About this file

This document is a Statement of Work (SOW) for Propane Services for the Defense Logistics Agency (DLA) Distribution Oklahoma City, Tinker AFB, Oklahoma 73145. The SOW covers a period of performance from 30 September 2024 through 30 September 2027 (12 months) and outlines the requirements for the vendor to supply, deliver, and maintain liquefied petroleum gas (LPG) cylinders and racks across 13 delivery locations at the Tinker AFB facility. The estimated yearly consumption is 45,000 - 50,000 gallons of propane. The vendor is responsible for filling empty cylinders, repairing or replacing defective cylinders, and ensuring proper markings and identification tags. Delivery is required on Mondays and Thursdays, with a 24-hour maximum response time for unscheduled refills. This SOW is associated with a federal contract opportunity (Solicitation Number SP3300-24-Q-5020) for Propane services, issued by the Defense Logistics Agency Distribution.

View the file

Other files for this federal contract opportunity

Other files attached to Propane, newest first.
File Type Posted
TAB 11 CSS SP330024Q5020.doc DOC document
SF30-16.pdf PDF
TAB 11 CSS SP330024Q5020.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK:

Propane Services for DLA Distribution Oklahoma City, Tinker AFB, Oklahoma 73145 Period of Performance: 30 September 2024 through 30 September 2027 (12 Months)

Type: UN1075, Liquefied Petroleum Gas, 2.1 Cannister Size: 3u – approximately 8 gallons Estimated Yearly consumption: 45,000 – 50,000 gallons.

Vendor will supply all cages; to include lockable storage racks and cylinders free of charge.

LPG Cylinders must be of accurate size to be secured in manufactures mount.

LPG Cylinders must contain operational fuel gauge.

Delivery date: Every Monday and Thursday. Holiday delivery will occur the day prior or the day after the holiday.

Vendor may be called to resupply LPG prior to the scheduled time; in these instances, a 24-hour maximum response time is required.

Services: Fill cylinders that are empty in rack locations, see below.

Repair/replace tanks that have bad O-rings, valves, or any other defects that may cause the leakage of Liquefied Petroleum Gas (LPG), or integrity of the cylinders.

Supply Markings to meet ANCI/OSHA Compliance.

Identification tags to be supplied by the vendor for inoperable cylinder(s).

Maintenance of LPG cylinders is the responsibility of vendor.

Used cylinders of LPG will be placed in supplied racks with the bottom of the tank facing outside.

Filled cylinders will be placed with valves to the outside.

Delivery Locations:

1. Building 10, Door 16 - 12 bottle rack + 9 bottles = 21 total

2. Building 11, Door - 0 bottle rack (borrow from 10) – 1 bottle = 1 total

3. Building 18, Door 17 – 12 bottle rack + 18 bottles = 30 total

4. Building 412, Door 10 – 8 bottle rack + 5 bottles = 13 total

5. Building 416, Door 19 – 16 bottle rack + 5 bottles = 21 total

6. Building 510, Door 8 – 24 bottle rack + 6 bottles = 30 total

7. Building 506, Door 47 – 48 bottle rack + 29 bottles = 77 total

8. Building 812 (Outside of Locked Gate) – 12 bottle rack + 4 bottle = 16 total

9. Building 1022 (Outside of Locked Gate) - 4 bottle rack + 1 bottle = 5 total

10. Building 3001 (Corp), by the fence of Bldg. 3117 – 12 bottle rack + 6 bottles = 18 total

11. Building 9001, Door – 4 bottle rack + 1 bottle = 5 total

12. Building 1, Door 64 - 9 bottle rack + 5 bottles = 14 total

13. Building 1130 (72nd/PCSI) – West Side - 6 Bottle Rack = 6 total

Total = 167 bottles in racks, 90 bottles in forklifts located in various buildings = 257

In case of future expanse, the contractor will provide additional racks and cylinders to accommodate the mission. There will be no down time to forklifts during transition period. Vehicles that are currently operating with LPG will have their tanks exchanged by the new vendor, prior to disposition of their old tanks.

The Contractor will be required to supply these racks, tanks, cylinders and bottles. Tanks and cylinders should be made of aluminum.

File details come from the government source that posted it. Updated .