This is a Performance Work Statement (PWS) for weed and pest control services at Lake Isabella Dam and Headquarters in Kern County, California, approximately 42 miles east of Bakersfield. The contract consists of a Base Year with four option years, with work performed seven days per week from sunrise to sunset. The contractor must provide all labor, materials, supplies, permits, licenses, equipment, and supervision necessary to complete the work.

The scope of work includes post-emergent and pre-emergent herbicide treatments on approximately 37 acres across multiple locations: Isabella Dam (6 acres), Isabella Auxiliary Dam (19.6 acres), Emergency Spillway (1.4 acres), Headquarters (3.8 acres), and Storage Yard (6.3 acres). Treatment schedules vary by location, with Isabella Dam and Auxiliary Dam treatments occurring February 1–May 31 and October 1–December 1, while Headquarters and Storage Yard treatments occur March 1–June 30 and November 1–January 1. Additionally, the contractor must apply pest control treatments to approximately 17,700 square feet of buildings within the first week of every month, targeting flying and crawling pests including ants, spiders, flies, gnats, ticks, roaches, earwigs, mosquitoes, and mice. All chemicals must be approved by federal and state regulations and applied with blue dye for visibility. No spraying shall occur within 24 hours of forecasted rain, and all areas must be posted with warning signs. The contractor must achieve a minimum 90% effective kill rate as determined by Corps of Engineers Quality Assurance inspectors. Required contractor submittals include certificates of insurance ($1,000,000 general liability and workers' compensation), safety hazard analysis, quality control plan, accident prevention plan, supervisor identification, state-qualified herbicide applicator licenses, monthly exposure reports (Form 94), Material Safety Data Sheets, pesticide use reports, AT-OPSEC training documentation, and E-Verify Program compliance. Invoices shall be submitted monthly in arrears upon completion of tasks, with payment made at contract unit price only for services actually performed. The Quality Assurance Surveillance Plan requires 100% completion of all tasks according to schedules and work performed to industry standards 95% of the time, with the contractor required to reperform any non-conforming work at no additional cost to the government.

View the file

Other files

File Type Posted
Lake Isabella Dams - Weed and Pest Control QAs.pdf PDF
Wage Determination 2015-5603.pdf PDF
Solicitation.pdf PDF
Maps.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STAEMENT

Isabella Dams, Weed and Pest Control Services

May 13, 2026

A. General Information:

1. Location: The work required under this contract is for Weed and Pest Control Services for Lake Isabella Dam and Headquarters. Isabella is in Kern County, California approximately 42 miles east of Bakersfield, CA. The contractor shall provide all labor, materials, supplies, permits, licenses, equipment, and supervision necessary to accomplish all work required for this contract.

2. Period of Performance: Contract consists of a Base Year and Four Option Years.

3. Authorities/Technical Direction: The Contractor shall take no direction from any Government employee or any other person other than the Contracting Officer (KO) that changes the terms and conditions of this contract action, the scope, or any change that impacts the cost, price or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the Changes clause of this contract when the contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contractor Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer. Contracting Officer Representatives (CORs) are limited to the authorities stated in the COR appointment letters.

4. Meetings: Pre-Work Meeting: The Prime contractor shall contact the COR to schedule an in-person pre-work meeting to discuss all elements of this contract and turn in all submittals prior to work commencing. The COR shall determine the date, time and location of this meeting.

5. Contractor Submittals:

a. Certificates of Insurance (General Liability and Worker’s Compensation at $1,000,000.00)

b. Safety Hazard Analysis - c. Quality Control Plan

d. Accident Prevention Plan (APP)

e. Name and telephone numbers of supervisor if other than the contractor.

f. Herbicide Applicators. A list of names of state qualified herbicide applicators.

Herbicide License shall be submitted.

g. Exposure Report – Form 94 (Man-hours worked). Submit along with invoice.

h. Monthly Invoice Template.

i. Material Safety Data Sheets (MSDS) for compounds to be used for the contract.

j. Pesticide Use Report for the prior calendar year. Submitted by January 31.

k. AT-OPSEC Initial Submittal and updates after

l. E-Verify Program

6. Invoicing and Payments: Invoices for payment shall be submitted upon completion of tasks as outlined in the PWS of this contract. Final invoice(s) shall be marked “Final”. Invoices shall be submitted to:

Original invoice only WITHOUT additional information or supporting documentation:

USAED, FINANCE CINETER

ATTN: CEFC-FP

5270 Integrity Drive Millington, TN 38054-5005 or CEFC-payments@usace.army.mil

One copy of each invoice WITH all required information including any necessary supporting documentation:

