PWS.docx

DOCX document 6 MB Posted

Attached to
B156 Fence Removal and Extension
Solicitation number
FA4460-24-Q-0271
Issued by

About this file

This document is a Performance Work Statement (PWS) for the removal and extension of an existing chain link fence at Building 156 on Little Rock Air Force Base in Arkansas. The contractor shall provide all necessary personnel, transportation, tools, equipment, materials, and services to remove the existing fence, furnish and install an extension to match the existing fence, and relocate two existing gates. The work shall be completed within 60 days of material arrival, with the estimated delivery date required to be provided to the Contracting Officer Representative (COR) within 10 days of contract award. The fence extension shall be approximately 853 linear feet, with the contractor required to remove a 194-foot section and the fence surrounding a propane tank. The new fence must closely match the existing in height and post spacing, with a three-strand climb-resistant top. The contractor must also relocate the existing 16-foot and 10-foot gates as specified.

View the file

Other files

File Type Posted
Addendum to 52.212-1 and 52.docx DOCX document
Combo B156 Fence Printed.pdf PDF
Provisions and Clauses_FA446024Q0271.pdf PDF
Wage Determination .txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FENCE REMOVAL AND EXTENSION

AT BUILDING 156 FIRE TRAINING AREA

1. DISCRIPTION OF SERVICES

1.1. The contractor shall provide all qualified personnel, transportation, tools, equipment, materials and services required remove, furnish and install an extension to the existing chain link fence at building 156 on Little Rock AFB, AR 72099. The contractor shall accomplish all services below to meet the requirements of this Performance Work Statement (PWS). Work shall be in compliance with all Federal, State and local regulations, codes and license requirements. Work shall be accomplished within 60 days of material arrival. Estimated delivery date of material is required to be sent to the Contracting Officer Representative (COR) within 10 days of contract award.

1.2. The requirements official has determined that none of the services to be performed are inherently governmental.

2. SAFETY AND REGULATORY REQUIREMENTS

2.1. The fence is located outside of building 156. Contractor shall coordinate with Contracting Officer Representative (COR) for access to building 156. It’s estimated that 100% of the work will need to be performed during normal working hours of 0800-1600 M-F excluding federal holidays and will not be considered as overtime hours. Contractor shall be escorted by government personnel for access to building 156. The intent is to complete all work within 60 calendar days. Escort shall be provided by LRAFB.

2.2. Pre-Install Requirements: Before services are commenced, the contractor shall inspect the work site and ascertain all information for the diligent performance of the service(s). The contractor shall notify the ordering agency of any conditions that prevent the suitable completion of these services to include operations that could endanger Government personnel or property and require appropriate abatement action. If the contractor discovers problems associated with the work after starting, he or she shall immediately notify the Contracting Officer (CO) for their approval if the work is to continue. Coordinate with the Government designated representative to have utilities/fire alarms etc…turned on or off during the competition of the task.

2.3. Disposal of waste: All waste disposals are the responsibility of the contractor to include any fees or permits. Recycling containers may be provided if needed for the operation. Coordinate through your government representative or Contracting Officer Representative (COR).

2.4. All work shall be accomplished in accordance with all UFGS 32-31-13, UFC 4-022-03 and ASTM Standards for Fence Materials and Products regarding the installation and repairs. Contractor must use newest regulations.

2.6. Clean/wipe/vacuum all areas to ensure the work area is clean from all work done. Protection of the work area is a must.

3. WORK REQUIREMENTS

3.1. Material provided by the contractor.

3.1.1 The contractor shall provide all chain link fencing matching existing fence in gauge and height including rails, post and guide wire material.

3.2. Installation

3.2.1. Contractor must remove required fence to expand and install fully operational chain link fence matching in size and material to the existing fence surrounding the fire training area. Extend the fence line approximately 853 linear feet. Remove the 194’ section of fence on the western most edge. Remove the fence surrounding the propane tank. Installation shall closely match existing fence in height and post spacing. Refer to Appendix B for plan. Posts shall be anchored in a minimum 12 inch wide by 24 inch deep concrete footing. Fence shall have a three-strand climb resistant top to match existing fence.

3.2.2. Contractor must relocate the existing 16’ gate to the entrance and the existing 10’ gate would be relocated to the east edge of the expansion. Refer to Appendix B for plan.

3.2.3. Contact Sherrita James (19 CES/CEOER 987-5208, sherrita.james@us.af.mil) when project is ready for commissioning.

4. GOVERNMENT FURNISHED EQUIPMENT - None

5. GENERAL REQUIREMENTS

5.1. Contractor personnel and vehicles must possess appropriate passes. These shall be obtained from Installation Security Forces Pass and ID at the Vehicle Inspection Center.

5.2. The Contractor is subject to all installation fire, safety, security, and traffic regulations.

5.3. The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.

5.4. The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor. Enforcement of workplace safety laws is the responsibility of the agency specified in the applicable law.

5.5. The Contracting Officer may notify the Contractor of hazards in Contractor operations that endanger Government personnel or property and require appropriate action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.

5.6. Accident prevention principles must be thoroughly integrated into all operations. Unsafe conditions and practices, as identified by the designated representative, must be corrected immediately.

5.7. Contractor Employees: While on the installation, the contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the Contracting Officer as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the organization or by wearing appropriate badges containing the organization's name and the employee's name. Contractor personnel must wear issued base identification cards at all times while on the installation.

5.8. Service contracts shall require contractor employees to identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with government personnel. In addition, contracts shall require contractor personnel to appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.

6.0. WARRANTY

6.1. Contractor shall guarantee all material, workmanship and labor from defects for a period of 12 months from the date of acceptance of the work. A warranty letter detailing the work accomplished per facility is required to be furnished to the government representative upon acceptance of the work.

7.0. APPENDIXES

APPENDIX A: Commander’s Environmental Policy APPENDIX B: Structural Fencing Plan