PSS Mezzanine- 03Feb23.docx
DOCX document 21 KB Posted
- Attached to
- Storage Mezzanine Federal contract opportunity
- Solicitation number
- 2123403Y2163A85001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PSS Mezzanine- 16MAR23.docx | DOCX document | |
| Solicitation - 2123403Y2163A85001.docx | DOCX document | |
| Far Smart Matrix Acquisition.GOV (1).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRODUCT SPECIFICATION SHEET
Yard Storage Mezzanine
U.S. Coast Guard Yard Storage Mezzanine (requirements):
*Product Specification Sheet will be modified & corrected, once on-site visit is complete
1. Mezzanine shall have approximately the deck size of 45’ by 28’ ft. Approx 1,100 square feet at a minimum.
2. Mezzanine will be assembled by structural type hardware
3. Mezzanine shall have approximately at a minimum clear height of 9’
4. Mezzanine should have a minimum capacity of 150 lbs. per square feet
5. Mezzanine shall have (1) stairway that will meet OSHA standards with closed treads, 36” wide steps, handrails, and open risers.
6. Mezzanine shall have sufficient lighting brackets.
7. Mezzanine shall have a handrail enclosing open areas of mezzanine
8. Mezzanine shall have 4” tall kick plates enclosing open areas of mezzanine
9. Mezzanine shall have (1) 6’ double gate. Contractor may provide options for recommendations.
10. Mezzanine flooring shall have sufficient decking and thickness that will tolerate a 3000lb pallet load and allow a pallet jack to be moved around on it.
11. Mezzanine shall be coated with a protective coating application on all steel at a minimum. Contractor may provide options for recommendations.
12. Mezzanine shall be painted with a colored coating application for all standard galvanized components. Contractor may provide options for recommendations.
13. Mezzanine shall include a knee bracing.
14. Mezzanine must be designed to have 2,000 lbs. on a standard 4’ by 4’ ft pallet jack
15. Mezzanine shall have a minimum of a 1-year parts and labor warranty, to include the following: 1 calendar day response time via call or email for Mezzanine casualty during the warranty period and 3 calendar day delivery of replacements parts during the warranty period
16. Mezzanine shall be anchored to the concrete floor by an engineered approved method.
17. Contractor shall replace all parts necessary to perform scheduled maintenance within the 1-year warranty period
18. Mezzanine shall be built to comply with all federal, state, local, OSHA standards, and may comply with AISC regulations.
19. Contractor shall provide licensed structural engineer seal and compliance.
20. Contractor shall provide weight test and certificate to prove weight compliance before acceptance.
21. Contractor will provide a metal placard with weight test date and total weight that it was weight tested to. This will be affixed to the mezzanine.
22. Contractor shall provide all operation and maintenance manuals in digital (PDF) and paper formats before acceptance.
23. Contractor shall provide a certified design drawing in digital (PDF) and paper formats before acceptance.
24. Contractor shall provide parts list in digital (PDF) and paper formats.
25. Contractor shall provide a point of contact for platform manufacturer
26. Mezzanine shall be connector or assembled with structural bolts and mounting material.
27. All support columns shall be anchored to the concrete.
DELIVERY SCHEDULE
INSTALLATION OF MEZZANINE: Fabrication is estimated to be up to 17 weeks after awarded contract. Delivery and installation is estimated to take approx. 3 weeks once fabrication is completed. Mezzanine acceptance will not occur until after completion of delivery, installation, weight test, and final inspection, which will be the Contractors responsibility. Government will provide the test weights.
OPTIONAL ITEMS
Please provide a Details (bid if needed) on the following as an optional item if we choose to exercise an option:
· Provide all color options and price if there is a cost for different colors.
· If Manufacture recommends a different type of gate, provide pictures of the options and price points.