About this file
This is a Request for Bids (RFB) specification document issued by the City of Tacoma Department of Public Works, Facilities Management Division for the FCC Tower Improvements Re-Bid project (Specification No. PW26-0140F). The project focuses on adding structural braces and structural steel to an existing communication tower to provide increased seismic resistance, repainting the tower, and installing or replacing a ground-mounted flagpole. The bid submission deadline is 11:00 a.m. Pacific Time on Tuesday, July 21, 2026, with sealed bids to be received either electronically via sendbid@tacoma.gov (maximum 35 MB) or in person at the Tacoma Public Utilities Administration Building North, 3628 South 35th Street, Tacoma, WA 98409. Bid opening will occur at 11:15 a.m. on the same day at the same location and virtually via Zoom. A pre-proposal meeting is scheduled for 9:00 a.m. Thursday, July 9, 2026, via Microsoft Teams, followed by an on-site walk-through on Friday, July 10, 2026, at 9:00 a.m. at 425 Tacoma Ave S, Tacoma, WA. The contract term is 60 calendar days from the Notice to Proceed for substantial completion, with liquidated damages of $1,000 per consecutive calendar day beyond the substantial completion date.
The project has an estimated cost of $86,000.00, and bids must include Washington State sales tax at 10.4%. All bidders must submit a 5-percent bid bond or certified check, and successful contractors must provide performance and payment bonds. The project is subject to Washington State prevailing wage requirements under RCW 39.12, and contractors must file a Statement of Intent to Pay Prevailing Wages with the Department of Labor and Industries upon contract award and an Affidavit of Wages Paid upon project completion. Bidders must meet mandatory state responsibility criteria including current contractor registration, Washington Unified Business Identifier (UBI) number, workers' compensation coverage, and compliance with prevailing wage statutes. The City of Tacoma supplemental responsibility criteria require adequate financial resources, necessary experience and technical qualifications, ability to meet the performance schedule, and a satisfactory record of performance and integrity. General contractor qualifications require minimum five projects of similar size and scope completed within the last five years. Insurance requirements include Commercial General Liability ($1,000,000 each occurrence/$2,000,000 aggregate), Commercial Automobile Liability ($1,000,000), Workers' Compensation as required by Washington law, Employers' Liability ($1,000,000), Installation Floater Insurance, and Builder's Risk Insurance covering the full contract value. No Equity in Contracting (EIC) or Local Employment Apprenticeship Program (LEAP) requirements apply to this project due to the estimated cost threshold.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Bids Specification No. PW25-0098F Template Revised: 07/23/2023
PUBLIC WORKS DEPARTMENT
FACILITIES MANAGEMENT DIVISION
REQUEST FOR BIDS
FCC Tower Improvements Re-Bid
SPECIFICATION NO. PW26-0140F
City of Tacoma Department of Public Works
Facilities Management Division
PROJECT MANUAL
FCC Tower Improvements Re-Bid
SPECIFICATION
NO.: PW26-0140F
TABLE OF CONTENTS
COVER
REQUEST FOR BIDS (RFB ADVERTISEMENT)
TABLE OF CONTENTS
SPECIAL NOTICE TO BIDDERS
DIVISION 00: BIDDING & CONTRACT REQUIREMENTS
A. BID PERIOD FORMS:
1. BIDDER QUESTION FORM
2. SUBSTITUTION REQUEST FORM
B. PROPOSAL FORMS (MUST BE SUBMITTED WITH BID):
1. BID PROPOSAL AND SIGNATURE PAGE
2. BID BOND
3. EQUITY IN CONTRACTING UTILIZATION FORM
4. SUBCONTRACTOR CATEGORIES OF WORK FORM
5. STATE RESPONSIBILITY FORM
6. GENERAL CONTRACTOR QUALIFICATION SUBMITTAL
7. CERTIFICATION OF COMPLIANCE WITH WAGE PAYMENT STATUTES FORM
C. CONTRACT FORMS (POST AWARD):
1. CONTRACT
2. INSURANCE CERTIFICATE REQUIREMENTS
3. PERFORMANCE BOND TO THE CITY OF TACOMA
4. PAYMENT BOND TO THE CITY OF TACOMA
5. GENERAL RELEASE TO THE CITY OF TACOMA
6. TPD DRAFT FORMS FOR FACILITY ACCESS
D. WASHINGTON STATE PREVAILING WAGE RATES
1. STATE PREVAILING WAGE RATES FOR PIERCE COUNTY
E. CITY PROGRAMS:
1. EQUITY IN CONTRACTING (EIC)
2. LOCAL EMPLOYMENT APPRENTICESHIP PROGRAM (LEAP)
F. GENERAL CONDITIONS AND OTHER CONTRACT TERMS & CONDITIONS:
1. CITY OF TACOMA, GENERAL PROVISIONS
2. MODIFICATIONS TO THE GENERAL CONDITIONS, AS MODIFIED BY THE
CITY OF TACOMA
3. GENERAL CONDITIONS FOR WASHINGTON STATE FACILITY
CONSTRUCTION
DIVISION 01: GENERAL REQUIREMENTS
• 01 10 00 – SUMMARY
• 01 12 00 - PERMITS AND FEES
• 01 22 00 - UNIT PRICES
• 01 23 00 - ALTERNATES
• 01 25 00 - SUBSTITUTION PROCEDURES
• 01 26 00 - CONTRACT MODIFICATION PROCEDURES
• 01 29 00 - APPLICATION FOR PAYMENT
• 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
• 01 32 15 - CONSTRUCTION SCHEDULE
• 01 33 00 - SUBMITTALS
• 01 35 16 - ALTERATION PROJECT PROCEDURES
• 01 45 00 - QUALITY CONTROL
• 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
• 01 60 00 - PRODUCT REQUIREMENTS
• 01 70 00 - EXECUTION AND CLOSEOUT REQUIREMENTS
• 01 78 00 - CLOSEOUT SUBMITTALS
TECHNICAL SPECIFICATIONS
DIVISION 10 – SPECIALTIES
• 10 75 00 – FLAGPOLES
TECHNICAL REPORTS
APEX/PBS HAZARDIOUS MATERIALS SURVEY
Form No. SPEC-040C Revised: 06/03/2024
Public Works Department/Facilities Management Division
REQUEST FOR BIDS PW26-0140F
FCC Tower Improvements Re-Bid
Submittal Deadline: 11:00 a.m., Pacific Time, Tuesday, July 21, 2026
Submittals must be received by the City’s Procurement and Payables Division by 11:00 a.m. Pacific Time.
