ITB - North Fork Improvements Project
Solicitation number
S-C25102-00014532
Issued by
Marion County, Oregon

About this file

This is Addendum #1 to an Invitation to Bid issued by Marion County, Oregon's Public Works Department for the North Fork Improvements Project (PW1719-25), effective January 21, 2026. The addendum clarifies key project specifications and requirements through a question-and-answer format addressing 12 substantive inquiries from prospective bidders. The project encompasses earthwork and drainage, asphalt paving, and electrical work, including luminaires, conduit, wiring, and an informational kiosk. Paving section depths are specified by station on the contract plans, with existing pavement thickness matching required at culvert trenches and tie-ins as detailed in the standard drawings. Traffic control is to be deployed as needed, anticipated for culvert installation, paving operations, and Loop Road tie-ins to North Fork Road, while most Loop Road work may proceed with closures. The contract end date is October 22, 2026, when all work shall be complete. The addendum confirms that bidders must be prequalified through the Oregon Department of Transportation in at least one class of work (Earthwork and Drainage, Asphalt Paving, or Electrical), with prequalification required at least 10 days prior to the bid opening on February 11, 2026.

The addendum establishes that asphalt quantities in the bid schedule follow design quantities as interpreted under the 2024 Marion County General Conditions, while traffic control utilization is flexible and not restricted to daylight hours. Notably, the contractor is responsible for utility service coordination and meter installation, and must furnish luminaires per the contract's special provisions on LED roadway lighting systems. The kiosks are to be fully contractor-designed and constructed per contract plans and special provisions, with no county-specified vendor requirements or additional aesthetic or architectural review requirements beyond the contract documents. No known utility conflicts beyond those shown in the contract plans have been identified. This is a federally funded project subject to Davis-Bacon Act prevailing wage requirements and federal "Buy America" and "Build America Buy America" provisions, with no Disadvantaged Business Enterprise set-asides specified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PW1719-25 - ITB - North Fork Improvements Project Page 1 of 3

ADDENDUM #1

TO THE

INVITATION TO BID

PW1719-25 - ITB - NORTH FORK IMPROVEMENTS PROJECT

ISSUED ON 1/21/2026 9:00:00 AM

The following information in this addendum, hereby become part of the Invitation To Bid. It is essential that all prospective Offerors note the content of this Addendum.

A. Question and Answers:

1. Question #1

Should the 30-year pavement section be assumed everywhere for the decel lane, or are nates allowed?

a. Answer #1

Paving section depths are shown by station on Sheet 2A.

2. Question #2

Will existing pavement thickness matching be required at any tie-ins beyond what’s shown?

a. Answer #2

Existing pavement thickness match will be required for the culvert trench shown on Sheet

2A, Section 2. See Sheet 1A3 for the list of ODOT Standard Drawings. RD300 refers to

RD302, Construction Note 4.

3. Question #3

Are asphalt quantities in the bid schedule design quantities or pay quantities?

a. Answer #3

See the 2024 Marion County General Conditions, 00120.20 Interpretation of Quantities in Bid Schedule.

4. Question #4

Is traffic control assumed full-time during paving only, or for entire construction duration?

a. Answer #4

Traffic control will be used as needed. It is anticipated that flagging will be needed for culvert installation and paving, Loop Road tie “ins” to North Fork Road, and paving. It is assumed that traffic control will not be needed for most of the Loop Road work which can remain closed during construction.

5. Question #5

Are night or off-peak work windows allowed or prohibited?

a. Answer #5

Refer to Special Provision 00220.40 (e) (1) for single lane closures. For other work, night or off-peak hours are not prohibited.

6. Question #6

Who is responsible for utility service coordination and meter installation?

a. Answer #6

The Contractor is responsible to coordinate services and installation. See Sheet IL1

General Notes.

7. Question #7

Are luminaires County-furnished or contractor-furnished?

a. Answer #7

Luminaires are Contractor furnished per Contract Special Provisions 00970.16 LED

Luminaires on Roadway Lighting Systems.

8. Question #8

Is the kiosk a County-specified vendor, or fully contractor-supplied?

a. Answer #8

The kiosks are not supplied by the County. The kiosks will be built by the contractor per the Contract Plans and Special Provisions.

9. Question #9

Are there any aesthetic or architectural review requirements beyond plans?

a. Answer #9

No.

10. Question #10

Are there any anticipated early utility conflicts not shown on plans?

a. Answer #10

There are no known conflicts or coordination issues other than what are shown in the

Contract Plans and Special Provisions.

11. Question #11

Confirm what are working days vs. calendar days in Special Provision 00180.50(h).

a. Answer #11

00180.50 (h) defines the Contract end date as October 22, 2026 when all work shall be complete.

12. Question #12

Is it required to be pre-qualified through ODOT in all classes of work called out in the contract documents or does the inclusion of the word either indicate that being pre-qualified in one of the categories (Earthwork and Drainage OR Asphalt Paving OR Electrical) will suffice?

a. Answer #11

The contractor must be prequalified in at least one class of work.