This performance work statement and sources sought notice outline requirements for a fire alarm system installation project for the Bureau of Reclamation. The contractor shall provide all labor, equipment, materials and services necessary to remove an existing fire panel and install a new hub panel with cellular monitoring capability at the Operations and Maintenance Boat Barn at the Klamath Basin Area Office compound in Klamath Falls, Oregon by June 30, 2024. The new panel must be compatible with existing sub-panels and fully restore and certify the fire alarm system operation. Interested vendors should submit capability statements including firm information and UEI number to the point of contact by March 11, 2024 to be considered for this work.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BUREAU OF RECLAMATION
PERFORMANCE WORK STATEMENT
SSA KBAO Compound Fire Panel Move Background KBAO’s fire system is outdated and was wired to the old building (Building One) which is slated for demolition. The new headquarters building’s main fire alarm panel is incompatible with the equipment that covers the O&M shops and outbuildings still in use at the KBAO compound. To get the rest of the facilities up to code, a new fire panel with cellular connection shall be installed at the O&M Boat Barn. This new hub panel will receive alarm signals from each of the outbuildings. The end product will result in two independent fire systems for the KBAO compound as a whole. Work must be complete prior to demolition of Building One.
Description of Requirement The Contractor shall provide all labor, personnel, management, supervision, administration, transportation, equipment, tools, parts, materials, supplies, and other items and services necessary to install a hub fire alarm system panel with cellular monitoring capability at the O&M Boat Barn.
The hub panel shall be connected to existing sub-panels such that the hub panel will receive wired alarm signals and be the cellular callout signal for the system. Sub-panels are already centrally wired to the hub panel location from the shops and outbuildings at the KBAO compound.
The current panel is a Silent Knight fire alarm control communicator Model 5820XL. This needs to be replaced with a compatible controller.
The panel which it will be connected to in the boat barn is Model 5496 intelligent power module.
The 5496 in the boat barn is the same as the box under the 5820XL.
Scope Restore and certify operation of the fire alarm system.
Fully test the panel and the communication with all devices.
Removal of existing fire panel that is no longer in use.
Contractor will program and test to ensure a fully functional fire alarm system.
Upon successful testing, contractor will certify fire alarm system and provide a report in accordance with National Fire Alarm and Signaling Code NFPA 72 standards.
Provide a copy of the programming.
Reports Reports shall be provided to the COR within five business days following Installation. The report format is flexible but must confirm that the system is fully functional.
Period of Performance The period of performance shall be from 4/1/2024 through 6/30/2024.
Hours of Operations and Recognized Holidays Normal business hours are 7:00am to 4:30pm Mon-Fri. The Bureau of Reclamation observes all federal holidays. No work will be done outside normal days and hours of operation, or during Government facility closures.
Place of Performance 6600 Washburn Way Klamath Falls, OR 97601 Safety The contractor shall be responsible to ensure safety at all times in compliance with OSHA and Reclamation Safety and Health Standards (RSHS). Job Hazard Analyses (JHAs) may be required at the COR’s discretion.
Government-Furnished Property No government Furnished Property is authorized for use by the Contractor. Restroom facilities are available.
Quality Assurance Plan Acceptable quality will be reviewed and verified by the COR.