PW#2026-005_1st_Ave_NE_SUP-BID_FORM.pdf
PDF 252 KB Posted
- Attached to
- 1st Ave NE Shared Use Path - N 120th to N 130th
- Solicitation number
- PW#2026-005
- Issued by
- King County, Spokane City, Washington
About this file
This is a bid form and contract document for a construction project issued by the City of Seattle, Department of Transportation. The project involves improvements to the 1st Ave NE Shared Use Path between N 120th Street and N 130th Street, located on the east side of 1st Ave NE. The base bid scope includes pavement removal, roadway paving, sidewalks, curb ramps, driveways, storm drainage, landscaping, channelization, and signage. An additive work package includes electrical systems, foundations, and pedestrian lighting. Bids are due by 2:00 p.m. on October 28, 2026, with public opening and oral reading of bids occurring immediately thereafter at Seattle Municipal Tower, Suite 4350, 700 Fifth Avenue, Seattle, Washington 98104. The contract completion timeline is 120 working days for the base bid and 140 working days if the additive is included. Bidders must have examined the project site and bid documents prior to submission. Electronic bid submission is required through the OpenGov platform.
The engineer's estimate for the base bid ranges from $2,800,000 to $3,300,000, with an additive estimated between $270,000 and $330,000. The project is funded by the 2024 Seattle Transportation Levy and Traffic Safety Camera Fund. A bid guaranty of at least five percent of the total bid amount, including retail sales tax, is required in the form of a cashier's check, certified check, or bid bond. Bidders must meet responsible bidder requirements under RCW 39.04.350, including possession of a certificate of registration, UBI number, industrial insurance coverage, employment security number, and state excise tax registration number. The contract includes an Inclusion Plan requirement as a condition of award and a Bidder/Subcontractor List requirement. Contractors must comply with prevailing wage requirements under Chapter 39.12 RCW and non-discrimination requirements under SMC Chapter 20.42. Liquidated damages will be assessed for failure to complete work within the specified timeframe, calculated in accordance with Section 1-08.9 of the specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PW#2026-005_1st_Ave_NE_SUP-PLANS.pdf | ||
| PW#2026-005_1st_Ave_NE_SUP-PROJECT_MANUAL.pdf | ||
| PW#2026-005_1st_Ave_NE_SUP-APPENDIX.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funded by: 2024 Seattle Transportation Levy and Traffic Safety Camera Fund
Bids Open: October 28, 2026
CITY OF SEATTLE
BID FORMS
Improvement of:
1st Ave NE Shared Use Path – N 120th to N 130th
PW#2026-005
1st Ave NE Shared Use Path – N 120th to N 130th Page 1 0-01.1 Instructions to Bidders
Version: 08/08/2025– City
BID REQUIREMENTS
0-01.1 INSTRUCTIONS TO BIDDERS
I. GENERAL
This Contract will be administered by the Director of the Seattle Department of Transportation, subject to the approval and acceptance of the Director of Finance and Administrative Services. All questions must be e-mailed and be directed to the following:
Before Bid Opening: David Vijarro Seattle Department of Transportation David.Vijarro@seattle.gov 206-615-1643
After Bid Opening and Before Execution:
Purchasing and Contracting FAS_PW_Admin@seattle.gov 206-684-0444
After Execution: Jesse Lopez Seattle Department of Transportation Construction Management Jesse.Lopez@Seattle.Gov
206-854-5343
Inclusion Plan: All questions on the Inclusion Plan must be directed to Miguel Beltran at Miguel.beltran@seattle.gov or 206-684-4525. Backup contact is Carmen Kucinski at carmen.kucinski@seattle.gov or 206-684-0188.
