BLACK HILLS NATIONAL FOREST

HELITACK HANGAR BI-FOLD DOOR REPLACEMENT

010150 – 1

GENERAL REQUIREMENTS

SECTION 010150

PART 1 – SUMMARY OF WORK

1.1 DESCRIPTION

A. Work for this project requires the Contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery and all necessary valid licenses and permits for the work summarized as follows:

1. Removal of existing bi-fold hangar door

2. Replacement of same-size bi-fold hangar door, complete with all electric work and installation to make full and operable installation.

B. This project is at the Black Hills National Forest, Interagency Helitack Base located at 12202 Aviation Way, Custer, SD 57730. The site is located at the Custer Airport. From Custer, proceed south on Highway 89 approximately 2.5 miles, then turn right (west) onto Aviation Way

C. Building Information: The metal Helitack hangar building was constructed in 1980. It is approximately 50’ x 60’ with 16’ walls. Roof pitch is 1:12.

1. The Forest does have design documentation for the original construction of the building structure.

2. Interior improvements, including electric work, have been performed after original construction. No as-built drawings or documentation of these modifications are available.

1.2 QUALIFICATONS OF CONTRACTORS

A. All work shall be performed by contractors with qualified craftsmen with experience with manufacture and installation of bi-fold aircraft hangar doors.

1.3 USE OF PREMISES

A. Use of Site: Confine work activity to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Full Government Occupancy: Government will occupy site and buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the work so as not to interfere with Government's day-to-day operations.

C. Adjacent Occupancies: Interagency Helitack Base is located at the Custer Airport.

Operations at the Airport and adjacent facilities, including Civil Air Patrol operations, will continue. Perform work so as not to interfere with day-to-day

010150 – 2 operations at Airport and associated facilities.

D. Emergency Operations: Helitack Base and nearby Civil Air Patrol and other activities at Custer Airport may be involved in emergency operations, including but not limited to wildland fire response, evacuations, and search and rescue. Such activities shall take precedence over Contractor’s Work. Contractor shall not interfere with such emergency activities.

1. Disruptions to Contractor’s Work and Schedule resulting from Emergency

Operations at the Project Site will be evaluated by the Contracting Officer on a case-by-case basis for fair and equitable contract adjustment, in accordance with applicable Contract FAR Clauses.

E. Driveways and Entrances: Keep roads, parking areas, paths, walkways, aprons, and entrances clear and available to Government, Government's employees, and emergency vehicles at all times. Park Contractor vehicles and trailers in areas designated by Contracting Officer. Store and stage materials, supplies, and disposal containers as directed by Contracting Officer.

1.3 WORK RESTRICTIONS

A. Smoking is not permitted within the buildings or within 25 feet of entrances, aircraft, fuel locations, propane storage areas, operable windows, or outdoor air intakes.

B. The Contractor shall repair existing Forest Service roads, parking areas, concrete aprons, floors, and improvements disturbed by work activity. Repair includes any work needed to return the improvements to their existing condition before work activity began.

1.4 CONTRACTOR’S RESPONSIBILITIES

A. Confine storage of materials to areas as approved by the CO.

B. Provide adequate signing and barricades and take necessary safety measures to protect government employees, contractors, and public during all construction operations. Minimize disturbance of all undisturbed areas.

1.5 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering supplies and materials.

PART 2 – DEFINITION OF ITEMS AND PAYMENT

2.1 DESCRIPTION

A. This section explains what is and what is not included in each pay item; the limits or cut-off points where one item ends and another begins; and basis of payment for work

010150 – 3 items listed in the Schedule of Items.

B. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, and as shown on the drawings.

2.2 SCHEDULE OF ITEMS

A. Schedule of Items: The project Schedule of Items includes several sections to organize the work into Base Items and Optional Items.

1. Provide pricing for all items listed in the Schedule of Items.

2. Contract award will be made for all Base Items.

3. Option Items are identified below as possible items that may be necessary based on conditions identified during demolition of existing improvements and inspection of presently concealed features.

