This is a Purchase Description for the manufacture of Impulse Cartridge Cups for the Crane Army Ammunition Activity (CAAA). The contractor must produce 10 First Article Test (FAT) units and 28,215 production units of Impulse Cartridge Cups with a coined point, manufactured from aluminum alloy 6061-T6 per drawing 201719312 using coining tooling per drawing 201719314. The material must be cold-finished bar stock per ASTM B211, with dimensions applied prior to the coining operation. The manufactured parts require annealing at 760 degrees F (±10 degrees F) for 2-3 hours, followed by cooling at a rate of 50 degrees F per hour until the temperature drops below 500 degrees F.

Quality acceptance requires that a representative sample of the coined point cups be hydrostatically burst tested using the specified burst fixture (drawing 201719315) and achieve a burst pressure between 1,000 ± 200 PSI at a rate of 100-400 PSI/sec. All deliveries must include material certifications and certificates of conformance per CAAA Form 702-37. The delivery schedule requires FAT units within 6 weeks of contract award, with production quantities delivered in two tranches: 14,000 units at 11 weeks after FAT approval and 14,215 units at 22 weeks after FAT approval, with a final delivery date of December 30, 2026. All shipments must be sent to Crane Army Ammunition Activity, Building 148, Crane, Indiana 47522, with receiving hours Monday through Thursday, 0630-1530, and Friday deliveries only by prescheduled appointment. The contractor must achieve at least a conditional CMMC Level 2 Self Assessment at contract award.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Purchase Description

FAT QTY – 10 EA

Production QTY – 28,215 EA

Impulse Cartridge Cup, Coined Point per DWG 201719312 manufactured from Impulse Cartridge Cup, Blank Point DWG 201719312 using Coining Tooling per DWG 201719314

- Material: Aluminum Alloy 6061-T6, ASTM B211, Cold-finished Bar

- Dimensions apply prior to Coining Operation as specified in 201719312

- 201719314 Coining Tooling has been found to provide satisfactory coining feature in the cup.

- Annealing parameters: A. Anneal machined part to 760 degrees F +/- 10 F for 2-3 hours. B.

Cool part at a rate of 50 degrees F per hour until temp is below 500 degrees F

- The center of this feature is .012 x .002 prior to coining.

- PRIOR TO ACCEPTANCE OF COINED POINT, IMPULSE CARTRIDGE CUP (201716312),

- A REPRESENTATIVE SAMPLE SHALL BE HYDROSTATICALLY BURST TESTED AND

- OBTAIN A BURST PRESSURE IN THE RANGE OF 1,000 ± 200 PSI, ACHIEVED AT A

- RATE OF 100-400 PSI/SEC.

- A. 201719315 HYDROSTATIC BURST FIXTURE HAS BEEN FOUND TO PROVIDE A

- SATISFACTORY BURSTING OF COINED CUP.draw

- All deliveries must include material certs.

- RDD 30 DEC 2026

- Delivery schedule:

o FAT QTY 10 delivered 6 weeks after contract award.

o Production QTY completed NLT 22 weeks after FAT approval.

o Multiple deliveries requested.

▪ 14,000 delivered 11 weeks after FAT approval

▪ 14,215 delivered 22 weeks after FAT approval

• CAAA will accept earlier deliveries at no additional cost to the government.

• All deliveries require material certifications/ certificate of conformance IAW CAAA

Form 702-37.

• BOL / shipping information must contain applicable contract number and applicable PR document number.

Please ship all deliveries to:

Crane Army Ammunition Activity 300 Highway 361 Building 148 Crane, IN 47522

* Receiving hours are Monday through Thursday, 0630-1530.

* Friday deliveries are only accepted by prescheduled appointment, Please call 812-854-8177 or 812-854-3744 for appointments.

* Closed on all Federal Holidays.

CMMC Requirements and Implementation

Due to the phased in implementation of CMMC requirements, The contractor will be required to meet at least conditional CMMC Level 2 Self Assessment at contract award.

File details come from the government source that posted it. Updated .