Isabella Dams Attn: Pest Control COR

Name and email will be provided at time of award

The contractor shall only be paid for those services performed. The Government shall pay the Contractor upon submission of proper invoices for services delivered and accepted for the portion of the work actually performed under the contract. Payment shall be made monthly in arrears at the contract unit price

Part B. Scope of Work:

1.General Information: Work can be performed (7) days a week, Sunday through Saturday from Sunrise to Sunset. Pest control to be completed inside Lake Isabella Dams Headquarters buildings shall be done between set office hours, while also cautious of federal holidays. No service shall be done within any 24-hour time frame of forecasted rain. Areas to be sprayed will be posted to warn the public that spraying activity is being performed. Applications shall have a blue dye added to the compound to allow treated areas to be visible.

The contractor shall provide all labor, equipment, materials, supplies, transportation, and supervision necessary to perform all weed and pest control services at Lake Isabella Dams and Headquarters buildings. The contractor shall, without charge, correct work found by the Contracting Officer Representative (COR) not to conform to contract requirements, or quality requirements. Quality shall be evaluated by inspection of completed work after an appropriate period. Inspections will be conducted by assigned Quality Assurance inspector of the Corps of Engineers. Quality shall be determined by the effective rate of kill and for the purpose of this contract shall be a minimum of 90%.

2.Recommended Chemicals mailto:CEFC-payments@usace.army.mil

A. All chemicals used must be approved for use by federal and state regulations.

Chemicals used under this contract shall not be mixed on Government property, nor shall tanks or equipment be washed and cleaned on property.

B. Public posting of chemicals and applications shall be posted before any work is to be performed.

3. Isabella Dam: A post-emergent treatment shall be applied on all vegetation from February 01

– May 31. A pre-emergent treatment shall be applied on the entire described surface from October 01 – December 01. Applications are below, see maps for reference.

a) Downstream toe of the Dam (1.7 acres)

b) Partial upstream face of the dam, approximately halfway to highwater mark. (2.5 acres)

c) Perimeter of the Control Tower (.4 acres)

d) Crest road (1 acres)

e) Fence and Rock Line with 2’ width (0.1 acres)

f) Gauging station, Accelerographs, and access (0.2 acres)

g) Perimeter of signs, culverts, power poles (0.1 acres)

Approximate total of 6 acres

4. Isabella Auxiliary Dam: A post-emergent treatment shall be applied on all vegetation from February 01 – May 31. A pre-emergent treatment shall be applied on the entire described surface from October 01 – December 01. Applications are below, see maps for reference.

a) Downstream toe of the Dam and abutment (2.3 acres)

b) Partial upstream face of the dam, approximately halfway to highwater mark. (10.2 acres)

c) Abutments and drainage areas (4.5 acres)

d) Crest of the dam (2 acres)

e) Accelerographs and pumpstation (0.2 acres)

f) Fence Line with a 2’ width (0.3 acres)

g) Perimeter of signs, culverts, power poles (0.1 acres)

Approximate total of 19.6 acres

5. Emergency Spillway: A post-emergent treatment shall be applied on all vegetation from February 01 – May 31. A pre-emergent treatment shall be applied on the entire described surface from October 01 – December 01. Applications are below, see maps for reference.

a) Spillway Labyrinth Wall with a 4’ buffer (0.4 acres)

b) West Spillway Access (0.2 acres)

c) East Spillway Access (0.3 acres)

d) East Spillway fence line with a 2’ width (0.2 acres)

e) Drainage area (0.2 acres)

f) Perimeter of signs, culverts, power poles (0.1 acres)

Approximate total of 1.4 acres

6. Headquarters: A post-emergent treatment shall be applied on all vegetation from March 01 – June 30. A pre-emergent treatment shall be applied on the entire described surface from November 01 – January 01. Applications are below, see maps for reference.

a) Perimeter of Administration building (0.1 acres)

b) Area of flower beds, picnic areas, fencing (0.6 acres)

c) Solar Farm (0.3 acres)

d) Pump house and entry road (0.4 acres)

e) Drainage area and fencing (0.5 acres)

f) 3’ buffer on roadways (1.5 acres)

g) Roadway pullouts (0.3 acres)

h) Perimeter of signs, culverts, power poles (0.1 acres)

Approximate total of 3.8 acres

7. Storage Yard: A post-emergent treatment shall be applied on all vegetation from March 01 – June 30. A pre-emergent treatment shall be applied on the entire described surface from November 01 – January 01. Applications are below, see maps for reference.

a) Entire Storage yard (4.8 acres)

b) Water Well, including access road (0.4 acres)

c) Sand and rock pile (1 acres)

d) Perimeter of signs, culverts, power poles (0.1 acres)