B. Base Items (BI):

1. Base Item No. 1- Mobilization, Demobilization, and Insurance.

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price shown in the Schedule of Items shall include all materials, equipment, labor, and incidentals required to perform all operations necessary for the movement of personnel, equipment, supplies and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.

2. Base Item No. 2- Demolition includes all materials, equipment, supplies labor, and incidentals required to disconnect, remove, and recycle and/or dispose of existing hangar door and all associated appurtenances and accessories. Perform all operations necessary for completion of work as specified and shown in the construction documents.

3. Base Item No. 3- Bi-Fold Hangar Door Replacement includes all materials, equipment, supplies labor, and incidentals required to provide, install, connect, adjust, new bi-fold hangar door with integral personnel door and all mountings, controls, counterbalances, safety features, insulations and finishes and all associated appurtenances and

010150 – 4 accessories and electric wiring and connections necessary for fully operable installation as specified and shown in the construction documents.

A. Option Items (OI):

1. Option Item No. 1- Repairs and Modifications of Existing Door Frame for new

Bi-Fold Hangar Door.

a. This is an Option Item. Description, measurement means and quantity, if any, shall be determined through mutual agreement by Government and Contractor in accordance with FAR clauses.

2. Option Item No. 2- Electrical Upgrades

a. This is an Option Item. Connection of new bi-fold door to existing power at existing electric panel is included in Base Item No. 3. This Option Item No. 2, if necessary, is for electric system upgrades if such are deemed necessary by Contractor inspection and evaluation by independent licensed electrician.

b. Description, measurement means and quantity, if any, shall be determined through mutual agreement by Government and Contractor in accordance with FAR clauses.

PART 3 – ACCIDENT PREVENTION

3.1 DESCRIPTION

A. This section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.

3.2 SUBMITTALS

A. Accident Prevention Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. Notice to Proceed will not be made until the plan is received. As a minimum the plan shall include:

1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.

2. Name and contact information of supervisor responsible to carry out the plan.

3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.

010150 – 5

4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.

B. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.

3.3 QUALITY ASSURANCE

A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions: In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees: Ensure employees are physically qualified to perform assigned duties in a safe manner.

3.4 ACCIDENT REPORTING

A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 calendar days of a reportable accident, fill out and forward to the CO a CA-1 form, which may be obtained from CO.

B. All Other Accidents: Report all accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.

3.5 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the type of work at the site.

3.6 EMERGENCY INSTRUCTIONS

A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

3.7 ESCAPE ROUTES

A. Provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101). No corridor, aisle, stairway, door or exit shall be obstructed or used in a manner that interferes with escape routes.

3.8 PROTECTIVE EQUIPMENT

A. Personal Protective Equipment (PPE) shall meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

010150 – 6

B. Inspect personal protective equipment daily and maintain in a serviceable condition.

Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

C. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.9 SAFETY MEETINGS

A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.

3.10 TRAINING

A. First Aid: Provide adequate training to ensure prompt and efficient first aid. Provide first aid supplies to use at the site.

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

PART 4 – SUBMITTAL PROCEDURES

4.1 PROCEDURES

A. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 10 working days for initial review of each submittal.

Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 10 working days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

B. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space approximately 2 by 3 inches on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

010150 – 7

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. Other necessary identification.

C. Deviations: Highlight, encircle, or otherwise identify deviations from the

Contract Documents on submittals.

D. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

E. Use for Construction: Use only final submittals with mark indicating action taken by

CO in connection with construction.

F. Review each submittal and check for compliance with the Contract Documents.

Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

G. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

4.2 SUBMITTALS

A. General: Prepare and submit Submittals required by individual Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Contractor's Construction Schedule: Provide a construction schedule.

C. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. Mark each copy of each submittal to show which products and options are applicable.

4.3 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified. RFIs submitted by entities other than the Contractor

010150 – 8 shall not be accepted.