II. BID OPENING
The authorized Bid Form must be submitted as specified in Section 1-02.9(1). In accordance with Section 1-02.12, Bids will be opened and read orally immediately after 2:00 p.m. on October 28, 2026 at the following address:
City of Seattle Purchasing and Contracting Seattle Municipal Tower Suite 4350 700 Fifth Avenue Seattle, Washington 98104
III. TIME OF COMPLETION
Work must begin immediately on the Notice To Proceed Date in the Written Notice from the Engineer and after the date of such notice must be physically completed within the following period per Section 3 of the Agreement:
BASE BID – 120 WORKING DAYS
BASE BID PLUS ADDITIVE - 140 WORKING DAYS
IV. LIQUIDATED DAMAGES
If the successful Contractor fails to complete Work within the time set forth above, (s)he will be charged Liquidated Damages per Section 4 of the Agreement and Section 1-08.9. See Section 1-08.9 for method for determining cost of liquidated damages.
V. SUBSURFACE INFORMATION
Refer to Section 1-02.4(2) for information about any geotechnical or environmental reports, soil boring data, soil sample test data, or other data accumulated by the Engineer.
1st Ave NE Shared Use Path – N 120th to N 130th Page 2 0-01.1 Instructions to Bidders
Version: 08/08/2025– City
VI. ITEMS OF INTEREST TO BIDDERS
Reference Addenda ...................................................................................................................................... 1-02.6 Additive, Alternate, Deductive ................................................................................................... 1-02.11 Award of Contract ........................................................................................................................ 1-03.2 Bidder, Responsible ................................................................................................................... 1-02.1 Bidder/Subcontractor List ..................................................................................................... 1-02.9(3) Bid, Form and Style of ................................................................................................................. 1-02.5 Bid Guaranty................................................................................................................................ 1-02.7 Bid Guaranty, Return of ............................................................................................................... 1-03.5 Bids, Public Opening of ............................................................................................................ 1-02.12 Bid Submittal .......................................................................................................................... 1-02.9(1) Bid Submittal Date, Change of ............................................................................................... 1-02.9(2) Bid Tabulation ........................................................................................................................ 1-03.1(1) Bid, Modification or Withdrawal of ............................................................................................. 1-02.10 Bidders, Disqualification of ........................................................................................................ 1-02.14 Bidders, Qualifications of ............................................................................................................. 1-02.1 Bids, Irregular ............................................................................................................................ 1-02.13 Bond, Bid — see Bid Guaranty ................................................................................................... 1-02.7 Bond, Payment and Performance .......................................................................................... 1-03.3(2) Contract, Execution of ................................................................................................................. 1-03.3 Contract, Failure to Execute the .................................................................................................. 1-03.4 Equal Benefits, Affirmative Efforts, Equal Employment Opportunity and Non-Discrimination Requirements ............................................................................................................................ 1-07.11 Error, Claim of ........................................................................................................................ 1-03.1(2) Examination of Bid Documents and Project Site......................................................................... 1-02.4 Information, Pre-Award .......................................................................................................... 1-03.1(4) Evidence of Insurance ............................................................................................................ 1-03.3(1) Liquidated Damages ...............................................................Agreement Form, Section 4 and 1-08.9 Non Collusion Requirement ........................................................................................................ 1-02.8 Inclusion Plan ........................................................................ 1-02.9(4), 1-02.13, 1-03.1(4), 1-07.11(3) Supplemental Bidder Responsibility Criteria ............................................................................... 1-02.2 Owner, Rights of the ............................................................................................................... 1-03.1(4) Responsible Bidder Requirements .............................................................................................. 1-02.1 Quantities, Estimated .................................................................................................................. 1-02.3 Time for Completion ................................................................Agreement Form, Section 3 and 1-08.5 Wages, Prevailing Wages ...................................................................................................... 1-07.9(1)
VII. USE OF RECYCLED MATERIALS
Refer to Section 9-03.16 for information on the use of recycled Materials in Aggregates.
Refer to Sections 5-05.3(1) and 6-02.3(1) for information on the use of pozzolans in cement concrete.
Other Sections of the Contract may also allow for the use of recycled Materials.
The Bidder must submit a Recycled Materials Proposal form with the Bid per Section 1-02.5(1).
VIII. REQUIREMENTS TO RECYCLE MATERIALS
Refer to Section 1-07.3(4) for information on requirements to recycle materials.
Other Sections of the Contract may also require the recycling of materials.
