair grounding on waveguide/ice bridge
iv. Properly ground waveguide/coax on top and bottom of run
v. Properly ground fence
vi. Provide and install RF radiation warning, and high voltage broadcast equipment signs
vii. Properly align anchors with tower legs and center
4. Contractor shall adhere to guidelines established in the Telecommunications Industry Association Structural Standard publication TIA-222-H, dated Oct 5th 2017, and the Army Safety Program AR385-10
5. Contractor will coordinate with the FLW-NEC POC on date and times of arrival to Fort Leonard Wood
a. Contractor shall provide the FLW-NEC POC with proper documentation for technicians entry onto Fort Leonard Wood
i. FLW-NEC POC will provide what information is needed after contract award
Quality Assurance
1. The Government will monitor the Contractor’s performance while onsite
Deliverables
1. A job site walk through is required to be performed with Network Enterprise Center personnel before any work is to start.
2. The Contractor shall keep the quality assurance inspector apprised of any issues at the worksites. POC Andrew Kirk @ 573-563-8298 or andrew.s.kirk.civ@army.mil.