1. Coordinate and submit RFIs in a prompt manner to avoid delays in

Contractor’s work or work of subcontractors.

2. Include a detailed, legible description of item needing information or interpretation and the following:

a. Project name and number

b. Date

c. Contractor Name and signature

d. RFI number, numbered sequentially

e. RFI subject

f. Specification Section, Drawing number, and detail references, as appropriate.

g. Field dimensions and conditions, as appropriate.

h. Contractor’s suggested resolution. If Contractor’s solution(s) affects the Contract Time or Contract Sum, Contractor shall state impact in the

RFI.

i. Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

3. CO’s Action: CO will review each RFI, determine action required, and respond.

Allow seven (7) working days for CO's response for each RFI. RFIs received by CO after 1:00 p.m. will be considered as received the following working day.

a. The following RFIs will be returned without action:

1) Requests for approval of submittals.

2) Requests for approval of substitutions.

3) Requests for coordination information already indicated in the

Contract.

4) Documents.

5) Requests for adjustments in the Contract Time or the Contract Sum.

6) Requests for interpretation of CO's actions on submittals.

7) Incomplete RFIs or inaccurately prepared RFIs.

b. CO's action may include a request for additional information, in which case CO's time for response will date from time of receipt of additional information.

c. CO's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Contracting Section "Contract Modification Procedures."

1) If Contractor believes the RFI response warrants change in the

Contract Time or the Contract Sum, notify CO in writing within 10 days of receipt of the RFI response.

010150 – 9

PART 5– TEMPORARY FACILITIES AND CONTROLS

5.1 DESCRIPTION

A. This section consists of requirements for temporary facilities and controls, including utilities, support facilities, and security and protection facilities.

5.2 UTILITIES

A. Sanitary Facilities: Use of Government sanitary facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.

B. Electric Power and Lighting Service: Use of Government's existing electric power and lighting service will be permitted without metering and without payment of use charges, as long as equipment is maintained in a condition acceptable to CO.

C. Telephone Service: The Contractor is responsible for providing telephone service deemed necessary for the duration of the construction.

5.3 DELIVERY, STORAGE, AND HANDLING

A. Contractor shall be responsible for providing secure storage facilities for materials, equipment and supplies. Confine storage to areas approved by the CO.. Forest Service will not be responsible for security of Contractor equipment, materials, supplies or other items at the work site.

B. Deliver materials and supplies to site, marked with Contractor name and project identifiers.

C. Locate temporary construction and support facilities for easy access and to avoid conflict with existing Government operations and operations at Airport and nearby facilities.

5.4 CONSTRUCTION WASTE DISPOSAL FACILITIES

A. Provide waste-collection containers in sizes adequate to handle waste from work activity. Waste materials and items from demolition activities shall be placed in containers or otherwise secured in manner to prevent blowing or becoming airborne or otherwise creating hazards to operations at Government facilities and adjacent operations.

B. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.

C. Do not burn waste materials.

010150 – 10

D. Transport waste materials off Government property and legally recycle or dispose of them. Recycling is the preferred method of waste management.

5.5 SECURITY AND PROTECTION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Avoid use of substances that contribute to indoor air quality deterioration. Provide Safety Data Sheets for all substances upon request of CO.

C. Fire Protection:

1. Store combustible materials in containers in fire-safe locations.

2. Maintain unobstructed access to fire extinguishers, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

3. Prohibit smoking within government facilities and within 25 feet of existing building.

D. The contractor shall install and maintain suitable barriers and warning signs to ensure the protection of the public, employees and facilities. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry to the work area. Material for barriers and signs may be new or used, but shall be suitable for intended purpose.

Barriers shall be structurally adequate and neat in appearance.

PART 6 – EXECUTION REQUIREMENTS

6.1 DESCRIPTION

A. This section consists of general procedural requirements governing execution of the Work including, but not limited to, the following:

1. Schedule.

2. Examination.

3. Execution.

4. Progress cleaning.

5. Correction of the Work.

6.2 SCHEDULE

A. Occupied Work Area: Work will be performed at an occupied and functioning

Government facility which is on an active airfield (Custer County Airport).