For electronic submittals, the City of Tacoma will designate the time of receipt recorded by our email server, as the official time of receipt. This clock will be used as the official time of receipt of all parts of electronic bid submittals. Include the specification number in the subject line of your email. Your submittal must be sent as an attachment, links to your electronic submittal will not be accepted.
For in person submittals, the City of Tacoma will designate the time of receipt recorded by the timestamp located at the lobby security desk, as the official time of receipt. Include the specification number on the outside of the sealed envelope. Late submittals will be returned unopened and rejected as non-responsive.
Submittal Delivery: Sealed submittals will be received as follows:
By Email:
sendbid@tacoma.gov Maximum email size including attachments: 35 MB.
Multiple emails may be sent for each submittal.
Note: Email may pass through multiple servers before arriving at its destination. Please allow sufficient time for email delivery of submittals. Timely electronic delivery is at the risk of the supplier.
In Person:
Tacoma Public Utilities Administration Building North, Main Floor, Lobby Security Desk 3628 South 35th Street Tacoma, WA 98409 Monday – Friday 8:00 am to 4:30 pm
Bid Opening: Submittals must be received by the City’s Procurement and Payables Division prior to 11:00 a.m. Pacific Time. Sealed submittals in response to a RFB will be opened Tuesday’s at 11:15 a.m. by a purchasing representative and read aloud during a public bid opening held at the Tacoma Public Utilities Administrative Building North, 3628 S. 35th Street, Tacoma, WA 98409, conference room M-1, located on the main floor. They will also be held virtually Tuesday’s at 11:15 a.m. Attend a Zoom meeting via this link or call 1
(253) 215 8782, using meeting ID # 884 0268 0573, passcode # 070737.
Submittals in response to an RFP, RFQ or RFI will be recorded as received, but not read at bid opening. As soon as possible, after 1:00 PM, on the day of submittal deadline, preliminary results will be posted to www.TacomaPurchasing.org.
If you believe your submittal was sent timely and was not read at bid opening, please contact sendbid@tacoma.gov immediately.
Solicitation Documents: An electronic copy of the complete solicitation documents may be viewed and obtained at the City’s plan distribution service provider, ARC, 632 Broadway, Tacoma, WA, or by going to http://www.e-arc.com/location/tacoma. Prospective bidders will be required to pay reproduction costs. A list of vendors registered for this solicitation is also available at their website.
Pre-Proposal Meeting: A pre-proposal meeting will be held virtually and in-person. The virtual meeting will take place at 9 am on Thursday, July 9, 2026 via the Microsoft Team meeting link provided below. Following the virtual meeting there will be an on-site walk-through (in-person meeting) starting at 9:00 am on Friday, July 10th, 2026. All interested participants should plan to meet on the sidewalk in front of 425 Tacoma Ave S.
in Tacoma, WA, at 9:00 am. The on-site walk will start promptly at 9:05 am.
mailto:sendbid@cityoftacoma.org https://us06web.zoom.us/j/88402680573?pwd=eThSaXZxNER0TWRhUGx6U0F2cURMZz09 https://www.cityoftacoma.org/cms/One.aspx?portalId=169&pageId=22848 mailto:sendbid@cityoftacoma.org http://www.ci.tacoma.wa.us/45bidsapps/PlanholderRegister.aspx
Form No. SPEC-040C Revised: 06/03/2024
Microsoft Teams meeting
Join: https://teams.microsoft.com/meet/266934682615054?p=dgp4Yrq7OXdV6OohCX
Meeting ID: 266 934 682 615 054
Passcode: YW3WR2Ne
Need help? | System reference
Dial in by phone
+1 253-666-4424,,323623872# United States, Tacoma
Find a local number
Phone conference ID: 323 623 872#
For organizers: Meeting options | Reset dial-in PIN
Project Scope: The project focuses on adding structural braces and structural steel to an existing communication tower to provide increased seismic resistance. The project will also include the repainting of the tower and the installation/replacement of a ground mounted flagpole.
Estimate: $86,000.00
Paid Sick Leave: The City of Tacoma requires all employers to provide paid sick leave in accordance with State of Washington law.
Americans with Disabilities Act (ADA Information: The City of Tacoma, in accordance with Section 504 of the Rehabilitation Act (Section 504) and the Americans with Disabilities Act (ADA), commits to nondiscrimination on the basis of disability, in all of its programs and activities. Specification materials can be made available in an alternate format by emailing the contact listed below in the Additional Information section.
Title VI Information:
“The City of Tacoma” in accordance with provisions of Title VI of the Civil Rights Act of 1964, (78 Stat. 252, 42 U.S.C. sections 2000d to 2000d-4) and the Regulations, hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, national origin in consideration of award.
Additional Information: Requests for information regarding the specifications may be obtained by contacting Stan Rowden by email to SRowden@tacoma.gov..
Protest Policy: City of Tacoma protest policy, located at www.tacomapurchasing.org, specifies procedures for protests submitted prior to and after submittal deadline.
