PROJECT SCHEDULE
Project: Parking Garage Maintenance Repairs to Infill of Cracks on Top Elevation Concrete Slab U.S. Embassy - Viantiane, Lao PDR
Item Description By Duration (Days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 ## ## ## ## ## ## 1 Ariba request submittal FM 1 1
1.1 Drawings
1.2 Statement of Work
1.3 Specifications
1.4 Independent Government Cost Estimate (IGCE)
1.5 Recommended Contractor(s)
1.6 JOFOC (if any)
2 Solicitation Package Preparation GSO/PROC 5 2
3 Solicitation (Bid Announcement) GSO/PROC 10 3 FedbizOpps Embassy Homepage
4 Bid conference (Pre-Bid Site Survey) FM, GSO/Proc, Bidder(s) 1 4
5 Bid Submittal (Bid Due) Bidder (s) 15
5.1 DBA Insurance 5
5.2 Bank Guarantee
5.3 Construction Management Organization Chart
5.4 List of Materials (complete the given form)
5.5 Product Data Sheets
5.6 Initial Project Execution
6 Contract Award GSO/PROC, FMC 5 6
7 Security Clearance FM, RSO, Contractor 20 7
7.1 List of Workers (without Embassy Clearance)
7.2 Security Clearance Form
7.3 Finger printing
7.4 Interview
8 Limited Notice to Proceed (LNTP) CO 1 8
8.1 Project Schedule to COR Contractor 5 8.1
8.2 On Site Survey COR, Contractor 2 8.2
8.3 Pre-Construction Submittal Package Contractor 5 8.3
8.4 Materials Ordering & Delivery Contractor 20 8.4
9 Administrative Notice FM, MGT 1 9
10 Notice to Proceed (NTP) CO 1 10
11 Construction Phase COR, Contractor
11.1 Site Mobilization Area Preparation 5 11.1
11.2 Surface and Crack Preparation 5 11.2
11.3 Crack Repairs 15 11.3
11.4 Application of Traffic Coating 5 11.4
12 Substantial Completion COR, Contractor 1 12
13 Completion cable FM 1 13
14 Correction work COR, Contractor 5 14
15 As-built, Warranties COR, Contractor 10 15
16 Project Acceptance / Close-out COR 1 16
Note:
Administrative Work
Actual Construction. The parking garage's upper floor will be closed.
W20W9 W15 W16 W17 W18 W19 Month 2 Month 3 Month 4 Month 5 Month 6
Schedule
W1 W2 W3 W4 W5 W6 W7 W8 W10 W11 W12 W13 W14 W21 Month 1