This is a Performance Work Statement (PWS) for on-site shredding and recycling services supporting three Ohio-based military installations: Ohio National Guard Headquarters (Beightler Armory), Defense Supply Center Columbus (DSCC) Building 5, and Rickenbacker Air National Guard Base (RANGB). The contractor must provide collection, on-site shredding, and cardboard recycling services on a bi-weekly schedule during operating hours of 0900-1500 on Tuesdays through Thursdays, excluding recognized U.S. federal holidays and government facility closures. The contractor will furnish all personnel, equipment, tools, materials, supervision, and quality control necessary to perform these services. Sensitive but unclassified materials must be shredded on-site before removal from facilities; no classified information will be handled. The contractor must supply lockable 95-gallon receptacles and consoles (totaling 16 receptacles and 51 consoles across all three locations) and remove recyclable cardboard in broken-down condition only. An additional annual visit to DSCC for federal records destruction is required. The contract period consists of one 12-month base year plus four 12-month option years, plus a six-month extension.

The contractor is responsible for developing and maintaining a Quality Control Plan within 10 days of contract award, complying with all installation security requirements, and completing mandatory training including AT Level 1 Awareness, iWATCH, and OPSEC training within 30 days. Background checks, personal identity verification, and Common Access Card (CAC) requirements apply per DoD standards. The contractor must maintain a stable workforce, designate a Contract Manager with full authority over daily operations, ensure all employees identify themselves as contractors, and report all labor hours (including subcontractors) annually via SAM.gov Service Contract Reporting. Contractors cannot telework and are not compensated for unexpected installation security closures or delays. The Government will conduct quality assurance surveillance through random monitoring by the Contracting Officer Representative to verify compliance with performance standards outlined in the Technical Exhibit Performance Requirements Summary.

View the file

Other files

File Type Posted
REGISTER OF WAGE DETERMINATIONS UNDER.docx DOCX document
Locked 95 Gallon Receptacle.pdf PDF
Solicitation - W9136426QA007 Professional Appearance.pdf PDF
Price List updated.docx DOCX document
Locked Shredding Console.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

Shredding and Recycling Services

1.0 General:

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform Shredding and Recycling Services, as defined in this PWS.

1.1.1 Objectives

1.2 Background: Contractor will provide an on-site shredding and recycling service to the Ohio National Guard (Beightler Armory), Defense Supply Center Columbus (DSCC) Building 5, and Rickenbacker Air National Guard Base (RANGB). Materials could be sensitive but unclassified and therefore must be shredded before removal from the facility. Contractors will not be exposed to any classified material. Contractor will also be responsible for the removal of recyclable cardboard materials.

1.3 Period of Performance (PoP): The Period of Performance shall be one (1) Base Year of 12 months and four (4) 12-month option years.

1.4 General Information:

1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0900-1500 on Tuesday through Thursday, except on recognized US holidays listed in 1.4.2 or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at the following locations:

· Ohio National Guard (Beightler Armory) located at 2811 W Dublin Granville Road, Columbus, Ohio 43235.

· Defense Supply Center Columbus (DSCC) located at 320 North James Road Bldg 5, Columbus, Ohio 43213.

· Rickenbacker Air National Guard Base (RANGB) located at 7750 South Access Road, Columbus, Ohio 43217.

The contractor shall at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that stability and continuity of the work force are essential.

1.4.1.1 Telework: The Government does not permit the contractor to telework in support of this requirement. In furtherance of Continuity of Operations Planning (COOP), a telework program may be enacted to ensure that the Government's mission-critical operations stay operational during times of national emergency or incidents of national significance. Telework shall be at no additional cost to the Government.

1.4.1.2 Security Requirements: Unscheduled gate closures by installation security personnel may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

1.4.2 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days:

1.4.2.1 New Year’s Day: January 1st

1.4.2.2 Martin Luther King, Jr.’s Birthday

1.4.2.3 President’s Day

1.4.2.4 Memorial Day

1.4.2.5 Juneteenth National Independence Day: June 19th

1.4.2.6 Independence Day: July 4th

1.4.2.7 Labor Day

1.4.2.8 Columbus Day

1.4.2.9 Veteran’s Day: November 11th

1.4.2.10 Thanksgiving Day

1.4.2.11 Christmas Day: December 25th

1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS). A final QCP shall be submitted to the Contracting Officer Representative (COR) NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO’s) acceptance in writing of any proposed changes to its QCP.

1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).

1.4.5 Installation Access and Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by Department of Defense (DoD), Headquarters Department of Army (HQDA) and/or local policy (see PWS 6.0). Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.4.5.1 Reserved.

1.4.5.1.1 Reserved.

1.4.5.1.2 Reserved.

1.4.5.1.3 Reserved.

1.4.5.1.4 Reserved.

1.4.5.1.5 Reserved.

1.4.5.1.6 Reserved.

1.4.5.2 For contractors that do not require a CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05), and applicable installation, facility and area commander installation/facility access, and local security policies and procedures (provided by a Government representative).