Approximate total of 6.3 acres

8. Pest Control: Treatment shall be applied to all building inside and out located on Lake Isabella within the first week of every month (Head Quarter, Aux Dam Maint. Storage Yard, Aux Dam Freefield and Main Dam Control Tower listed below). The targeted pests are as follows: Variety of flying and crawling pests (ants, spiders, flies, gnats, ticks, roaches, earwigs, mosquitoes, and mice).

a) Head Quarters: Admin Building (4500 sqft), Storage Shed (5000 sqft), Flammable Storage Building (500 sqft), Maintenance Shop (2000 sqft), Water Tank Pumphouse (300 sqft), Switchgear Cabinets, Solar Power Cabinets, and Emergency Generator (500sqft)

b) Aux Dam Maintenance Storage Yard: Maintenance Garage (600 sqft), Core Sample Boxes (1400 sqft), Conex Containers (1000 sqft)

c) Aux Dam Freefield: Water Wellhouse (100sqft)

d) Main Dam Control Tower: 1st Floor, 2nd Floor, and 3rd Floor (1800 sqft).

Approximate total of 17,700 sqft

C. Contractor’s Responsibility:

1. Personnel:

a. General Requirements: The Contractor shall provide an adequate number of fully qualified personnel to perform the work specified herein. It shall be the Contractors responsibility to ensure that personnel fulfill the requirements of the contract.

b. Supervision: During regular working hours, the Contractor shall designate in writing who shall have full authority to direct the work required by this contract. The designated supervisor shall be able to understand, speak, read and write the English language. It is required that the prime contractor conduct Quality control of work, in person, at the job site, at a minimum once a month.

c. Identification of Contractor Employees and Vehicles: The Contractor shall furnish their employees, standardized uniforms with a company patch or embroidered identification on the breast pocket or on the sleeve at the top of the arm, within 30 calendar days after notice of award of the contract. Any employee hired 30 calendar days after award of the Contract shall be in the required uniform within 14 calendar days of the date of hire. Contractor uniforms shall not resemble U.S. Army Corps of Engineers uniforms. Contractor employees and subcontractors shall wear these uniforms at all times they are performing services under this contract.

Exceptions may be granted by the COR for short-term workers, or during disasters, emergencies, or special circumstances specified by the COR. Stained or faded uniforms shall not be worn. All vehicles used by the Contractor to perform services under this contract shall be identified with the company name prominently displayed on the outside of both front doors of each vehicle in a professional manner to provide an attractive and readily visible means of identification.

2. Safety: All installation safety regulations shall be followed. Comply with the most current edition of USACE EM 385-1-1, and all applicable federal, state, and local laws, ordinances, rules and regulations including but not limited to 29 CFR 1910 and 29 CFR 1926.

a. EM 385-1-1 can be viewed at the following website:

http://www.publications.usace.army.mil/USACEPublications/EngineerManuals

All project-associated activities shall be performed without damaging or contaminating adjacent work and areas. Where such work or areas are damaged or contaminated, the Contractor shall restore work and areas to the original condition at no additional cost to the Government.

b. All accidents shall be reported to the Safety Office through the COR. This is to be accomplished within the same shift, preferably as soon after the accident as is practical.

Fill out an Occupational Safety and Health Administration (OSHA) Form 300; and ENG 3394 shall be submitted to the Safety Office 5 days after an accident. In the event of serious injury or damage, work will stop, and everything will be left in place exactly as it was at the time of the accident, except when the possibility of more damage or injury exists. Medical expenses for Contractor personnel are the responsibility of the Contractor.

c. Use a qualified person to prepare the written site-specific Accident Prevention Plan (APP). Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1. Cover all paragraph and subparagraph elements IAW USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM 385-1-1, Section

1. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.

d. The equipment used by the Contractor for the specified service shall be in satisfactory operating condition and shall be maintained in good condition. The Government reserves the right to require the Contractor to discontinue the use of unsatisfactory equipment and to require that such equipment be replaced with acceptable equipment to maintain contract compliance. The decision of the Contracting Officer as to serviceability of the equipment shall be final. Equipment shall meet current Federal, State and local safety requirements and all applicable requirements of the USACE EM 385 1 1.