Meeting sites are accessible to persons with disabilities. Reasonable accommodations for persons with disabilities can be arranged with 48 hours advance notice by calling 253-502-8468.
https://teams.microsoft.com/meet/266934682615054?p=dgp4Yrq7OXdV6OohCX https://aka.ms/JoinTeamsMeeting?omkt=en-US https://teams.microsoft.com/l/meetup-join/19%3ameeting_OGZhY2UzMTAtZDA2Mi00ZGUxLTg0ZGItMDVjZDA3MDU3NzNi%40thread.v2/0?context=%7b%22Tid%22%3a%228ef8e5fc-f375-40ae-ab99-e5cee9801271%22%2c%22Oid%22%3a%22f775039d-dad6-4145-82ae-38e6ee61f83c%22%7d tel:+12536664424,,323623872 https://dialin.teams.cloud.microsoft/5349761c-1f7c-49ce-8138-c91754a307ae?id=323623872 https://teams.microsoft.com/meetingOptions/?organizerId=f775039d-dad6-4145-82ae-38e6ee61f83c&tenantId=8ef8e5fc-f375-40ae-ab99-e5cee9801271&threadId=19_meeting_OGZhY2UzMTAtZDA2Mi00ZGUxLTg0ZGItMDVjZDA3MDU3NzNi@thread.v2&messageId=0&language=en-US https://dialin.teams.cloud.microsoft/usp/pstnconferencing http://cms.cityoftacoma.org/Purchasing/CandA/ProtestPolicy052711.pdf http://www.tacomapurchasing.org/
Revised: 07/1/2026 Page 1 of 5
CITY OF TACOMA
FINANCE/PURCHASING DIVISION
SPECIAL NOTICE TO BIDDERS
Public works and improvement projects for the City of Tacoma are subject to Washington state law and Tacoma Municipal Code, including, but not limited to the following:
I. STATE OF WASHINGTON
A. RESPONSIBILITY CRITERIA – STATE OF WASHINGTON
In order to be considered a responsible bidder the bidder must meet the following mandatory state responsibility criteria contained in RCW 39.04.350:
1. Have a current certificate of registration as a contractor in compliance with chapter 18.27
RCW, a plumbing contractor license in compliance with chapter 18.106 RCW, an elevator contractor license in compliance with chapter 70.87 RCW, or an electrical contractor license in compliance with chapter 19.28 RCW, as required under the provisions of those chapters, which must have been in effect at the time of bid submittal;
2. Have a current Washington Unified Business Identifier (UBI) number;
3. If applicable:
a. Have Industrial Insurance (workers' compensation) coverage for the bidder’s employees working in Washington, as required in Title 51 RCW;
b. Have a Washington Employment Security Department number, as required in Title
50 RCW;
c. Have a Washington Department of Revenue state excise tax registration number, as required in Title 82 RCW and;
4. Not be disqualified from bidding on any public works contract under RCW 39.06.010 (unlicensed or unregistered contractors) or 39.12.065(3) (prevailing wage).
5. If bidding on a public works project subject to the apprenticeship utilization requirements in RCW 39.04.320, not have been found out of compliance by the Washington state apprenticeship and training council for working apprentices out of ratio, without appropriate supervision, or outside their approved work processes as outlined in their standards of apprenticeship under chapter 49.04 RCW for the one-year period immediately preceding the date of the bid solicitation;
6. Have received training on the requirements related to public works and prevailing wage under chapter 39.04 RCW and chapter 39.12 RCW. The bidder must designate a person or persons to be trained on these requirements. The training must be provided by the department of labor and industries or by a training provider whose curriculum is approved by the department. The department, in consultation with the prevailing wage advisory committee, must determine the length of the training. Bidders that have completed three or more public works projects and have had a valid business license in Washington for three or more years are exempt from this subsection. The department of labor and industries must keep records of entities that have satisfied the training requirement or are exempt and make the records available on its website. Responsible https://app.leg.wa.gov/rcw/default.aspx?cite=39.04.350 https://app.leg.wa.gov/rcw/default.aspx?cite=18.27 http://app.leg.wa.gov/RCW/default.aspx?cite=18.106 http://app.leg.wa.gov/RCW/default.aspx?cite=70.87 http://app.leg.wa.gov/RCW/default.aspx?cite=19.28 https://app.leg.wa.gov/rcw/default.aspx?Cite=51 https://app.leg.wa.gov/rcw/default.aspx?Cite=50 https://app.leg.wa.gov/rcw/default.aspx?Cite=50 https://apps.leg.wa.gov/rcw/default.aspx?Cite=82 https://app.leg.wa.gov/rcw/default.aspx?cite=39.06.010 https://app.leg.wa.gov/rcw/default.aspx?cite=39.12.065 http://app.leg.wa.gov/RCW/default.aspx?cite=39.04.320 http://app.leg.wa.gov/RCW/default.aspx?cite=49.04 https://app.leg.wa.gov/rcw/default.aspx?cite=39.04.350 http://app.leg.wa.gov/RCW/default.aspx?cite=39.12
Revised: 07/1/2026 Page 2 of 5 parties may rely on the records made available by the department regarding satisfaction of the training requirement or exemption;
7. Within the three-year period immediately preceding the date of the bid solicitation, not have been determined by a final and binding citation and notice of assessment issued by the department of labor and industries or through a civil judgment entered by a court of limited or general jurisdiction to have willfully violated, as defined in RCW 49.48.082, any provision of chapter 49.46, 49.48, or 49.52 RCW;
8. At the time of bid submittal, not be subject to a revocation of a minor work permit under
RCW 49.12.390(4)
B. RECIPROCAL PREFERENCE FOR RESIDENT CONTRACTORS:
Effective March 30, 2012, RCW 39.04.380 imposes a reciprocal preference for resident contractors. Any bid received from a non-resident contractor from a state that provides an in-state percentage bidding preference is subject application of a comparable percentage disadvantage.
A non-resident contractor from a state that provides an in-state percentage bidding preference means a contractor that:
1. Is from a state that provides a percentage bid preference to its resident contractors bidding on public works projects, and
2. Does not have a physical office located in Washington at the time of bidding on the City of Tacoma public works project.
The state of residence for a non-resident contractor is the state in which the contractor was incorporated, or if not a corporation, the state in which the contractor’s business entity was formed.
The City of Tacoma will evaluate all non-resident contractors for an out of state bidder preference. If the state of the non-resident contractor provides an in state contractor preference, a comparable percentage disadvantage will be applied to the non-resident contractor’s bid prior to contract award. The responsive and lowest and best responsible bidder after application of any non-resident disadvantage will be awarded the contract.
The reciprocal preference evaluation does not apply to public works procured pursuant to RCW 39.04.155, RCW 39.04.280, federally funded competitive solicitations where such agencies prohibit the application of bid preferences, or any other procurement exempt from competitive bidding.