1.4.5.3 Awareness Training (AT) Level 1: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level 1 training within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel. AT Level 1 awareness training is available at the following website: https://jko.jten.mil/courses/atl1/launch.html.

1.4.5.4 iWATCH Training: The contractor and all associated subcontractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program (training standards provided by the requiring activity Antiterrorism Officer (ATO)). This local developed training shall be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or the KO. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each contractor employee and subcontractor employee to the COR within 15 calendar days after completion of training.

1.4.5.5 OPSEC Training: Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training or OPSEC Awareness for Military Members, DoD Employees and Contractors (GS130.16) at: https://securityawareness.usalearning.gov/opsec/index.htm.

New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

1.4.5.6 Reserved.

1.4.5.6.1 Reserved.

1.4.5.6.2 Complete initial and/or annual Information Assurance (IA) training as defined in the IA Best Business Practices (BBP) training (https://atc.us.army.mil/iastar/docs/Training_BBP.pdf).

1.4.5.6.3 Mark and safeguard files, output products, and storage media per classification level and disseminate them only to individuals authorized to receive them with a valid need to know.

1.4.5.6.4 Protect IS and IS peripherals located in their respective areas in accordance with physical security and data protection requirements.

1.4.5.6.5 Practice safe network and Internet operating principles and take no actions that threaten the integrity of the system or network.

1.4.5.7 Reserved.

1.4.5.8 Reserved.

1.4.5.9 Reserved.

1.4.5.10 Reserved.

1.4.5.11 Reserved.

1.4.5.12 Reserved.

1.4.5.13 Reserved.

1.4.5.14 Reserved.

1.4.6 Reserved.

1.4.7 Reserved.

1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.

1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.

1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.

1.4.12 Reserved.

1.4.13 Reserved.

1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.15 Phase In / Phase Out Periods. To minimize any decreases in productivity and to prevent possible negative impacts on additional services, the contractor shall have personnel on board, during the 30 days phase in/ phase out periods. During the phase in period, the contractor shall become familiar with performance requirements in order to commence full performance of services on the contract start date.

2.0 Definitions and Acronyms:

2.1 Definitions:

2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.

2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.

2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.

2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 Acronyms:

AEIArmy Enterprise Infostructure
ARArmy Regulation
AT/OPSECAntiterrorism/Operational Security
BIBackground Investigation
CMContract Manager
CORContracting Officer Representative
DADepartment of the Army
DD254Department of Defense Contract Security Classification Specification
DFARSDefense Federal Acquisition Regulation Supplement
DoDDepartment of Defense
DSCADefense Counterintelligence and Security Agency
FARFederal Acquisition Regulation
GFP/M/E/SGovernment Furnished Property/Material/Equipment/Services
HQDAHeadquarters, Department of the Army
HSPDHomeland Security Presidential Directive
IAInformation Assurance
ISInformation System(s)
KOContracting Officer
NGBNational Guard Bureau
OCIOrganizational Conflict of Interest
PIIPersonally Identifiable Information
PIPOPhase In/Phase Out
POCPoint of Contact
PRSPerformance Requirements Summary
PWSPerformance Work Statement
QAQuality Assurance
QASPQuality Assurance Surveillance Plan
QCQuality Control
QCPQuality Control Program
SCRService Contract Reporting
SSNSocial Security Number
TETechnical Exhibit
USD(I)Under Secretary of Defense for Intelligence

3.0 Reserved.

3.1 Reserved.

3.2 Reserved.

3.3 Reserved.

3.4 Reserved.

3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 5.1 and Technical Exhibit 1.

4.2 Reserved.

4.3 Reserved.

5.0 Requirements:

5.1 Contractor will provide an on-site collection, shredding and recycling services to the Ohio National Guard at the locations listed in 1.4.1. Materials could be sensitive but unclassified, and therefore must be shredded before removal from the facility. Contractor will not be exposed to any classified material. Contractor will also be responsible for the removal of recyclable cardboard materials. The contractor shall reference Technical Exhibit 1 for specific requirements.

5.1.1 Collection: Contractor will provide 95 Gallon Receptacles and Consoles for distribution throughout the locations listed in Paragraph 1.4.1 and Technical Exhibit 1. Contractor will provide bins that are lockable and capable of securely containing sensitive but unclassified information. Keys to these secure bins will ONLY be maintained by the Contractor and by a representative designated by the customer and will not be distributed to any other entity nor personal. The disposal bins will be used to receive paper products (copier paper, envelopes, glossy paper, carbonless paper, etc.) that may be stapled or bounded. The Contractor will collect materials from the pre-positioned bins on a bi-weekly set schedule. Price list for receptables and consoles will need to be provided for cardboard pickup and recycling. Bulk shredding price per pound will need to be provided.