B. Emergency Work Area:

010150 – 11

1. The Helitack Base is subject to emergency operations in response to wildland firefighting activities. Contractor’s work shall not interfere with emergency operations that may occur at the Helitack Base.

2. Custer Airport and Civil Air Patrol may be involved in emergency operations.

Contractor’s work shall not interfere with emergency operations at these facilities.

C. Schedule: Contractor shall submit Proposed Schedule to CO.

D. Completion: Contractor shall notify CO upon completion of work. Upon such notification, CO shall within 2 business days perform inspection of work. Deficiencies identified by inspection shall be corrected by Contractor, reinspected, and when satisfactory, will be accepted by Government.

6.3 EXAMINATION

A. Existing Conditions: Before beginning work, investigate and verify the existing conditions affecting the Work.

B. Acceptance of Conditions: Examine areas, and conditions, with Contractor.

Record observations.

1. Verify compatibility with and suitability of substrates, including compatibility with existing materials and finishes.

2. Notify Contracting Officer of unsatisfactory conditions immediately upon discovery.

3. Proceed with Work only after unsatisfactory conditions have been addressed.

Proceeding with the Work indicates acceptance of surfaces and conditions.

6.4 PREPARATION

A. Field Measurements: Take field measurements as required to fit the Work properly.

Verify space requirements and dimensions prior to ordering materials.

B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

C. Verification: Before proceeding with Work, verify information shown on project

Documents in relation to actual conditions. If discrepancies are discovered, notify CO promptly.

6.5 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

010150 – 12

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of maintenance operations.

B. Comply with manufacturer’s written instructions and recommendations for installation and adjustments of products.

C. Execute work at time and under conditions that will ensure the best possible results.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy. Allow for building movement, including thermal expansion and contraction.

E. Anchors, Fasteners, and Supports: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.

1. Where mounting heights are not indicated, mount components at heights directed by CO.

2. Allow for building movement, including thermal expansion and contraction and response to loads induced by installed materials and wind loads.

F. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints

G. Do not use products, cleaners, and installation materials that are considered hazardous.

6.6 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.

1. Remove combustible waste from site daily.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain Project site free of waste materials and debris. Prevent materials and wastes from becoming airborne or otherwise affecting operations at airfield and associated facilities.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness

010150 – 13 necessary for proper execution of the Work.

D. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

6.7 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide final protection and maintain conditions that ensure Work is clean and without damage or deterioration at time of Acceptance by Government.

B. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use-cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

C. During handling and installation, clean and protect construction in progress and ad-joining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration.

D. Limiting Exposures: Supervise construction operations to assure that no part of the construction completed or in progress is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

6.8 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

B. Restore permanent facilities used during construction to their specified condition.

C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

D. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

PART 7 – OPERATIONS AND MAINTENANCE MANUALS

7.1 SUBMITTALS

A. Submit three opies of Operations and Maintenance data in final form withing 5 working days of completion of installation.

010150 – 14

B. Operation and Maintenance data shall include:

1. Operation Data: Include instructions, equipment descriptions, equipment identification with serial number of each component, list of parts and diagrams of parts, for routine and emergency operations

2. Maintenance Data: Include manufacturer's information, product(s) name and model number(s), list of spare parts, nomenclature and number of replacement parts, maintenance procedures, maintenance and service schedules for preventive and routine maintenance, and procedures for routine cleaning.

3. Adjustments: Procedures and parameters to adjust alignment, checking adjustments, noise and vibration adjustments.

4. Troubleshooting diagnostic instructions and test and inspection procedures.

5. Repairs: Diagnosis instructions; repair instructions; disassembly, component removal, repair and replacement; and reassembly instructions.