Bidders must provide the City of Tacoma with their state of incorporation or the state in which the business entity was formed and include whether the bidder has a physical office located in Washington.
The bidder shall submit documentation demonstrating compliance with above criteria on the enclosed State Responsibility and Reciprocal Bidder Information form.
C. SUBCONTRACTOR RESPONSIBILITY
http://app.leg.wa.gov/RCW/default.aspx?cite=49.48.082 http://app.leg.wa.gov/RCW/default.aspx?cite=49.46 https://app.leg.wa.gov/rcw/default.aspx?cite=49.48 http://app.leg.wa.gov/RCW/default.aspx?cite=49.52 http://app.leg.wa.gov/RCW/default.aspx?cite=49.12.390 https://app.leg.wa.gov/rcw/default.aspx?cite=39.04.380 https://app.leg.wa.gov/rcw/dispo.aspx?cite=39.04.155 https://apps.leg.wa.gov/rcW/default.aspx?cite=39.04.280
Revised: 07/1/2026 Page 3 of 5
1. The Contractor shall include the language of this subcontractor responsibility section in each of its first tier subcontracts, and shall require each of its subcontractors to include the same language of this section in each of their subcontracts, adjusting only as necessary the terms used for the contracting parties. The requirements of this section apply to all subcontractors regardless of tier.
2. At the time of subcontract execution, the Contractor shall verify that each of its first tier subcontractors meets the following bidder responsibility criteria:
a. Have a current certificate of registration as a contractor in compliance with chapter
18.27 RCW, which must have been in effect at the time of subcontract bid submittal;
b. Have a current Washington Unified Business Identifier (UBI) number;
c. If applicable, have:
i. Have Industrial Insurance (workers' compensation) coverage for the bidder’s employees working in Washington, as required in Title 51 RCW;
ii. A Washington Employment Security Department number, as required in Title 50
RCW;
iii. A Washington Department of Revenue state excise tax registration number, as required in Title 82 RCW;
iv. An electrical contractor license, if required by Chapter 19.28 RCW;
v. An elevator contractor license, if required by Chapter 70.87 RCW and;
3. Not be disqualified from bidding on any public works contract under RCW 39.06.010
(unlicensed or unregistered contractors) or 39.12.065(3) (prevailing wage).
https://app.leg.wa.gov/rcw/default.aspx?cite=18.27 https://app.leg.wa.gov/rcw/default.aspx?Cite=51 https://app.leg.wa.gov/rcw/default.aspx?Cite=50 https://apps.leg.wa.gov/rcw/default.aspx?Cite=82 https://app.leg.wa.gov/rcw/default.aspx?cite=19.28 https://app.leg.wa.gov/rcw/default.aspx?cite=70.87 https://app.leg.wa.gov/rcw/default.aspx?cite=39.06.010 https://app.leg.wa.gov/rcw/default.aspx?cite=39.12.065
Revised: 07/1/2026 Page 4 of 5
II. CITY OF TACOMA
A. SUPPLEMENTAL RESPONSIBILITY CRITERIA – CITY OF TACOMA:
In order to be considered a responsible bidder, the prospective bidder shall have all of the following qualifications set forth in Tacoma Municipal Code 1.06.262:
1. Adequate financial resources or the ability to secure such resources;
2. The necessary experience, stability, organization and technical qualifications to perform the proposed contract;
3. The ability to comply with the required performance schedule, taking into consideration all existing business commitments;
4. A satisfactory record of performance, integrity, judgment and skills; and
5. Be otherwise qualified and eligible to receive an award under applicable laws and regulations.
a. Bidder Responsibility. Bidders shall not be in violation of 39.04.350 RCW Bidder
Responsibility Criteria - Supplemental Criteria.
In addition to the mandatory bidder responsibility criteria listed immediately above, the City may, in addition to price, consider any or all of the following criteria contained in Tacoma Municipal Code Chapter 1.06.262 in determining bidder responsibility:
1. The ability, capacity, experience, stability, technical qualifications and skill of the respondent to perform the contract;
2. Whether the respondent can perform the contract within the time specified, without delay or interference;
3. Integrity, reputation, character, judgment, experience, and efficiency of the respondents, including past compliance with the City’s Ethics Code;
4. Quality of performance of previous contracts;
5. Previous and existing compliance with laws and ordinances relating to contracts or services;
6. Sufficiency of the respondent’s financial resources;
7. Quality, availability, and adaptability of the supplies, purchased services or public works to the particular use required;
8. Ability of the respondent to provide future maintenance and service on a timely basis;
9. Payment terms and prompt pay discounts;
10. The number and scope of conditions attached to the submittal;
11. Compliance with all applicable City requirements, including but not limited to the City's
Ethics Code and its Small Business Enterprise and Local Employment and Apprenticeship programs;
12. Other qualification criteria set forth in the specification or advertisement that the appropriate department or division head determines to be in the best interests of the City.
The City may require bidders to furnish information, sworn or certified to be true, to demonstrate compliance with the City responsibility criteria set forth above. If the city manager or director of utilities is not satisfied with the sufficiency of the information provided, or if the prospective respondent does not substantially meet all responsibility requirements, any submittal from such respondent must be disregarded.
Revised: 07/1/2026 Page 5 of 5
B. ADDITIONAL SUPPLEMENTAL CRITERIA – NOT APPLICABLE
C. MODIFICATIONS TO SUPPLEMENTAL CRITERIA
Potential bidders may request modifications to the City’s supplemental criteria by submitting a written request to the Purchasing Division no later than 5:00 p.m. Pacific Time, three days prior to the submittal deadline. Please include the Specification No. and Title when submitting such requests. Requests must include justification for why certain criteria should be modified. Requests received after this date and time will not be considered.