1st Ave NE Shared Use Path – N 120th to N 130th Page 3 0-01.2 Checklist for Bidders
Version: 08/08/2025– City
0-01.2 CHECKLIST FOR BIDDERS
The following items must be completed:
1. Bid Form – Unit Prices (Section 0-01.3):
• Include unit prices and unit price extensions for each Bid item on all Bid Schedules (when indicated) and Additives (when indicated).
• Complete Bid summary.
2. Declaration (Section 0-01.3(1))
• Acknowledge all Addenda issued as a part of this Contract
• Complete and sign Declaration. Signer must be authorized to legally bind the Bidder.
3. Bid Guaranty (Section 1-02.7):
• Must not be less than 5% of the maximum Bid amount including retail sales tax.
4. With regard to Section 0-01.4 INCLUSION PLAN:
a. Have you completed the Inclusion Plan? This form must be submitted with your bid if the Owner has estimated the Project will cost over $300,000. The Inclusion Plan is a condition of Award for this Contract.
5. Bidder / Subcontractors List (Section 0-1.5, 1-02.9(3)):
a. Have you completed and signed the Bidder/Subcontractor List? This list is required to be submitted if the Owner has estimated the Project will cost $1,000,000 or more.
b. For the purpose of evaluating the Bidder/Subcontractor List, refer to Section 1-02.9(3) for the determination by the Owner of what trades are included in the project. Failure to name a Subcontractor(s) or name itself to perform the trades of work may render the Bidder’s Bid non-responsive and rejected.
c. Failure to complete, sign, and submit the Bidder/Subcontractor list with the Bid Forms will result in the Bid being declared non-responsive.
6. Supplemental Bidder Responsibility Criteria (Section 1-02.2):
• The Supplemental Bidder Responsibility Criteria Form and any additional documentation must be submitted to PC within three (3) Business Days of receipt of request.
7. Recycled Materials Proposal (Section 1-02.5(1)):
• Submit the “Proposal for Incorporating Recycled Materials into the Project” with the Bid.
Bid Submittal:
1.) Electronic Bid Submittal:
Submit Bids only through OpenGov. Bids are due at 2:00 PM on the Bid opening date. PC will accept Electronic Signature for the Declaration and the Bidder/Subcontractor List, if applicable. Required documents to support the Bid that are due after the Bid Opening time must be submitted as a PDF file(s) with a maximum individual file size of 15MB. The Bidder must email the PDF file(s) by the appropriate deadline to the following address:
FAS_PWSecureBid@seattle.gov.
Identify both the email and the attached Post Bid Submittal File with the full Public Works Contract Number (PW#) and name of the Bidder (e.g. “PW# 2020-001 – Joe’s Construction”).
Bid Opening: Bids received by 2:00 P.M. on October 28, 2026 will be publicly opened and read immediately after 2:00 P.M. on October 28, 2026. See Section 1-02.12.
1st Ave NE Shared Use Path – N 120th to N 130th Page 4 0-01.3 Bid Form
Version: 08/08/2025– City
0-01.3 BID FORM
TO THE DIRECTOR OF FINANCE AND ADMINISTRATIVE SERVICES OF THE CITY OF SEATTLE:
A. The undersigned Bidder hereby certifies to have personally and carefully examined the Bid Documents issued for: 1st Ave NE Shared Use Path – N 120th to N 130th , as authorized under Ordinance Number(s) 127362.
B. The Bidder has examined the Project Site where the Work is to be performed and the conditions affecting the Work;
C. Understanding that the quantities shown in the Bid are estimates only, being given for the purposes of comparing Bids, the Bidder hereby proposes to furnish all Material and labor and to perform all Work which may be required, and to complete the Work within the time fixed and upon the terms and conditions provided in the Bid Documents for the following prices:
D. The Bidder has attached a Bid Guaranty in the amount of five percent (5%) of the Total Bid including retail sales tax in the form of cashier’s check, certified check, or Bid bond;
(NOTE: The letters “SP” whenever appearing in the Bid item number column of the Bid Form indicate that additions or revisions to the Standard Specifications applicable to that Bid item are included in the Standard Supplemental Specifications and Special Provisions. The Contractor is advised to review those requirements regarding Bid items so designated.
