Proposed LHII Evaluation Factors 04-08-2024.pdf

PDF 74 KB Posted

Attached to
FEMA LogHOUSE II - DRAFT Work Statement Federal contract opportunity
Solicitation number
70FB8023B00000006RFI
Issued by
Federal Emergency Management Agency

About this file

The provided document is a summary of the proposed evaluation procedures for the FEMA LogHOUSE II contract opportunity. FEMA plans to award a multiple-award IDIQ contract through a two-phase advisory down-select process, where non-cost evaluation factors will be weighted more heavily than price.

The key details are:

  • FEMA will utilize the tradeoff process to determine best value, and may award to other than the lowest priced offeror.
  • The proposed evaluation factors include corporate/team experience (Phase I), oral presentation, quality assurance plan, past performance, and price (Phase II).
  • FEMA reserves the right to award without discussions, but may conduct negotiations with the highest-rated offerors.
  • The related federal contract opportunity is a draft work statement for the FEMA LogHOUSE II requirement, which seeks services for the transition, maintenance, and deactivation of FEMA temporary housing units. FEMA plans to issue the solicitation in June 2024 and is seeking vendor input on the performance work statement and acquisition planning.

View the file

Other files for this federal contract opportunity

Other files attached to FEMA LogHOUSE II - DRAFT Work Statement, newest first.
File Type Posted
DRAFT LogHOUSE II Section C 04-08-2024.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LogHOUSE II Proposed Evaluation Procedures

FEMA will award a multiple award IDIQ contract to the offerors whose proposal presents the best value to the Government in accordance with FAR 12, using competitive source selection procedures provided at FAR 15.101. In making a best value determination(s) for award, FEMA will utilize FAR 15.101-1, Tradeoff Process. Non-cost evaluation factors will be weighted more important than price.

The Government reserves the right to make award to a higher priced offeror for a superior solution as set forth in the technical and past performance evaluation factors. As such, the Government may award to other than the lowest priced offeror, or other than the offeror with the highest technical rating. The proposed evaluation factors are:

STEP 1: Phase I

Factor One (1) Corporate/Team Experience

STEP 2: Advisory Down-Select

STEP 3: Phase II

Factor Two (2) Oral Presentation (Technical Approach) Factor Three (3) Quality Assurance Plan Factor Four (4) Past Performance Factor Five (5) Price

FEMA is planning to utilize a two-phase advisory down-select approach to evaluate all vendors. During Phase I, Factor 1 will be evaluated by the Technical Evaluation Team, and offerors will be advised as to whether FEMA considers them to be a viable competitor for this acquisition. While Phase I is advisory, all offerors must participate in Phase I to proceed to Phase II. During Phase II, FEMA will require offerors to orally present on such areas as scenario planning, response, and quality control procedures. FEMA will do a consensus evaluation immediately following each offeror’s oral presentation.

FEMA asserts the right to award without discussions. However, if discussions/negotiations are required, the Contracting Officer (CO) will conduct cost/price negotiations in accordance with FAR Part 15, with the highest rated offerors.

Final source selection will be made to the proposals that present the best value to the Government, price and other factors considered. The offerors must be determined responsible and otherwise eligible for contract award with no known organizational conflict of interests.

File details come from the government source that posted it. Updated .