Requests for modifications to the supplemental criteria may be submitted via postal mail or delivered personally, or sent by e-mail or fax, within the above timeline as follows:
By Carrier:
City of Tacoma Procurement & Payables Division Tacoma Public Utilities 3628 S 35th Street Tacoma, WA 98409
In Person:
City of Tacoma Procurement & Payables Division Tacoma Public Utilities Lobby Security Desk Administration Building North – Main Floor 3628 S 35th Street Tacoma, WA 98409
By Mail:
City of Tacoma Procurement & Payables Division Tacoma Public Utilities PO Box 11007 Tacoma, WA 98411-0007
Fax: 253-502-8372 E-mail: bids@tacoma.gov
The City will respond to a timely submitted request prior to the bid opening date. Changes to the supplemental criteria, if warranted, will be issued by addendum to the solicitation documents and posted to the City’s website for the attention of all prospective bidders.
D. DETERMINATION OF BIDDER RESPONSIBILITY
If the City determines the bidder does not meet the criteria above and is therefore not a responsible bidder, the City shall notify the bidder in writing with the reasons for its determination. If the bidder disagrees, the bidder may appeal the determination in a manner consistent with the City’s Protest Policy. Appeals are coordinated by the Purchasing Division heard by the Procurement and Payables Division manager for contracts less than or equal to $200,000 and by Contracts and Awards Board for contracts greater than $200,000.
mailto:bids@tacoma.gov
BID PERIOD FORMS
The following forms shall be used during the bidding process to request clarifications and request substitutions. These forms are not required to be submitted with the Bid.
• Bidder Question Form
• Substitution Request Form
BIDDER QUESTION FORM
PW26-0140F
FCC Tower Improvements Re-Bid
Prospective bidders must submit questions or clarifications in writing on this form allowing time for a written reply to reach all prospective bidders before the submission of the bids. Bidder questions shall be submitted on this form via e-mail to:
Stan Rowden, Senior Buyer.
E-mail address: SRowden@tacoma.gov
All e-mails must be received by 5:00 pm on Friday, July 10th, 2026. Where changes in the project documents are required, an addendum will be issued to everyone on the plan holder’s list and posted on www.tacomapurchasing.org.
I have the following question(s):
Submitted by:
Name
Representing
Address
Fax Number
Phone Number
SUBSTITUTION REQUEST FORM
FCC Tower Improvements Re-Bid
SPECIFICATION NO.: PW26-0140F
Prospective bidders may request substitutions in writing on this form. Substitutions shall be submitted on this form via e-mail to:
Stan Rowden, Senior Buyer.
E-mail address: SRowden@tacoma.gov
All e-mails must be received by 5pm on Friday, July 10th, 2026. Where changes in the project documents are required, an addendum will be issued to everyone on the plan holder’s list and posted on www.tacomapurchasing.org.
SUBSTITUTION REQUEST FORM
SPECIFICATION NO.: PW26-0140F
PROPOSAL FORMS
The following forms must be completed in their entirety and submitted with the bid. Bidders must use the forms provided. Do not modify or substitute forms.
Failure to complete and submit all the forms in this section may result in the bid being declared unresponsive and rejected.
1. BID PROPOSAL AND SIGNATURE PAGE
2. BID BOND
3. EQUITY IN CONTRACTING UTILIZATION FORM
4. SUBCONTRACTOR CATEGORIES OF WORK
5. STATE RESPONSIBILITY FORM
6. GENERAL CONTRACTOR QUALIFICATION SUBMITTAL
7. CERTIFICATION OF COMPLIANCE WITH WAGE PAYMENT STATUTES
FORM
B I D P R O P O S A L
Page 1 of 3 BID PROPOSAL FORM & SIGNATURE PAGE
City of Tacoma Department of Public Works
Facilities Management
Name of Firm: ___________________________________________________________ (Write in company name)
In compliance with the contract documents, the following bid proposal is submitted:
BASE BID:
Lump sum base bid is inclusive of the Scope of Work described in the Contract Documents.
BASE BID: $_________________________
WA STATE SALES TAX @ 10.4%: $_________________________
GRAND TOTAL: $_________________________
BID ALTERNATES:
There are no alternates in this Request for Bids.
UNIT PRICES:
There are no Unit Prices in this request for bids
B I D P R O P O S A L
Page 2 of 3 BID PROPOSAL FORM & SIGNATURE PAGE
INTENT AND AFFIDAVIT OF WAGES PAID:
In compliance with Chapter 296-127 WAC the Contractor shall pay all fees associated with the Intent and Affidavit of Wages Paid to the Department of Labor and Industries. These costs shall be included in the base bid.
CITY OF TACOMA PROGRAMS:
EIC:
This project does not meet the thresholds for EIC requirement incorporation, and as such does not have any EIC requirements.
LEAP:
This project does not meet the thresholds for LEAP requirement incorporation, and as such does not have any LEAP requirements.
TIME FOR COMPLETION:
The undersigned hereby agrees to substantially complete all the work under the Base Bid (and accepted alternates and/or unit prices) within 60 calendar days after the Notice to Proceed.
LIQUIDATED DAMAGES:
The undersigned agrees to pay the Owner as liquidated damages the sum of $1,000 for each consecutive calendar day beyond the SUBSTANTIAL COMPLETION date. Liquidated damages shall be deducted from the contract by change order.
B I D P R O P O S A L
Page 3 of 3 BID PROPOSAL FORM & SIGNATURE PAGE
SUSTAINABILITY:
1) Have you incorporated sustainability into your everyday business practices? Yes / No
Please Describe:
2) Have you taken measures to minimize impacts to the environment in the delivery of proposed goods and services? Yes / No
Please Describe:
3) Will you be incorporating and implementing sustainable practices during the construction of this project? Yes / No
Please Describe:
Form No. SPEC-080A Revised: 06/01/2021
SIGNATURE PAGE
CITY OF TACOMA
Public Works Department / Facility Management Division
All submittals must be in ink or typewritten, executed by a duly authorized officer or representative of the bidding/proposing entity, and received and time stamped as directed in the Request for Bids page near the beginning of the specification. If the bidder/proposer is a subsidiary or doing business on behalf of another entity, so state, and provide the firm name under which business is hereby transacted.
REQUEST FOR BIDS SPECIFICATION NO. PW26-0140F
FCC Tower Improvements Re-Bid
The undersigned bidder/proposer hereby agrees to execute the proposed contract and furnish all materials, labor, tools, equipment and all other facilities and services in accordance with these specifications.