The number to the left of the Bid item description denotes the “Bid item code” for that particular Bid item.
If it is a six-digit number, the first three digits indicate the associated Specification division and section number. If it is a seven-digit number, the first digit denotes the schedule number and the next three digits indicate the associated Specification division and section number. The last three digits comprise the identification number for that item within the particular Section.
A separate schedule will be issued for those items the Owner will pay retail sales tax in accordance with the excise tax Rule 170 (refer to Section 1-07.2(3) of the Specifications). For all other Bid items, the Contractor must include retail sales tax in accordance will the excise tax Rule 171 (refer to Section 1- 07.2(2) of the Specifications).
1st Ave NE Shared Use Path – N 120th to N 130th Page 5 0-01.3 Bid Form
Version: 08/08/2025– City
The Bid Forms can be found as a separate attachment at: https://procurement.opengov.com/portal/seattle
NOTE TO BIDDERS:
Bidders must submit pricing proposal through OpenGov as specified in the bid documents.
1st Ave NE Shared Use Path – N 120th to N 130th Page 6 0-01.3(1) Declaration
Version: 08/08/2025– City Bid Declaration: FAS Rev Aug 28 2024
0-01.3(1) DECLARATION
I declare, under penalty of perjury under the Laws of the State of Washington, as follows:
A. BID: I agree to perform the Work in compliance with the Bid Documents, for the prices stated in the OpenGov Bid Form.
B. NON-DISCRIMINATION: I agree to ensure equal opportunity for employment and to engage in Affirmative Efforts in the solicitation of women and minorities and WMBE firms for participation on this Contract in accordance with SMC Ch. 20.42 and RCW 35.22.650.
C. NON COLLUSION: I have not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free, competitive bidding in the preparation and submission of a Bid to the Owner for consideration in the award of a contract on the improvement described in the Bid Documents.
D. My bid takes into account the requirements imposed by Section 1-07.18, Subsection 6 which waives, with respect to the Owner only, the Contractor’s immunity under RCW Title 51, (Industrial Insurance) of the Revised Code of Washington.
E. I agree to comply with the requirements regarding subcontracting, and the purchase of supplies or materials from firms that are not disqualified or otherwise debarred from doing business with the City under the provisions of SMC Ch. 20.42 or SMC Ch. 20.70.
F. Responsible Bidder Requirements: My bid acknowledges that I am in compliance with all of the responsible bidder requirements under RCW 39.04.350, including: having a certificate of registration under RCW 18.27 prior to bidding; a UBI number; industrial insurance coverage if required under Title 51 RCW; an employment security number under Title 50; a state excise tax registration number under Title 82; and have received training on requirements related to public works and prevailing wage by Labor and Industries or approved training provider under RCW 39.04.350, and chapter 39.12 or are exempted by Labor and Industries https://secure.lni.wa.gov/verify I affirm I am not disqualified from bidding on any public works contract under RCW 39.06 or RCW 39.12.065(3) or on the System for Award Management (SAM.gov). I will provide proof of these requirements if requested.
1st Ave NE Shared Use Path – N 120th to N 130th Page 7 Recycled Materials Proposal
Rev 07/2020
PROPOSAL FOR INCORPORATING RECYCLED MATERIALS
Replace this sheet in the Bid Form package with the form titled “Proposal for Incorporating Recycled Materials into the Project.”