5.1.2 Shredding: Once materials are collected, Contractor will need to shred on-site. Contractor will have the capability to shred the contents of all receptacles filled to maximum capacity on a bi-weekly set schedule. The Contractor can satisfy this requirement in a single visit or multiple visits as long as the bi-weekly requirement is met. The Contractor's operations will be self-sufficient and will not rely on any equipment or utility access to be provided by the Customer. All materials will be shredded on site: no intact documents or personally identifiable information will be removed from the location. The Contractor will not be responsible nor be permitted to shred Classified Information of any kind.

Contractor will also include a yearly visit to a Federal Records Holding site located at the Defense Supply Center-Columbus (DSCC) 320 North James Road Bldg 5, Columbus, Ohio 43213. This visit will be in addition to the weekly/bi-weekly schedule, and will not disrupt collection or shredding services at the Beightler or RANGB locations. The purpose of the annual visit is to properly destroy expiring Federal Records. These records will be shredded on site at DSCC and cannot be removed from the facility. Again, the Contractor’s operations will be self-sufficient and will not rely on any equipment or utility access to be provided by the Customer.

5.1.3 Recycling: Contractor will be responsible for removal of recyclable cardboard from locations listed in 1.4.1. on a bi-weekly set schedule. The customer does not possess crushing, compressing or banding capabilities, so the Contractor will be prepared to remove cardboard that is only in a broken-down state.

5.2 Service Contract Reporting:

5.3 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the National Guard Bureau via a secure data collection site.

5.4 The contractor shall completely fill in all required data fields using the following web address: https://sam.gov. Log in and select Entity Registrations and then select Service Contract Reporting.

The Contractor shall report the required information annually by October 31, for services performed under this contract during the preceding Government fiscal year (October 1-September 30).

The DoD Guidebook for Service Contract Reporting in SAM, available on the DoD Procurement Toolbox at https://dodprocurementtoolbox.com/site-pages/service-contract-reporting-scr. The General Services Administration (GSA) has also posted additional guidance such as quick start guides, informational videos, and frequently asked questions, that can be accessed by going to https://sam.gov and searching the “HELP” section. The SAM Federal User Guide is also available in the “HELP” section for comprehensive instructions on navigating SAM. Contractors requiring assistance using SAM should contact the Federal Service Desk at https://www.fsd.gov.

6.0 Applicable Publications: Publications applicable to this PWS are listed below:

Publication (Chapter/Page)

Date of Publication
Mandatory or Advisory
Website

Federal Acquisition Regulation https://www.acquisition.gov/?q=browsefar

Defense Federal Acquisition Regulation Supplement http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html or https://www.acquisition.gov/dfars

Joint Travel Regulation (JTR) https://www.defensetravel.dod.mil/site/travelreg.cfm

DoDM 1000.13-M-V1 DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b) 01/23/2014 (Change 1: 07/28/2020) http://www.esd.whs.mil/Directives/issuances/dodm

Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors (paragraph 9) August 2013 http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf

DoDM 5200.2 Procedures for the DoD Personnel Security Program (PSP)
04/03/2017

https://www.esd.whs.mil/Directives/issuances/dodm/

DoDI 5200.46 DoD Investigative and Adjudicative Guidance for Issuing the Common Access Card (CAC) 09/09/14 (Change 1: 05/04/2018) https://www.esd.whs.mil/Directives/issuances/dodi/

Homeland Security Presidential Directive (HSPD)-12 Policy for a Common Identification Standard for Federal Employees and Contractors 08/27/2004 https://www.dhs.gov/homeland-security-presidential-directive-12

DoDI 5400.11 Department of Defense Privacy and Civil Liberties Programs 01/29/2019 https://www.esd.whs.mil/Directives/issuances/dodi/

DoD 5400.11-R Department of Defense Privacy Program 05/14/2007 https://www.esd.whs.mil/Directives/issuances/dodm/

DoDD 8140.01 Cyberspace Workforce Management

10/05/2020 https://www.esd.whs.mil/Directives/issuances/dodd/

DoD 8570.01-M Information Assurance Workforce Improvement Program 12/19/2005 (Change 4: 11/10/2015) https://www.esd.whs.mil/Directives/issuances/dodm/

DoD 5220.22-M National Industrial Security Program Operating Manual (NISPOM) 02/28/2006 (Change 2: 05/18/2016) https://www.esd.whs.mil/Directives/issuances/dodm/

Army Directive 2014-05 Policy and Implementation Procedures for Common Access Card Credentialing and Installation Access for Uncleared Contractors 03/07/2014 https://armypubs.army.mil/ProductMaps/PubForm/ArmyDir.aspx

AR 25-2

Information Assurance 04/04/2019 http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx

AR 530-1

Operations Security 09/26/2014 http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx

AR 525-13

Antiterrorism 12/09/2019 http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx

AR 381-12

Threat Awareness and Reporting Program (TARP) (Section II, ¶ 2-4.b) 06/01/2016 http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx

6.1 Applicable Forms: Forms applicable to the PWS are listed below:

Form
Date
Website

DD 1172-2

Application for Identification Card/DEERS Enrollment

Mar 2017
http://www.dtic.mil/whs/directives/forms/index.htm

I-9 Employment Eligibility Verification 10/21/2019 https://www.uscis.gov/sites/default/files/files/form/i-9.pdf

DD 441

Department of Defense Security Agreement Feb 2020 http://www.dtic.mil/whs/directives/forms/dd/ddforms0001-0499.htm

DD 250

Material Inspection and Receiving Report

Aug 2000
https://www.esd.whs.mil/Directives/forms/dd0001_0499/

TECHNICAL EXHIBIT 1

Performance Requirements Summary (PRS)

This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

Performance Objective / Task
Performance Location

(1.4.1)

Performance Standard
Acceptable Quality Levels (AQL)
Surveillance Method / By Whom

5.1.1 Collection

Beightler Armory
QTY 8 - 95-gallon receptacles

QTY 26 - consoles

Contractor will have the capability to shred the contents of all receptacles filled to maximum capacity on a bi-weekly schedule.
Random monitoring / COR

Defense Supply Center Columbus (DSCC)

QTY 2 - 95-gallon receptacles

Rickenbacker Air National Guard Base (RANGB)

QTY 6 - 95-gallon receptacles

QTY 12 - consoles

5.1.2 Shredding Beightler Armory

Materials are collected and shredded on-site. Contractor will have the capability to shred the contents of all receptacles filled to maximum capacity on a bi-weekly schedule.
Contractor will have the capability to shred the contents of all receptacles filled to maximum capacity on a bi-weekly schedule.

Additional yearly pickup at RANGB.

Random monitoring / COR

Defense Supply Center Columbus (DSCC)

Rickenbacker Air National Guard Base (RANGB)

5.1.3 Recycling Beightler Armory

Contractor will be responsible for removal of recyclable cardboard from a designated area within Beightler, DSCC BLDG 5, and RANGB buildings.
Contractor will have the capability to shred the contents of all receptacles filled to maximum capacity on a bi-weekly schedule.
Random monitoring / COR

Defense Supply Center Columbus (DSCC)

Rickenbacker Air National Guard Base (RANGB)

Rickenbacker Air National Guard Base (RANGB) Multiple Locations:

Bldg 846 - QTY 1 Console Bldg 920 - QTY 2 Consoles & QTY 2 95-Gallon Receptacles Bldg 943 - QTY 1 Console (Main Hallway) Bldg 930 - QTY 1 Console & QTY 1 95-Gallon Receptacle Bldg 931 - QTY 1 Console Bldg 918 - QTY 1 Console Bldg 933 - QTY 1 Console (Main Hallway) Bldg 946 - QTY 1 Console & QTY 1 95-Gallon Receptacle (Main Hallway) Bldg 945 - QTY 1 Console (Room 111) Bldg 950 - QTY 2 Console & QTY 2 95-Gallon Receptacle

Beightler Armory Multiple Locations: Same Building between East and West Wing.

E102 - QTY 1 Console E113 - QTY 1 Console E207 - QTY 1 Console E215 - QTY 1 Console E220 - QTY 1 Console C202 - QTY 1 Console C211 - QTY 1 Console C212 - QTY 1 Console C220 - QTY 1 Console C222 - QTY 1 Console W103 - QTY 1 Console W104 - QTY 1 Console W105 - QTY 1 Console W112 - QTY 1 Console W113 - QTY 1 Console W118 - QTY 1 Console W124 - QTY 1 Console W134 - QTY 1 Console W201 - QTY 1 Console W205 - QTY 1 Console W209 - QTY 1 Console W217 - QTY 1 Console W222 - QTY 1 Console W 2nd floor middle upstairs - QTY 1 Console W basement middle stairs - QTY 2 Console

E 1st floor Back parking lot under stairs - QTY 1 95-Gallon Receptacle E 1st by USPFO under stairs - QTY 1 95-Gallon Receptacle W135 - QTY 1 95-Gallon Receptacle Drill Floor - QTY 5 95-Gallon Receptacle

TECHNICAL EXHIBIT 2

Deliverables Schedule

PWS Reference / Deliverable Title
Frequency
Number of Copies
Medium/Format
Submit To
1.4.5.3 AT Level 1 Awareness Training Certificates
Provide within 15 calendar days after employee completes training.
1
Electronic Submission
COR

1.4.5.4 iWATCH Training Certificates

Provide within 15 calendar days after employee completes training.