This document is a Performance Work Statement (PWS) for the replacement of garage door openers at the U.S. Coast Guard IPD St. Louis facility in Saint Louis, Missouri. The PWS outlines the requirements for a contractor to remove and replace four existing garage door openers, including two in the Carpentry Shop, one in the center bay, and one in the Welding Shop. The work is to be completed in accordance with the PWS, and a firm-fixed-price purchase order will be awarded to the Lowest Bidder Technically Acceptable. This opportunity is set aside 100% for small businesses, and all contractors must be actively registered in SAM.gov. The related federal contract opportunity, Solicitation Number 70Z02924QNEWO0018, seeks qualified individuals or firms to provide all labor, materials, and equipment necessary to perform the required work. A site visit is recommended prior to submitting a quote.

View the file

Other files

File Type Posted
Construction Clauses Provisions FAC 2023-01.doc DOC document
Garage door SF1442-14b.pdf PDF
Wage determiniation (003).txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCG IPD ST. LOUIS GARAGE DOOR OPENER REPLACMENT

U.S. Coast Guard IPD St. Louis

Performance of Work Statement

Garage Door Opener Replacement

Located at:

100 Arsenal St Building 17 Saint Louis, MO 63118

GENERAL REQUIREMENTS

1. General

1.1. The United States Coast Guard is accepting quotes for qualified individuals or firms to provide all labor, materials, and equipment necessary to conduct. The intent of this project is to replace the old garage door openers, as defined in this scope of work, located at US Coast Guard IPD St. Louis, Saint Louis, MO. Contractor shall furnish all labor, tools, materials, transportation, equipment, supervision, and personnel to perform the removal and installation of new garage door openers at IPD St. Louis. No repairs outside the Performance of Work Statement criteria are authorized without permission from the contracting officer or their representative.

1.2. Prior to submitting a quote, it is mandatory to examine the Performance Work Statement (PWS) and it is highly recommended to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed.

All work is to be completed in accordance with the performance work statement. This will be a firm- fixed priced purchase order awarded to the Lowest Bidder Technically Acceptable (LBTA). This is set aside 100% for small business. All contractors must be actively registered in SAM.gov.

1.3. LOCATION: Project site is located at Base St. Louis Service Base, 100 Arsenal Street. St. Louis, MO. 63118.

1.4. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Perform all on-site work between the hours of 6:00 AM and 4:00 PM, Monday through Friday (federal holidays excluded), unless otherwise approved by the Contracting Officer or Contracting Officer’s representative.

WORK ITEM 1: GARAGE DOOR OPENERS

2. SCOPE

2.1. Intent: This work item describes the requirements for the Contractor to remove and replace four (4) garage door openers.

2.2. Locations: 2 openers in the Carpentry Shop, 1 in center bay (big door), 1 in Welding Shop

1.3 Government Furnished Property: None

3.1 Removal of old garage door openers, see Fig A.

3.2 Install new garage door openers.

3.2.1 Mount new garage door opener.

3.2.2 Complete operational test of new garage door opener.

FIG. A

4. NOTES

4.1 Site Visit: Site visits are recommended. All site visits should be scheduled with the Contracting Officer, Facilities Engineer and/or their representative.

POC: DCC John Eister Email: John.J.Eister@uscg.mil Phone: (314)-771-6044 x2107

POC: IPD Supervisor James Tepen Email: James.A.Tepen@uscg.mil Phone: 314-771-6044 x 2130

4.2 Performance Standards: Proper adherence to all OSHA and Industry safety procedures is required prior, during and after work being performed. The contractor shall furnish all personnel with and require donning of required personal protective equipment (PPE). The contractor shall safeguard the public and government personnel, property, materials, supplies, and equipment exposed to contractor operations and activities, and avoid interruptions of government operations in the performance of services.

4.3 Liability of Damages: The contractor shall be liable for all damages to Government equipment and property when such damage is due to fault or negligence of the contractor. The contractor shall be responsible for all damages or injury to persons that occur as a result of the contractor’s fault or negligence. The contractor shall take proper safety and health precautions to protect the work, the workers, the public, and the property of others.