1st Ave NE Shared Use Path – N 120th to N 130th Page 8 0-02.1 Agreement (Contract) Form (Page 2 of 3)
CONTRACT REQUIREMENTS
0-02.1 AGREEMENT (CONTRACT) FORM
This agreement by and between the Director of the Department of Finance and Administrative Services, acting on behalf of The City of Seattle, a municipal corporation of the State of Washington, hereinafter referred to as the Owner, and
, hereinafter referred to as the
Contractor, witnesseth that in accordance with the terms and conditions of Contract PW#2026-005 awarded the ____________Day of ________________, 20 the parties agree as follows:
SECTION 1. That the Contractor must do or cause to be done all Work and must furnish or cause to be furnished all tools, Materials, Equipment, Supplies and labor necessary to improve
1st Ave NE Shared Use Path – N 120th to N 130th as ordered by Ordinance No. 127362 in all respects, in accordance with and as described in the Contract Documents now on file in the office of the Engineer for the following Awarded Contract Price:
Base Bid .......................................... $
Additive ............................................ $
State Sales Tax (10.55 %) .............. $ N/A
Awarded Contract Price .................. $
The Contractor must provide and bear the expense of all Equipment, Material, Supplies, work, and labor of any sort whatsoever that may be required for the transfer of Materials and for constructing and completing the Work provided for in this Contract and every part thereof, except such as are mentioned in the Contract Documents furnished by the Owner.
SECTION 2. The parties are bound by the Constitution and Laws of the State of Washington and the Charter, Ordinances, Rules and Regulations of the City of Seattle and by all applicable federal laws and government regulations, which provisions are incorporated by reference herein.
For the convenience of the parties of this Contract it is mutually agreed that any claims or causes of action which the Contractor has against the Owner arising from this Contract must be brought within 180 Calendar Days from the Completion Date of the Contract. It is further agreed by the parties that any such claims, disputes, or causes of action which cannot be resolved pursuant to the procedures set forth in the Contract Documents must be brought only in the Superior Court of King County. The parties understand and agree that the Contractor’s failure to bring suit within the time period provided shall be a complete bar to any such claims or causes of action.
SECTION 3. The Contractor must begin the Work of the Contract on the Notice to Proceed Date stated in the Notice to Proceed issued to said Contractor by the Engineer, and to carry said Work on regularly and without interruption thereafter (unless the Engineer specifically directs otherwise, in writing) with such forces as to physically complete said Work in a manner acceptable to the Engineer within
BASE BID – 120 WORKING DAYS
BASE BID PLUS ADDITIVE - 140 WORKING DAYS
after such notice to begin Work; the time of beginning, rate of progress, and time of completion being essential and material provisions of the Contract.
1st Ave NE Shared Use Path – N 120th to N 130th Page 9 0-02.1 Agreement (Contract) Form (Page 2 of 3)
SECTION 4. If the Work is not completed within the time specified, the Contractor must pay to the Owner, as Liquidated Damages, the sum dependent upon the Contract Award amount in accordance with Section 1-08.9, for each and every Working Day the Work remains uncompleted after expiration of the specified time, exclusive of those Days wherefore the Engineer has granted an extension of time.
The Contractor hereby agrees the amount set forth above is a reasonable estimate of actual damage which would be caused by the failure to complete the work on time, and that the amount indicated is for Liquidated Damages and is not a penalty.
SECTION 5. The Owner agrees to employ the Contractor to complete the Work in accordance with the Contract Documents and agrees to pay for the same according to the schedule of unit, lump sum, or itemized prices listed in the Bid Form, at the time and in the manner and upon the conditions provided for in the Contract.
The Contractor must inform all Subcontractors who work on the Improvement named in Section 1 of this Agreement of the manner and method of payment and the manner and method of measuring or computing the quantities of subcontracted work.
SECTION 6. In accordance with Chapter 39.12 RCW, the City Charter, and the Project Manual, the Contractor must pay, or cause to be paid to persons employed on or in connection with this Work, not less than the prevailing rate of wage for an hour’s work specified for the labor performed.
SECTION 7. The Contractor on behalf of his or her heirs, executors, administrators, successors, and assigns, does hereby agree to the full performance of all the covenants to which the Contractor is obligated under the terms of the Contract.
SECTION 8. It is further provided that no liability will attach to the Owner by reason of entering into this Contract except as expressly provided herein.
SECTION 9. If the Contractor violates any material covenant or any provision of this Contract the Owner may: withhold payment due on any work done under the Contract until the Contractor complies with the Contract; order that the Work may be stopped, terminate the Contract, debar the Contractor in accordance with SMC 20.70.
