This is a Performance Requirements Summary (Quality Assurance Surveillance Plan) for compartment 3 seedlings/planting at Overflow National Wildlife Refuge planned for 2026. The document outlines requirements for providing and planting 44,500 bare root hardwood seedlings across approximately 102 acres of open fields using 10' x 10' spacing. The work must be performed between January 15, 2026, and March 1, 2026.
The contractor must comply with specific performance standards including: obtaining USFWS approval for work dates 48 hours in advance, maintaining 97% compliance with work schedules, following Arkansas Best Management Practices for Forestry, adhering to Arkansas Department of Agriculture Seedling Care and Planting Guidelines, ensuring proper PPE usage, and keeping equipment debris-free to prevent invasive species spread. Species selection can only vary up to 3% from the provided list, with any deviations requiring government representative approval. The Fish and Wildlife Service will conduct visual inspections to ensure compliance, with non-compliance resulting in negative performance ratings or requirement to redo work at contractor's expense.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Oxbone_locator_map.pdf | ||
| PWS_Compartment_3_Seedlings___Planting_(2026).doc | DOC document | |
| Sol_140FS325Q0009.pdf | ||
| Oxbone_aerial_map.pdf | ||
| Seedling_species_list_for_Oxbone_fields_on_Overflow_NWR_(2026_update).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Requirements Summary (Quality Assurance Surveillance Plan) Compartment 3, Seedlings/Planting, Overflow NWR 2026
| Desired Outcome (What do we want to accomplish as the end result of the contract?) |
| Task or Deliverable (What task must be accomplished to give us the desired result?) |
| Performance Standard (What should the standards for completeness, reiliability, accuracy, timeliness, quality and/or cost be?) |
| Acceptable Quality Level (AQL) (How much error/variation will we accept/allow from the standard?) |
| Surveillance Method (How will we determine that success has been achieved?) |
| Positive/Negative Incentive formeeting or not meeting the Performance Standards (What will be the best reward for good performance or retribution for poor performance?) |
| 1) Work completed by the end of the performance period. |
| Contractor must have work dates and a plan of work approved by the USFWS 48 hours prior to beginning work, preferably established during a face-to-face pre-work meeting. |
| Comply with work schedules 100% |
| 97% compliance (3% allowance due to uncontrollable circumstances, etc). Species of seedlings may not vary more than 3% for the attached species list and must be replaced with adequate species that are compatible with this site as determined by the Government Representative. Any other deveiation from the species list must be agreed upon by both the contractor and the governement representative (GR) prior to planting. |
| Visual inspection or review of time-sheets and work logs. |
| Non-compliance with work schedule will result in negative performance rating and/or request for new operator. |
| 2) Provide 44,500 bare root seedling and hand plant on approximately 102 acres of open fields on within comparmtment 3 on Overflow NWR. |
| Provide 44,500 (1-0) bare root hardwood seedlings (see attached species list) and hand plant on a 10 x 10’ spacing on Overflow NWR. |
Treatment area identified in blue on attached map.
The contractor will supply all material, equipment, and labor to perform the mechanical treatment.
Treatment date shall be between January 15, 2026 and March 1, 2026.
| A minimum of 95% of the area should be planted with species selected and location directed by Fish and Wildlife Service staff. |
| Visual inspection. |
| Non-compliance will result in work being re-done at contractor’s expense. |
| 3) Maintain land resources. |
| Protect soil integrity, minimize rutting. Any rutting considered “excessive” by Project Leader or Government Representative is unaccpetable. |
| Application must be in compliance with Arkansas Best Management Practices for Forestry. |
Seedlings should be cared for and planted according to the AR Dept. of Agriculture Seedling Care and Planting Guidelines.
100% compliance with BMPs.
Seedlings should be cared for and planted according to the AR Dept. of Agriculture Seedling Care and Planting Guidelines.
Visual inspection for BMP compliance. May request a compliance audit from Arkansas Forestry Commission.
Seedlings should be cared for and planted according to the AR Dept. of Agriculture Seedling Care and Planting Guidelines.
Non-compliance will result in negative performance rating.
| 4) Maintain safety of all workers and staff. |
| Equipment operators wear proper gear. |
| Equipment operators to wear appropriate PPE at all (100%) time. |
| 100 % compliance; zero violations of safety requirements. |
| Observance/inspection. |
| Immediately stop violator from work. Report to OSHA. May not be considered for future contracts. |
| 5) Prevent transport and introduction of invasive plant species. |
| All equipment must be clean, free of debris. |
| All equipment must be debris-free. |
| 5% deviation. |
| Visual inspection. |
| Non-compliance will result in negative performance rating and re-cleaning of equipment at contractor’s expense. |