6. Instructions for identifying parts and components.

7. Review of spare parts needed for operation and maintenance.

8. Copies of warranties and lists of circumstances and conditions that would affect validity of warranties

9. Source Information: For each product, list name, address, and telephone number of Installer or supplier.

C. Training

1. Provide instruction in operation and maintenance of door, controls, and appurtenances and accessories.

2. Coordinate training with Government operations. Adjust schedule as required to minimize disruption of operations and to ensure availability of key Government personnel.

3. Training shall include routine operations, emergency operations, maintenance, and adjustments and inspection protocols and troubleshooting protocols.

D. 1.

PART 8 – CLOSEOUT PROCEDURES

8.1 DESCRIPTION

A. This section consists of administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Inspection procedures.

2. Project Record Documents.

3. Final cleaning.

010150 – 15

8.2 SUBSTANTIAL COMPLETION

A. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for

Final Completion.

8.3 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.

B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

8.4 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do no use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

010150 – 16

1. Clean Project site and areas disturbed by construction activities of rubbish, waste material, litter, and other foreign substances.

2. Remove tools, construction equipment, machinery, and surplus material from Project site.

3. Clean exposed hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Restore reflective surfaces to their original condition.

4. Remove debris and surface dust from work area and adjacent areas affected by work.

D. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.

PART 9 – QUALITY REQUIREMENTS

9.1 DESCRIPTION

A. This section includes administrative and procedural requirements for quality assurance and quality control.

B. The Contractor is responsible for compliance with the Contract Document requirements, and quality control procedures that facilitate compliance with Contract Document requirements.

9.2 CONFLICTING REQUIREMENTS

A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to CO for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum with reasonable limits. The Contractor is responsible for verifying measurements and quantities prior to starting work. Refer uncertainties to CO for a decision before proceeding.

9.3 QUALITY CONTROL

A. General: The quality of all work shall be the responsibility of the Contractor.

B. Inspect all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable

010150 – 17 specifications and drawings. Failure to inspect work often enough does not relieve Contractor of responsibility of redoing work to achieve an acceptable level of quality of work being performed.

B. Reinspecting: Regardless of whether original inspections were Contractor's responsibility, The Contractor is responsible for notifying the CO for reinspection of work that failed to comply with requirements established by the Contract Documents.

C. Enforcement: The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the CO.

9.4 REPAIR AND PROTECTION

A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

B. Restore patched areas and extend restoration into adjoining areas in a manner that eliminates evidence of patching.

END OF SECTION 010150

024119 - 1

SELECTIVE DEMOLITION

SECTION 024119

SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

1.2 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.3 INFORMATIONAL SUBMITTALS

A. Inspection Survey: Submit survey of condition of building components that may be affected by this work. Include Pre-demolition photographs or video.

B. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property to ensure building remains weather-tight and secure. Indicate proposed locations and construction of barriers.

C. Schedule of selective demolition activities with starting and ending dates for each activity.

1.4 FIELD CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area.

Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

C. Notify Contracting Officer of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

024119 - 2

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. Hazardous materials will be removed by Owner before start of the Work.

2. If suspected hazardous materials are encountered, do not disturb; immediately notify

Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Storage or sale of removed items or materials on-site is not permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain electric services to remainder of facility during selective demolition operations.

2. Maintain fire-protection facilities in service during selective demolition operations.

3. Coordinate all electric power disruptions with Contracting Officer.

G. Arrange selective demolition schedule so as not to interfere with Owner's operations.

1.5 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSP A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

024119 - 3

B. Perform an engineering survey of condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective building demolition operations.

C. Inventory and record the condition of items to be removed and salvaged.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

3.3 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

C. Remove temporary barricades and protections where hazards no longer exist.

3.4 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new installation and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

4. Maintain fire watch during and for at least two (2) hours after flame-cutting operations.

5. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

6. Dispose of demolished items and materials promptly. Demolished items and wastes shall be promptly containerized in manner to prevent materials from becoming airborne and spreading by wind.

024119 - 4

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, adjacent aircraft and airport operations, and other adjacent occupied and used facilities.

C. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition.