The bidder/proposer agrees, by submitting a bid/proposal under these specifications, that in the event any litigation should arise concerning the submission of bids/proposals or the award of contract under this specification, Request for Bids, Request for Proposals or Request for Qualifications, the venue of such action or litigation shall be in the Superior Court of the State of Washington, in and for the County of Pierce.
Non-Collusion Declaration
The undersigned bidder/proposer hereby certifies under penalty of perjury that this bid/proposal is genuine and not a sham or collusive bid/proposal, or made in the interests or on behalf of any person or entity not herein named; and that said bidder/proposer has not directly or indirectly induced or solicited any contractor or supplier on the above work to put in a sham bid/proposal or any person or entity to refrain from submitting a bid/proposal; and that said bidder/proposer has not, in any manner, sought by collusion to secure to itself an advantage over any other contractor(s) or person(s).
Bidder/Proposer’s Registered Name
Address
City, State, Zip
Authorized Signatory E-Mail Address
E.I.No. / Federal Social Security Number Used on Quarterly
Federal Tax Return, U.S. Treasury Dept. Form 941
E-Mail Address for Communications
Signature of Person Authorized to Enter Date into Contracts for Bidder/Proposer
Printed Name and Title
(Area Code) Telephone Number / Fax Number
State Business License Number in WA, also known as UBI (Unified Business Identifier) Number
State Contractor’s License Number (See Ch. 18.27, R.C.W.)
Addendum acknowledgement #1_____ #2_____ #3_____ #4_____ #5_____
THIS PAGE MUST BE SIGNED AND RETURNED WITH SUBMITTAL.
Form No. SPEC-090A Revised: 08/2004
Herewith find deposit in the form of a cashier’s check in the amount of $__________________ which amount is not less than 5-percent of the total bid.
SIGN HERE__________________________________
BID BOND
KNOW ALL MEN BY THESE PRESENTS:
That we, ______________________________________________________________, as Principal, and
______________________________________________________________________, as Surety, are held and firmly bound unto the City of Tacoma, as Obligee, in the penal sum of __________________
_________________________________________________ dollars, for the payment of which the Principal and the Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, by these presents.
The condition of this obligation is such that if the Obligee shall make any award to the Principal for according to the terms of the proposal or bid made by the Principal therefor, and the Principal shall duly make and enter into a contract with the Obligee in accordance with the terms of said proposal or bid and award and shall give bond for faithful performance thereof, with Surety or Sureties approved by the Obligee; or if the
Principal shall, in case of failure to do so, pay and forfeit to the Obligee the penal amount of the deposit specified in the call for bids, then this obligation shall be null and void; otherwise it shall be and remain in full force and effect and the Surety shall forthwith pay and forfeit to the Obligee, as penalty and liquidated damages, the amount of this bond.
SIGNED, SEALED AND DATED THIS _______________ DAY OF __________________, 20______.
PRINCIPAL: SURETY:
__________________, 20______
Received return of deposit in the sum of $ _______________________________________________
Subcontractor Categories of Work
Revised: 7/22/2025
Supplier Name: Spec Number:
Project Name:
Subcontractor(s) that are proposed to perform the work of: HVAC (heating, ventilation and air conditioning), and/or plumbing, as described in Chapter 18.106 RCW, and/or electrical as described in Chapter 19.28 RCW must be listed below. Proof of License must also be provided. This information must be submitted with the bid proposal.
Subcontractor(s) that are proposed to perform the work of structural steel installation and/or rebar installation must be listed below. This information must be submitted with the bid proposal or within forty-eight hours of the published bid submittal time via email to sendbid@tacoma.gov
Failure to list subcontractors or naming more than one subcontractor to perform the same work will result in a bid being non-responsive. Contractors self-performing must list themselves below if licensed to perform the work including their specialty license numbers if applicable. General contractor license numbers given for specialty work may result in a non-responsive bid. The work to be performed is to be listed below the subcontractor(s) name.
Subcontractor Name:
(and License Number, if required)
Work to be performed:
Subcontractor Name:
(and License Number, if required)
Work to be performed:
Subcontractor Name:
(and License Number, if required)
Work to be performed:
Subcontractor Name:
(and License Number, if required)
Work to be performed:
Subcontractor Name:
(and License Number, if required)
Work to be performed:
mailto:sendbid@tacoma.gov
Specification Number: _______________________
Name of Bidder: _____________________________
Revised: 7/01/2026
State Responsibility and Reciprocal Bid Preference Information
A). Certificate of registration as a contractor (Must be in effect at time of bid submittal).
Number: ________________________________ Effective Date: ___________________________ Expiration Date: __________________________
B). Current Washington Unified Business Identifier (UBI) Number:
Number: _________________________________
C). Do you have industrial insurance (workers compensation) coverage for your employees working in Washington?
☐ Yes ☐ No ☐ Not applicable
Washington Employment Security Department Number:
Number: _________________________________
Washington Department of Revenue state excise tax Registration number:
Number: __________________________________
D). Have you been disqualified from bidding on any public works contracts under RCW
39.06.010 or 39.12.065 (3)?
If yes, provide an explanation of your disqualification on a separate page.
E). Have you been found out of compliance by the Washington state apprenticeship and training council for working apprentices out of ratio, without appropriate supervision, or outside their approved work processes as outlined in their standards of apprenticeship under chapter 49.04 RCW for the one-year period immediately preceding the date of the bid solicitation disqualification on a separate page
F). Have received training on the requirements related to public works and prevailing wage under chapter 39.04 RCW and chapter 39.12 RCW?
☐ Yes ☐ No ☐ Exempt
G). Have you, within the three-year period immediately preceding the date of the bid solicitation, have you been determined by a final and binding citation and notice of assessment issued by the department of labor and industries or through a civil https://app.leg.wa.gov/rcw/default.aspx?cite=39.06.010 https://app.leg.wa.gov/rcw/default.aspx?cite=39.12.065 http://app.leg.wa.gov/RCW/default.aspx?cite=49.04 http://app.leg.wa.gov/RCW/default.aspx?cite=39.12
Specification Number: _______________________
Name of Bidder: _____________________________
Revised: 7/01/2026 judgment entered by a court of limited or general jurisdiction to have willfully violated, as defined in RCW 49.48.082, any provision of chapter 49.46, 49.48, or 49.52 RCW disqualification on a separate page
H). At the time of bid submittal, have you been subject to a revocation of a minor work permit under RCW 49.12.390(4)?