SECTION 10: The Contractor shall acknowledge that they have received and read the Consent Decree between the city and the United States of America and agree that all Work in this Contract shall be performed in conformity with the terms of the Consent Decree.
1st Ave NE Shared Use Path – N 120th to N 130th Page 10 0-02.1 Agreement (Contract) Form (Page 3 of 3)
Contractor must declare option for management of statutory retained percentage of this Contract by checking applicable box below.
Contractor elects to submit a bond in lieu of retained funds.
Contractor hereby elects to have the retained percentage of this Contract held in a non-interest bearing fund by The City of Seattle until sixty (60) Days following the Completion Date.
Contractor hereby elects to have The City of Seattle invest the retained percentage of the Contract from time to time as such retained percentage accrues and in accordance with RCW 60.28.011, .021 and .051. Contractor hereby designates:
Name of Financial Institution
Street Address, City, State, Zip Code
City, State, Zip Code of Financial Institution as the repository for the escrow of said funds. Contractor hereby further agrees to be fully responsible for payment of all costs or fees incurred as a result of placing said retained percentage in escrow and investing it as authorized by statute. The City of Seattle shall not be liable in any way for any cost or fees in connection therewith.
IN WITNESS WHEREOF, the Owner has caused these presents to be signed by the designee of Director of Finance and Administrative Services ; and the Contractor has hereunto affirmed his or her signature.
THE CITY OF SEATTLE
Director of Finance and Administrative Services
By Date Director, Purchasing and Contracting
CONTRACTOR
Business name
By Date
Title
1st Ave NE Shared Use Path – N 120th to N 130th Page 11 0-02.3 Plans, Drawings and Specifications
Version: 08/08/2025– City
0-02.3 PLANS, DRAWINGS AND SPECIFICATIONS
The Work must be accomplished in accordance with these General Special Provisions (GSP) and Special Provisions (SP) together with the provisions, insofar as they are applicable, of the following documents:
1. The Engineering Drawing No. 894-30, Sheets 1 through 64.
2. The City of Seattle Standard Plans and Standard Specifications, which are comprised of:
a. “2023 edition City of Seattle Standard Specifications for Road, Bridge and Municipal Construction” (hereinafter referred to as the Standard Specifications).
b. “2023 edition City of Seattle Standard Plans for Municipal Construction” (hereinafter referred to as the Standard Plans) except modified, updated, or additional Standard Plans included in the appendix. Standard Plans included in the appendix of the Contract must be considered Standard Plans for this Contract.
c. City of Seattle Traffic Control Manual for In-Street Work, 2024 edition, which supplements and is to be utilized in conjunction with the 2023 version of the “Manual on Uniform Traffic Control Devices for Streets and Highways (MUTCD),” as modified and adopted by the Washington Department of Transportation (WSDOT). The Revised Code of Washington (RCW) 47.36, requires traffic control devices along city streets to conform to the WSDOT adopted standards to the extent possible.
3. The terms and conditions of such permits, agreements, ordinances, regulations, instructions and requirements as may be included in the appendix or otherwise attached hereto.
4. Right of Way Opening and Restoration Rule effective at the Bid advertisement date: The Seattle Transportation Director’s Rule may be found at:
http://seattle.gov/transportation/stuse_pavementopen.htm
5. Director’s Rules based on the City of Seattle “Stormwater Code”, SMC Chapters 22.800 through 22.808.
6. SDOT Pedestrian Mobility in and around Work Zones Director’s Rule (10-2015) which may be found: http://www.seattle.gov/transportation/drules.htm
The Contractor must obtain copies of these publications at Contractor’s own expense.
0-02.4 LOCATION OF PROJECT
1st Ave NE from N 120th St to N 130th St N 120th to N130th
0-02.5 NATURE OF IMPROVEMENT
Base Bid includes pavement removal, roadway paving, sidewalks, curb ramps, driveways, storm Drain, landscaping, channelization and signage. Additive work includes, electrical, foundations and pedestrian lighting.
For the purpose of the Bidder/Subcontractor List, this project includes electrical and rebar installation.