NOTE: An observed violation of safety requirements shall be grounds for the Government to stop work. Such work shall not continue until the violation is corrected.

e. Reporting: The contractor shall report any needed repairs, malfunctions, or damage of government property affected under this contract to the COR.

f. Vehicles: All vehicles used for the completion of this contract shall be in accordance with all state, county, and federal regulations. Proof of insurance shall be provided to the COR prior to commencement of work.

g. Safety Exposure Report: The contractor shall complete and submit to the COR a monthly

Safety Exposure Report, CESPD Form 94, documenting the total number of person-hours expended for each month of service, it is the contractor's responsibility to provide additional copies. Failure to submit a Safety Exposure Report with monthly invoices may delay payment for services performed. Negative reports are required.

3. Security:

a. General Security Requirements and Guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the COR. Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

b. AT-OPSEC: Antiterrorism (AT) Level 1 Training: All contract personnel requiring routine access to Army installation, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level 1 awareness training.

All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR, within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:

https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf; or it can be provided by the COR in presentation form which will be documented via memorandum.

c. Physical Security and Access Control Requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

d. Suspicious Activity Reporting Training (e.g., iWatch, CorpsWatch, or See

Something, Say Something): All contract personal should revive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager., security representative or law enforcement entity.

e. Pre-screen Candidates Using E-Verify Program: Contractors shall comply with the requirements set forth in Employment Eligibility Verification in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws. An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

4. Storage Area:

a. The Government shall not provide the Contractor with a designated area of storage.

Part D – Government Responsibilities:

1. Government Furnished Property: None

2. Inspection/Acceptance of Services:

3. The Government will not pay for services not performed. The COR will conduct random checks to ensure compliant services are being performed. Quality Assurance Surveillance Plan:

The Government shall monitor the Contractors’ performance in each functional area under this contract and reserves the right to use whatever additional surveillance procedures are deemed appropriate. The Government shall monitor the Contractor's services using the random sampling method, the planned sampling method and/or the 100% inspection method. The Government reserves the right to change or alter the type of inspection plan at its discretion at any time.

Performance Assessment Plan:

a. Monitoring Performance. During the course of the evaluation period, the COR will track Contractor performance. Interim (mid-term) evaluations may be provided to identify strengths and weaknesses in the Contractor's performance during the period being evaluated. At the end of the period, the COR will assess the Contractor's performance in accordance with the Quality Assurance Surveillance Plan (QASP) and report to the Contracting Officer.

b. Contractor Self-Assessment. Following each evaluation period, the Contractor may provide a written self-assessment of its performance to the COR to be considered in its report to the Contracting Officer. The self-assessment shall be submitted not later than 5 working days after the end of each evaluation period. The self-evaluation shall not exceed 1 page per PRS element. The self-assessment shall address both the strengths and weaknesses of the Contractor's performance during the evaluation period. Where deficiencies in performance are noted, the Contractor shall describe the actions planned or taken to correct such deficiencies and avoid their recurrence. The self-assessment itself will NOT be the basis for the payment re-calculation determination.

c. COR Recommendation. The COR will consider all evaluations and any other pertinent information, including Contractor self-assessment, and will prepare a report for the Contracting Officer with findings and recommendations. The Contractor will be provided a copy of the draft findings and recommendations of the COR and will be afforded the opportunity to identify factual errors. The COR's draft recommendation is not subject to negotiation, and the COR will not engage in discussions with the Contractor. Any errors identified by the Contractor will be addressed by the COR in its final report. The Contractor will be provided a copy of the final COR report at the same time the report is submitted to the Contracting Officer.

d. Payment Determination. The Contracting Officer may meet with the COR to discuss the COR's report. The Contracting Officer will make a final determination in writing as to the percentage of work successfully completed, and the resulting payment to be made. A copy of the determination will be provided to the Contractor no later than 45 calendar days after the end of the period being evaluated. All Contracting Officer decisions regarding payment re-calculations are unilateral decisions made solely at the discretion of the Government.

e. Payment Re-Calculations. Notwithstanding any other clause of this contract, payment re-calculations will be made within the later 60 days after the end of the evaluation period or 30 days after receipt of an approved invoice.

f. The Quality Assurance Surveillance Plan is one evaluation method the government uses to surveillance performance to determine whether the Contractor meets the standards of performance as defined in the PWS. The absence of a QASP for any contract requirement, however, shall not detract from its enforceability or limit the rights or remedies of the government under any other provision of the contract in determining the quality of the Contractor performance.

QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

Performance Requirement

Summary (PRS) Acceptable Quality Level Means of

Measurement Remedy

Contractor shall comply with the

Performance Work Statement Tasks as outlined in Part B.

a. Timeliness - 100% Completion of all tasks in accordance with provided schedules.

b. Quality - All work is performed to an industry standard 95% of the time

Periodic or 100%

Surveillance

Inspection by the Government

Customer Compliant

Contractor shall re-perform at no additional cost to the government until AQL is reached.