3.5 CLEANING

A. Remove demolition waste materials from Project site and recycle or dispose of them according to Section 010150.

1. Do not allow demolished materials to accumulate on-site.

2. Do not allow demolished materials to become airborne and spread across project site, or onto other parts of Airport, or otherwise interfere with operations of Government and adjacent facilities.

3. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn demolished materials.

C. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 024119

BLACK HILLS NATIONAL FOREST 083613 - 1

HELITACK HANGAR BI-FOLD DOOR REPLACEMENT SECTIONAL DOORS

SECTION 083613

SECTIONAL DOORS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes insulated bi-fold hangar doors with integral personnel door, and all associated parts and accessories.

1.2 SUBMITTALS

A. As specified in “Submittal Procedures” in Division 1 Section “General Requirements.”

1. Product Data: For each type and size of sectional door and accessory include:

a. Details of construction and fabrication.

b. Material descriptions, dimensions of individual components, profile door sections, and finishes.

c. Rated capacities, operating characteristics, electrical characteristics, and furnished accessories.

d. Storage and handling requirements and recommendations.

2. Shop drawings: Include plans, elevations, sections, details of framing members, anchoring methods, required clearances, hardware, accessories, and details of installation.

Verify openings by field measurement before fabrication.

3. Selection Samples: For each finish product specified, provide color sample chart representing manufacturer’s full range of available colors and patterns.

4. Manufacturer’s Certificates: Certify products meet or exceed specified requirements.

5. Operation and Maintenance Data: Submit Operations and Maintenance Manual. Include:

a. Directions for operations.

b. Lubrication requirements and frequency.

c. Directions for periodic adjustments required.

6. Sample warranty.

1.3 QUALITY ASSURANCE

A. Manufacturer Qualifications: Company specializing in performing Work of this section with a minimum of five years’ experience in the fabrication and installation of aircraft storage hangar doors.

B. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer for both installation and maintenance of units required for this Project.

C. Source Limitations: Provide each type of product from a single manufacturing source to ensure uniformity.

BLACK HILLS NATIONAL FOREST 083613 - 2

1.4 DELIVERY, STORAGE, AND HANDLING

A. Store products in manufacturer’s unopened packaging until ready for installation.

B. Protect materials from damage due to weather, excessive temperature, and exposure to moisture.

1.5 PROJECT CONDITONS

A. Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer’s absolute limits.

1.6 WARRANTY

A. Manufacturer’s limited door and operator system, except the counterbalance spring and finish, to be free from defects in materials and workmanship for 3 years or 20,000 cycles, whichever occurs first.

B. Manufacturer’s limited door warranty for 2 years for all parts and components.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Basis of Design: Schweiss Hangar Door, Bi-Fold Door with Lift Straps and with motor drive mounted at bottom of door, or equal. Schweiss Doors, 72121 470th Street, Hector, MN; 55342;

800-746-8273; 507-426-8273; https://www.bifold.com

B. Substitutions: Approved equal meeting requirements of specifications, as approved by Contracting Officer.

2.2 PERFORMANCE REQUIREMENTS

A. General Performance: Bi-fold hangar door shall comply with performance requirements specified without failure due to defective manufacture, fabrication, installation, or other defects in construction and without requiring temporary installation of reinforcing components.

B. Single-Source Responsibility: Provide door, tracks, operators, motors, and accessories, from one manufacturer for each type of door. Provide secondary components from source acceptable to manufacture of primary components.

C. Structural Performance, Exterior Doors: Capable of withstanding the design wind loads.

1. Design Wind Load: Design door assembly to withstand design wind speed of 115 mph and wind/suction load of 25 psf (1,197 Pa) without damage to door or assembly components in conformance with ASTM E330.

https://www.bifold.com/

BLACK HILLS NATIONAL FOREST 083613 - 3

2. Operation Cycles: Door assembly, including operator, to operate for not less than 20,000 cycles. One operation cycle is complete when a door is opened from the closed position to the fully open position and returned to the closed position.