If yes, provide an explanation on a separate page
Do you have a physical office located in the State of Washington?
If incorporated, in what state were you incorporated?
State: ___________________________________
If not incorporated, in what state was your business entity formed?
State: ___________________________________
Submittal of your signed bid constitutes your statement under penalty of perjury as required by RCW 39.04.350 (2), that you are in compliance with the responsible bidder criteria requirements of (G) and (H) above.
http://app.leg.wa.gov/RCW/default.aspx?cite=49.48.082 http://app.leg.wa.gov/RCW/default.aspx?cite=49.46 https://app.leg.wa.gov/rcw/default.aspx?cite=49.48 http://app.leg.wa.gov/RCW/default.aspx?cite=49.52 http://app.leg.wa.gov/RCW/default.aspx?cite=49.12.390
\Page 1
SPECIFICATION NO.: PW26-0140F
GENERAL CONTRACTOR QUALIFICATIONS SUBMITTAL
This form shall be completed in its entirety, submitted with the bid, and shall be used to demonstrate the General Contractor’s minimum experience. Failure to submit this form may be grounds for bid rejection.
The City shall be the sole judge in determining if the prospective Contractor meets the bidder minimum experience requirements. The City reserves the right to take whatever action it deems necessary to ascertain the ability of the bidder to perform the work satisfactorily.
Qualification of General Contractor: General Contractor shall have a minimum of five (5) projects, of similar size and scope within the last five (5) years, demonstrating an ability to meet the contract schedule and requirements. General Contractor shall meet all Local and State Certifications and License requirements prior to bidding. Copies of the required Certificates and Licenses shall be made available upon request.
Name:
(General Contractor)
Address:
Contact Person: Phone:
Project Experience:
Project No. 1 Name:
Project Owner:
Owner Contact / Phone No.:
Date Work Completed:
Description of Work:
Project No. 2 Name:
Project Owner:
Owner Contact / Phone No.:
Date Work Completed:
Description of Work:
GENERAL CONTRACTOR QUALIFICATIONS SUBMITTAL
\Page 2
Project No. 3 Name:
Project Owner:
Owner Contact / Phone No.:
Date Work Completed:
Description of Work:
Project No. 4 Name:
Owner Contact / Phone No.:
Contact Person:
Date Work Completed:
Description of Work:
Project No. 5 Name:
Owner Contact / Phone No.:
Contact Person:
Date Work Completed:
Description of Work:
GENERAL CONTRACTOR QUALIFICATIONS SUBMITTAL
\Page 3
Certification of Compliance with Wage Payment Statutes 09/20/2018
Certification of Compliance with Wage Payment Statutes
The bidder hereby certifies that, within the three-year period immediately preceding the bid solicitation date (July 7, 2026), that the bidder is not a “willful” violator, as defined in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the
Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction.
I certify under penalty of perjury under the laws of the state of Washington that the foregoing is true and correct.
Bidder
Signature of Authorized Official*
Printed Name
Title
Date City State
Check One:
Individual ☐ Partnership ☐ Joint Venture ☐ Corporation ☐
State of Incorporation, or if not a corporation, the state where business entity was formed:
If a co-partnership, give firm name under which business is transacted:
* If a corporation, proposal must be executed in the corporate name by the president or vice-president
(or any other corporate officer accompanied by evidence of authority to sign). If a co-partnership, proposal must be executed by a partner.
CONTRACT FORMS (POST AWARD)
1. CONTRACT
2. INSURANCE CERTIFICATE REQUIREMENTS
3. PERFORMANCE BOND TO THE CITY OF TACOMA
4. PAYMENT BOND TO THE CITY OF TACOMA
5. GENERAL RELEASE TO THE CITY OF TACOMA
6. TPD DRAFT FORMS FOR FACILITY ACCESS
S A M
P
LE
Supplies_PurchasedServices_PW Form No. SPEC-120A CW####### Template Revised: 02/03/2022 Page 1 of 9
CONTRACT
Resolution No.
Contract No.
This Contract is made and entered into effective as of [Month], [Day], [Year] (“Effective Date”) by and between the City of Tacoma, a Municipal Corporation of the State of Washington (“City”), and [supplier name as it appears in Ariba, including dbas or trade names] (“Contractor”).
That in consideration of the mutual promises and obligations hereinafter set forth the Parties hereto agree as follows:
I. Contractor shall fully execute and diligently and completely perform all work and provide all services and deliverables described herein and in the items listed below each of which are fully incorporated herein and which collectively are referred to as “Contract Documents”:
1. Specification No. [Spec Number] [ Spec Title] together with all authorized addenda.
2. Contractor’s submittal [or specifically described portions thereof] dated [Enter Submittal Date] submitted in response to Specification No. [Spec Number] [Spec Title].
3. Describe with specific detail and list separately any other documents that will make up the contract (fee schedule, work schedule, authorized personnel, etc.) or any other additional items mutually intended to be binding upon the parties.
II. If federal funds will be used to fund, pay or reimburse all or a portion of the services provided under the Contract, the terms and conditions set forth at this Appendix A are incorporated into and made part of this Contract and CONTRACTOR will comply with all applicable provisions of Appendix A and with all applicable federal laws, regulations, executive orders, policies, procedures, and directives in the performance of this Contract.
If CONTRACTOR’s receipt of federal funds under this Contract is as a sub-recipient, a fully completed Appendix B, “Sub-recipient Information and Requirements” is incorporated into and made part of this Contract.
III. In the event of a conflict or inconsistency between the terms and conditions contained in this document entitled Contract and any terms and conditions contained the above referenced Contract Documents the following order of precedence applies with the first listed item being the most controlling and the last listed item the least controlling:
1. Contract, inclusive of Appendices A and B.
2. List remaining Contract Documents in applicable controlling order.
IV. The Contract terminates on xxxxx, and may be renewed for xxxxxxxx
V. The total price to be paid by City for Contractor’s full and complete performance hereunder, including during any authorized renewal terms, may not exceed:
$[Dollar Amount], plus any applicable taxes.