3. Deflection Limits: Design bi-fold doors to withstand design wind loads without evidencing permanent deformation or disengagement of door components.

a. Deflection of door sections in horizontal position (open) shall not exceed 1/120 of the door width.

b. Deflection of horizontal track assembly shall not exceed 1/240 of the door height.

4. Operability under Wind Load: Design overhead doors to remain operable under design wind load, acting inward and outward.

D. Products Requiring Electrical Connection: Listed and classified by Underwriters Laboratories, Inc. acceptable Contracting Officer and meeting requirements of National Electric Code and NFPA 409 “Standard for Aircraft Hangars”.

2.3 DOOR SECTIONS

A. Steel Bi-Fold Door: Bi-Fold door formed with hinged sections, steel.

B. Exterior Section Faces and Frames: Zinc-coated (galvanized), cold-rolled, commercial steel (CS) sheet, complying with ASTM A 653/A 653M, with indicated G60 zinc coating and thickness. Section Thickness: 2 inches.

1. Exterior-Face, Steel Sheet Thickness: Min. 0.015-inch-nominal coated thickness.

a. Surface: Flat.

b. Surface: Manufacturer's standard, paneled.

c. Exterior surface shall be finished with baked enamel or powder-coat finish consisting of prime coat and thermosetting topcoat with color and gloss as selected by CO from manufacturer's full range..

C. Reinforce bottom section with a continuous channel or galvanized steel angles, or other reinforcement as designed by manufacturer and conforming to bottom-section profile

D. Reinforce sections with continuous horizontal and diagonal reinforcement, as required to stiffen door and for wind loading. Provide galvanized-steel bars, struts, trusses, or strip steel, formed to depth and bolted or welded in place and as recommended and designed by manufacturer.

E. Provide reinforcement for hardware attachment.

F. Foamed-in-Place Thermal Insulation: Insulate interior of steel sections with door manufacturer's standard CFC-free polyurethane insulation, foamed in place to completely fill interior of section and pressure bonded to face sheets to prevent delamination under wind load, and with maximum flame-spread and smoke-developed indexes of 75 and 450, respectively, according to ASTM E 84. Enclose insulation completely within steel sections and the interior facing material, with no exposed insulation.

BLACK HILLS NATIONAL FOREST 083613 - 4

1. Insulation: Foamed in place, R-20.

2. Other type of thermal insulation, completely enclosed within steel sections of door, with R-Value 20, as recommended by manufacturer and with Contracting Officer approval.

G. Interior Facing Material: Zinc-coated (galvanized), commercial steel sheet, with a nominal coated thickness of manufacturer's recommended dimension to comply with performance requirements.

1. Interior facing materials shall be finished with baked enamel or powder-coat finish to match exterior face and consisting of prime coat and thermosetting topcoat with color and gloss as selected by CO from manufacturer's full range.

H. Fabricate sections so finished door assembly is rigid and aligned, with tight hairline joints and free of warp, twist, and deformation.

2.4 TRACKS AND SUPPORTS

A. Track and Supports: Manufacturer's standard, galvanized-steel track system of configuration indicated, sized for door size and weight, designed for lift type indicated and clearances measured at existing structure. Provide complete system including brackets, bracing, and reinforcement to ensure rigid support of framing, supports and accessories required door type, size, weight, and loading.

1. Evaluate existing structure to determine structural adequacy to support door and associated members. Notify Contracting Officer immediately of deficiencies and do not proceed with installation until deficiencies are remedied.

2.5 WEATHERSEALS

1. Replaceable, adjustable, continuous, compressible weather-stripping seal of flexible rubber, EPDM, vinyl, or neoprene fitted to bottom and top of sectional.

2. Replaceable, adjustable, interior weatherstripping mounted to door frame e as recommended by of flexible rubber, EPDM, vinyl, or neoprene as recommended by manufacturer.

3. Provide and install lintel weatherseal as recommended by manufacturer.

Provide and install bottom weatherseal placement as recommended by manufacturer…