VI. Contractor agrees to accept as full payment hereunder the amounts specified herein and in Contract Documents, and the City agrees to make payments at the times and in the manner and upon the terms and conditions specified. Except as may be otherwise provided herein or in Contract Documents Contractor shall provide and bear the expense of all equipment, work and labor of any sort whatsoever that may be required for the transfer of materials and for constructing and completing the work and providing the services and deliverables required by this Contract.
VII. The City’s preferred method of payment is by ePayables (Payment Plus), followed by credit card (aka procurement card), then Electronic Funds Transfer (EFT) by Automated Clearing House (ACH), then check or other cash equivalent. CONTRACTOR may be required to have the capability of accepting the City’s ePayables or credit card methods of payment. The City of Tacoma will not accept price changes or pay additional fees when ePayables (Payment Plus) or credit card is used. The City, in its sole discretion, will determine the method of payment for this Contract.
M
P
LE
Supplies_PurchasedServices_PW Form No. SPEC-120A CW####### Template Revised: 02/03/2022 Page 2 of 9
VIII. Failure by City to identify a deficiency in the insurance documentation provided by Contractor or failure of City to demand verification of coverage or compliance by Contractor with the insurance requirements contained in the Contract Documents shall not be construed as a waiver of Contractor’s obligation to maintain such insurance.
IX. Contractor and for its heirs, executors, administrators, successors, and assigns, does hereby agree to the full performance of all the requirements contained herein and in Contract Documents.
It is further provided that no liability shall attach to City by reason of entering into this Contract, except as expressly provided herein.
IN WITNESS WHEREOF, the Parties hereto have accepted and executed this Contract, as of the Effective Date stated above, which shall be Effective Date for bonding purposes as applicable.
CITY OF TACOMA: CONTRACTOR:
Signature: Signature:
Name: Name:
Title: Title:
(City of Tacoma use only - blank lines are intentional)
Director of Finance: ______________________________________________________________
Deputy/City Attorney (approved as to form): _________________________________________________
Approved By: ___________________________________________________________________
Approved By: ___________________________________________________________________
Approved By: ___________________________________________________________________
Approved By: ___________________________________________________________________
Approved By: ___________________________________________________________________
Approved By: ___________________________________________________________________
APPENDIX A
FEDERAL FUNDING
M
P
LE
Supplies_PurchasedServices_PW Form No. SPEC-120A CW####### Template Revised: 02/03/2022 Page 3 of 9
1. Termination for Breach
CITY may terminate this Contract in the event of any material breach of any of the terms and conditions of this Contract if CONTRACTOR’s breach continues in effect after written notice of breach and 30 days to cure such breach and fails to cure such breach.
2. Prevailing Wages
1. If federal, state, local, or any applicable law requires CONTRACTOR to pay prevailing wages in connection with this Contract, and CONTRACTOR is so notified by the CITY, then CONTRACTOR shall pay applicable prevailing wages and otherwise comply with the Washington State Prevailing Wage Act (RCW 39.12) in the performance of this Contract.
2. If applicable, a Schedule of Prevailing Wage Rates and/or the current prevailing wage determination made by the Secretary of Labor for the locality or localities where the Contract will be performed is made of part of the Contract by this reference. If prevailing wages apply to the Contract, CONTRACTOR and its subcontractors shall:
i. Be bound by and perform all transactions regarding the Contract relating to prevailing wages and the usual fringe benefits in compliance with the provisions of Chapter 39.12 RCW, as amended, the Washington State Prevailing Wage Act and/or the Davis-Bacon Act (40 U.S.C. 3141- 3144, and 3146-3148) and the requirements of 29 C.F.R. pt. 5 as may be applicable, including the federal requirement to pay wages not less than once a week.
ii. Ensure that no worker, laborer or mechanic employed in the performance of any part of the Contract shall be paid less than the prevailing rate of wage specified on that Schedule and/or specified in a wage determination made by the Secretary of Labor (unless specifically preempted by federal law, the higher of the Washington state prevailing wage or federal Davis-Bacon rate of wage must be paid.
iii. Immediately upon award of the Contract, contact the Department of Labor and Industries, Prevailing Wages section, Olympia, Washington and/or the federal Department of Labor, to obtain full information, forms and procedures relating to these matters. Per such procedures, a Statement of Intent to Pay Prevailing Wages and/or other or additional documentation required by applicable federal law, must be submitted by CONTRACTOR and its subcontractors to the CITY, in the manner requested by the CITY, prior to any payment by the CITY hereunder, and an Affidavit of Wages Paid and/or other or additional documentation required by federal law must be received or verified by the CITY prior to final Contract payment.
3. COPELAND ANTI-KICKBACK ACT
For Contracts subject to Davis Bacon Act the following clauses will be incorporated into the Contract:
A. CONTRACTOR shall comply with 18 U.S.C. § 874, 40 U.S.C. § 3145, and the requirements of 29 C.F.R. pt. 3 as may be applicable, which are incorporated by reference into this Contract.
B. CONTRACTOR or subcontractor shall insert in any subcontracts the clause above and such other clauses federal agencies may by appropriate instructions require, and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts.
M
P
LE
Supplies_PurchasedServices_PW Form No. SPEC-120A CW####### Template Revised: 02/03/2022 Page 4 of 9
The prime contractor shall be responsible for the compliance by any subcontractor or lower tier subcontractor with all of these Contract clauses.
C. Breach. A breach of the contract clauses above may be grounds for termination of the contract, and for debarment as a contractor and subcontractor as provided in 29 C.F.R. § 5.12.
4. EQUAL EMPLOYMENT OPPORTUNITY
During the performance of this Contract, CONTRACTOR will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin. If the CONTRACTOR does over $10,000 in business a year that is funded, paid or reimbursed with federal funds, CONTRACTOR will take specific and affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action shall include, but not be limited to the following:
A. Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising;
layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. CONTRACTOR agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.
B. CONTRACTOR will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin.
C. CONTRACTOR will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .