Project_Manual_4250-01 (Sealed 05-27-26).pdf
PDF 12 MB Posted
- Solicitation number
- CB-2026-0048
- Issued by
- Harris County, Texas
About this file
This is a Project Manual for the City of Houston's on-call services solicitation for wastewater collection system rehabilitation and renewal. The project encompasses rehabilitation and replacement of sanitary sewer system components, including point repairs, sewer replacement, service lateral repairs, sliplining, pipe bursting, slurry boring, and service reconnections. Additional work includes cleaning and televising sanitary sewers, installation and rehabilitation of manholes, and pavement restoration. The manual establishes the framework for qualified bidders to submit proposals for these comprehensive wastewater infrastructure services on an as-needed, on-call basis rather than as a single defined project with fixed quantities.
The manual provides the technical specifications, requirements, and evaluation criteria necessary for bidders to prepare competitive proposals. It establishes the standards for contract performance, including work quality, safety requirements, scheduling, and compliance with City of Houston standards and applicable state and federal regulations. The document serves as the primary reference for all potential contractors regarding scope of work definitions, technical requirements, and contractual obligations. Interested bidders should review this manual thoroughly to understand all project requirements and submission procedures for the on-call services contract.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Houston Houston Public Works
Houston Water
PROJECT MANUAL
On-Call Services for Wastewater Collection System Rehabilitation and Renewal
Project Location: Within City Limits Project No.: WBS No. R-000266-0415-4, File No. 4250-01
VOLUME NO. 1 OF 1
Divisions 00 through 03
May 2026
City of Houston Wastewater Operations 4545 Groveway Drive Houston, Texas 77087
5/27/2026
TABLE OF CONTENTS
00010-1 05-27-2026
Document 00010
TABLE OF CONTENTS
NOTE: Capitalized Specification Sections for Division 01 are included in https://www.houstonpermittingcenter.org/media/3776/download?inline and Division 02-16 are included in https://www.houstonpermittingcenter.org/media/6386/download , and are incorporated in Project Manuals by reference as if copied verbatim. Documents listed "for filing" are to be provided by Bidder and are not included in this Project Manual unless indicated for example only. The Document numbers and titles hold places for actual documents to be submitted by Contractor during Bid, post-bid, or construction phase of the Project. Specification Sections marked with an asterisk (*) are amended by a supplemental specification, printed on blue paper and placed in front of the Specification it amends. Documents in the 00200, 00300 and 00400 series of Division 00, except for Document 00410B, �Bid Form, Part B,� are not part of the Contract.
Doc. No. Document Title Doc. Date
INTRODUCTORY INFORMATION
00010 Table of Contents ...................................................................... 05-27-2026 00015 List of Drawings ......................................................................... 02-01-2004
CONTRACTING REQUIREMENTS
AGREEMENT
00520WO Work Order Agreement .............................................................. 05-27-2026 00570 Contractor�s Revised MWSBE Participation Plan ...................... 03-16-2026 00571 Record of Post-Award Good Faith Efforts .................................. 03-16-2026 00572 Contractor�s Request for Plan Deviation .................................... 03-16-2026
BONDS AND CERTIFICATES
00600 List of Proposed Subcontractors and Suppliers ......................... 07-01-2013 00610 Performance Bond ..................................................................... 07-30-2020 00611 Statutory Payment Bond ............................................................ 07-30-2020 00612 One-year Maintenance Bond ..................................................... 05-17-2005 00613 One-year Surface Correction Bond ............................................ 05-17-2005
GENERAL CONDITIONS
00700 General Conditions .................................................................... 02-27-2026
SUPPLEMENTARY CONDITIONS
00803 Work Order Supplementary Conditions ..................................... 05-27-2026 00808 Requirements for the City of Houston Program for Minority, Women and Small
Business Enterprises (MWSBE), and Persons with Disabilities Business Enterprises (PDBE).................................................................... 03-16-2026
00820 Wage Scale and Payroll for Engineering Construction .............. 02-01-2026
ADDENDA AND MODIFICATIONS
On-Call Services for Wastewater Collection System Rehab Project No.: WBS No. R-000266-0415-4, File No. 4250-01
Doc. No. Document Title Doc. Date
00010-2 05-27-2026
00943 Monthly Subcontractor Payment Reporting Form ...................... 04-07-2026 00946 Payment Notification � Explanation of Withholding ......................... 02-27-2026
SPECIFICATIONS
Division 01 through 03 Specifications reference the latest editions of the Standard Specifications that are in effect as of the date of receipt of bids, unless otherwise noted.
Supplemental Specifications include Doc Date for reference.
DIVISION 1 - GENERAL REQUIREMENTS
01110 Summary of Work 01145S Use of Premises ........................................................................ 09-19-2024
*01145 USE OF PREMISES
01255 CHANGE ORDER PROCEDURES
01270S Measurement and Payment ....................................................... 08-06-2024
*01270 MEASUREMENT AND PAYMENT
01312 COORDINATION AND MEETINGS
01321S Construction Photographs ......................................................... 08-06-2024
*01321 CONSTRUCTION PHOTOGRAPHS
01326S Construction Schedule (Bar Chart) ............................................ 11-01-2004
*01326 CONSTRUCTION SCHEDULE (BAR CHART)
01330S Submittal Procedures................................................................. 07-22-2005
*01330 SUBMITTAL PROCEDURES
01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
01410 TPDES REQUIREMENTS (WITH ATTACHMENTS)
01450 CONTRACTOR'S QUALITY CONTROL
01452 INSPECTION SERVICES
01454 TESTING LABORATORY SERVICES
01502S Mobilization ................................................................................ 05-18-2026
*01502 MOBILIZATION
01504S Temporary Facilities and Controls ............................................. 02-08-2022
*01504 TEMPORARY FACILITIES AND CONTROLS
01506S Diversion Pumping ..................................................................... 11-17-2025
*01506 DIVERSION PUMPING
01555S Traffic Control and Regulation ................................................... 12-01-2025
*01555 TRAFFIC CONTROL AND REGULATION
01562S Tree and Plant Protection .......................................................... 08-06-2024
*01562 TREE AND PLANT PROTECTION
01570S Storm Water Pollution Control ................................................... 09-19-2024
*01570 STORM WATER POLLUTION PREVENTION CONTROL
01576 WASTE MATERIAL DISPOSAL
01578S Control of Ground and Surface Water ....................................... 12-01-2025
*01578 CONTROL OF GROUND AND SURFACE WATER
01610 BASIC PRODUCT REQUIREMENTS
00010-3 05-27-2026
01630 PRODUCT SUBSTITUTION PROCEDURES
01731 CUTTING AND PATCHING
01740S Site Restoration ......................................................................... 03-11-2026
*01740 SITE RESTORATION
01770S Closeout Procedures ................................................................. 09-19-2024
*01770 CLOSEOUT PROCEDURES
01785S Project Record Documents ........................................................ 08-06-2024
*01785 PROJECT RECORD DOCUMENTS
DIVISION 2 - SITE WORK
02082S Precast Concrete Manholes ....................................................... 03-11-2026
*02082 PRECAST CONCRETE MANHOLES
02083S Fiberglass Manholes .................................................................. 08-06-2024
*02083 FIBERGLASS MANHOLES
02086S Adjusting Manholes, Inlets, and Valve Boxes to Grade ............. 09-19-2024
*02086 ADJUSTING MANHOLES, INLETS, AND VALVE BOXES TO GRADE
02090 FRAMES, GRATES, RINGS, AND COVERS
02091 NON METALLIC FRAMES, GRATES, RINGS, AND COVERS
02221S Removing Existing Pavements and Structures .......................... 03-11-2026
*02221 REMOVING EXISTING PAVEMENTS, STRUCTURES, WOOD, AND
DEMOLITION DEBRIS.
02222S Abandonment of Sewers ............................................................ 08-06-2024
*02222 ABANDONMENT OF SEWERS
02260S Trench Safety System ................................................................ 08-06-2024
*02260 TRENCH SAFETY SYSTEM
02317S Excavation and Backfill for Utilities ............................................ 03-11-2026
*02317 EXCAVATION AND BACKFILL FOR UTILITIES
02318S Extra Unit Price Work for Excavation and Backfill ...................... 05-12-2025
*02318 EXTRA UNIT PRICE WORK FOR EXCAVATION AND BACKFILL
02320 UTILITY BACKFILL MATERIALS
02321S Cement Stabilized Sand ............................................................ 09-19-2024
*02321 CEMENT STABILIZED SAND
02336S Lime-Stabilized Subgrade .......................................................... 09-19-2024
*02336 LIME STABILIZED SUBGRADE
02338S Portland Cement Stabilized Subgrade ....................................... 09-19-2024
*02338 PORTLAND CEMENT STABILIZED SUBGRADE
02400S Tunnel Shafts ............................................................................. 10-27-2025
*02400 TUNNEL SHAFTS
02448S Pipe and Casing Augering for Sewers ....................................... 08-06-2024
*02448 PIPE AND CASING AUGERING FOR SEWERS
02501S Ductile Iron Pipe and Fittings ..................................................... 03-11-2026
*02501 DUCTILE IRON PIPE AND FITTINGS
02505 HIGH DENSITY POLYETHYLENE (HDPE) SOLID AND PROFILE WALL
PIPE
00010-4 05-27-2026
02506S Polyvinyl Chloride Pipe .............................................................. 08-06-2024
*02506 POLYVINYL CHLORIDE PIPE
02521 GATE VALVES
02524 AIR RELEASE AND VACCUM RELIEF VALVE
02528 POLYETHYLENE ENCASEMENT/WRAP
02531S Gravity Sanitary Sewers ............................................................ 11-17-2025
*02531 GRAVITY SANITARY SEWERS
02532 SANITARY SEWER FORCE MAINS
02533S Acceptance Testing for Sanitary Sewers ................................... 12-05-2025
*02533 ACCEPTANCE TESTING FOR SANITARY SEWERS
02534S Sanitary Sewer Service Stubs or Reconnections ....................... 05-12-2026
*02534 SANITARY SEWER SERVICE STUBS OR RECONNECTIONS
02550 SLIPLINING SANITARY SEWERS
02553S Point Repairs and Obstruction Removals .................................. 05-13-2026
*02553 POINT REPAIRS AND OBSTRUCTION REMOVALS
02555S Manhole Rehabilitation .............................................................. 02-19-2026
*02555 MANHOLE REHABILITATION
02556S Cured-in-Place Pipe ................................................................... 11-10-2025
*02556 CURED-IN-PLACE PIPE
02558S Cleaning and Television Inspection ........................................... 11-19-2025
*02558 CLEANING AND TELEVISION INSPECTION
02571S Pipe Bursting/Crushing Sanitary Sewers ................................... 11-12-2025
*02571 PIPE BURSTING/CRUSHING SANITARY SEWERS
02611S Reinforced Concrete Pipe .......................................................... 05-13-2025
*02611 REINFORCED CONCRETE PIPE
02621 GEOTEXTILE
02711S Hot Mix Asphalt Base Course .................................................... 12-09-2025
*02711 HOT MIX ASPHALT BASE COURSE
02712S Cement Stabilized Base Course ................................................ 12-09-2025
*02712 CEMENT STABILIZED BASE COURSE
02713S Recycled Crushed Concrete Base Course ................................ 12-09-2025
*02713 RECYCLED CRUSHED CONCRETE BASE COURSE
02741S Asphaltic Concrete Pavement .................................................... 06-17-2025 *02741 Asphaltic Concrete Pavement
02743 TACK COAT
02751S Concrete Paving ........................................................................ 05-20-2026
*02751 CONCRETE PAVING
02752S Concrete Pavement Joints ......................................................... 09-19-2024
*02752 CONCRETE PAVEMENT JOINTS
02753 CONCRETE PAVEMENT CURING
02754S Concrete Driveways ................................................................... 09-19-2024
*02754 CONCRETE DRIVEWAYS
02771 CURB, CURB AND GUTTER, AND HEADERS
02775S Concrete Sidewalks ................................................................... 09-24-2024
00010-5 05-27-2026
*02775 CONCRETE SIDEWALKS
02821 Chain Link Fences and Gates .................................................... 06-28-2005
02911 TOPSOIL
02915S Tree Planting ............................................................................. 06-25-2025
*02915 TREE PLANTING
02921S Hydro Mulch Seeding................................................................. 09-19-2024
*02921 HYDRO MULCH SEEDING
02922S Sodding ...................................................................................... 08-06-2024
*02922 SODDING
02951S Sodding ...................................................................................... 06-17-2025
*02951 PAVEMENT REPAIR AND RESTORATION
DIVISION 3 � CONCRETE
03315S Concrete for Utility Construction ................................................ 03-13-2026
*03315 CONCRETE FOR UTILITY CONSTRUCTION
END OF DOCUMENT
LIST OF DRAWINGS
00015-1 02-01-2004
Document 00015
LIST OF DRAWINGS
Drawing Title Drawing Date 02082-01 Sanitary Sewer Shallow Manhole�������������������.10-01-2002 02082-02 Sanitary Sewer 4�-0� Diameter Precast Concrete Manhole������.��.07-01-2010 02082N-02 Sanitary Sewer 4�-0� Diameter Precast Concrete Manhole Notes�..����10-01-2002 02082-03 Sanitary Sewer 5�-0� to 8�-0� Diameter Precast Concrete Manhole�����07-01-2010 02082-04 Sanitary Sewer Pile Supported Manhole for Unstable Subgrade���.��..10-01-2002 02082-05 Sanitary Sewer Crushed Stone Supported Manhole for Wet Stable Trench�.10-01-2002 02083-03 Sanitary Sewer Fiberglass Manhole with Cast-in-Place Base�����.��10-01-2002 ------------ New & Replacement Pre-Cast Concrete Manhole on MRC Sanitary Sewer�.02-06-2004 ------------ New & Replacement Fiberglass Manhole on MRC Sanitary Sewer�����02-13-2004 02090-01 Sanitary Sewer and Water Manhole Frame and Cover����������.07-01-2016 02091-01 Non-Metallic Manhole Frame and Cover����������������.07-01-2021 02317-01 Sanitary Sewer Embedment and Trench Zone Backfill for Dry or Wet
Stable Trench���������������������������...07-01-2016 02317-03 Sanitary or Storm Sewer Bedding and Backfill for Dry Stable Trench����03-02-2026 02317-08 Sanitary Sewer Backfill of Shafts�������������������..10-01-2002 02531-01 (REVD) Sanitary Sewer Sealing of Sliplining at Manhole���.���.�����. �02-24-2007 02531-02 (REVD) Sanitary Sewer Sealing of Liner at Manhole�������............................02-22-2007 02531-04 Sanitary Sewer Pipe Transition for 36� Sewer and Smaller�������.....10-01-2002 02531-07 Sanitary Sewer Concrete Collar Detail for Connecting Existing Monolithic Sewers to Pipe
Sewers������������������������������..10-01-2002 02534-01 Sanitary Sewer Service Reconnection for Liner Pipe�����������10-01-2002 02534-02 Sanitary Sewer Service Reconnection with Stack on New or
Replacement Sewer�������������������������10-01-2002 02534-03A Sanitary Sewer Manhole Lining Payment Limits�������������10-01-2002 02534-05 Standard Cleanout Detail on Service Lead���������������.07-01-2010 ------------ Standard Cleanout Detail on Service Lateral������������...������ CO-4 Inch 4-Inch Cleanout Detail on Service Lead���������������......03-29-2007 02741-01 Hot-Mix Asphaltic Concrete Pavement Details�������������...11-27-2023
02751-01 Concrete Pavement Details���������������������...11-27-2023 02752-01 Pavement Expansion and Construction Joint Details���������......11-27-2023 02752-02 Sidewalk Expansion and Construction Joint Details�����������..11-27-2023 02754-01A 02754-01B
Driveway Detail with 4"x12" Curb for Local Residential Street�������11-27-2023 Driveway Detail with 6� Curbed Streets ����������������..11-27-2023
02754-02 Driveways with Culverts on Open Ditch Type Streets�������..�.�...11-27-2023 02775-01 Typical Sidewalk Layout and Details for Streets with Curbs..�������..11-27-2023 02775-02 Typical Curb Ramp Details ..�������������������.��11-27-2023 02775-03 Parallel Curb Ramp�������������������������.11-27-2023 02775-06 Detectable Warning Curb Ramp Details����������������..11-27-2023 02951-01 Street Cut for Concrete Pavement Replacement/Restoration Age of Pavement <=
5yrs����..��������..�������������������11-27-2023 02951-02 Street Cut for Concrete Pavement Replacement/Restoration Age of Pavement >
5yrs������������������������������...�.11-27-2023 02951-03 Street Cut for Asphalt Pavement Replacement/Restoration for Pavement of All
Ages�����.�������..�������������������11-27-2023 02951-04 Pavement Repair Details for Street Cuts (Flex-Base Pavement & Concrete
Pavement)���������������������������.��11-27-2023 02951-05 Pavement Repair Details for Street Cuts (Non-Reinforced Concrete & Brick
Pavement)���������.��..�����������������.11-27-2023 Detail MH-1 Raise Existing Sanitary Sewer Manhole Frame and Cover������..��02-15-2007
LIST OF DRAWINGS
00015-2 02-01-2004
Drawing Title Drawing Date Detail MH-2 Rehabilitation of Manhole Bench and Invert������������...��02-21-2007
END OF DOCUMENT
WORK ORDER
AGREEMENT
00520WO-1
05-27-2026
Document 00520WO
WORK ORDER AGREEMENT
Project:
Project Location:
Project No:
The City:
THE CITY OF HOUSTON, 900 Bagby Street, Houston, Texas 77002 (the �City�) and
Contractor:
(Address for Written Notice)
Contact Name and Email address:
For HPW and GSD construction projects, with respect to the General Conditions, the City Engineer, is:
Oluwole McFoy, P.E. (or his successor)
P. O. Box 1562
Houston, Texas 77251-1562
(Address for Written Notice)
For HAS construction projects, with respect to the General Conditions, the City Engineer is:
Eren Selcen, P.E. (or his successor)
111 Standifer Drive
Humble, Texas 77338
(Address for Written Notice)
THE CITY AND CONTRACTOR AGREE AS FOLLOWS:
ARTICLE 1
THE WORK OF THE CONTRACT
1.1 Contractor shall perform the Work in accordance with the Contract.
1.2 One or more Work Orders may be issued concurrently at any given time under the Contract.
ARTICLE 2
CONTRACT TIME
On-Call Services for Wastewater Collection System Rehab Project No.: WBS No. R-000266-0415-4, File No. 4250-01
On-Call Services for Wastewater Collection System Rehabilitation and Renewal
Within City Limits
WBS No. R-000266-0415-4, File No. 4250-01
00520WO-2
05-27-2026
2.1 The City may issue Work Orders within calendar days after Notice To Proceed for the Contract. This Agreement is effective on the Notice To Proceed date until the final acceptance of the last Work Order issued by the City. If the Director, makes a written request for renewal to the Contractor at least 30 days before expiration of the then-current term, and if sufficient funds are allocated, then, upon expiration of the then-current term, this Agreement is renewed for one (1) year upon expiration upon the same terms and conditions.
2.2 Each Work Order will establish the Contract Time for that Work Order based on the Estimated Work
Order Price. Contract Time shall be as following:
30 days for Estimated Work Order Price from $0 to $50,000;
60 days for Estimated Work Order Price from $50,001 to $100,000;
90 days for Estimated Work Order Price from $100,001 to $250,000;
90 + days for Estimated Work Order Price from $250,001 and over.
Project Manager may adjust the actual duration and Completion Date based on availability of materials or to comply with infrastructure needs.
2.3 The Parties recognize that time is of the essence for this Agreement and that the City will suffer financial loss if the Work is not completed within the Contract Time. Parties also recognize delays, expense, and difficulties involved in proving in a legal or arbitration proceeding actual loss suffered by the City if the Work is not completed on time. Accordingly, instead of requiring any such proof, the Parties agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay the City the amount stipulated in Document 00803, �Supplementary Conditions,� for each day beyond Contract Time.
2.4 Contractor shall achieve Date of Substantial Completion within the stipulated duration noted in each
Work Order, subject to adjustments of the Contract Time as provided in the Contract. Each Work Order will establish a date of Commencement and Completion Date specific to that Work Order.
ARTICLE 3
CONTRACT PRICE
3.1 Subject to terms of the Contract, the City will pay Contractor the Contract Price set out in each
Work Order in current funds for Contractor's performance of the Contract. The total Contract Price, as sum of Contract Prices of all Work Orders issued, shall not exceed_ , which includes Allowances, and Alternates, if any, accepted below.
3.2 The City accepts Alternates as follows: NA
ARTICLE 4
PAYMENTS
4.1 The City will make progress payments to Contractor as provided below and in the General
Conditions of the Contract.
4.2 The Period covered by each progress payment is one calendar month ending on the [___] 15th or
[X] last day of the month.
4.3 The City will issue Certificates for Payment and will make progress payments on the basis of such Certificates as provided in the General Conditions of the Contract.
4.4 Final payment, constituting entire unpaid balance of Contract Price, will be made by the City to
Contractor as provided in the General Conditions of the Contract.
On-Call Services for Wastewater Collection System Rehab
00520WO-3
05-27-2026
ARTICLE 5
CONTRACTOR REPRESENTATIONS
5.1 Contractor represents:
5.1.1 Contractor has examined and carefully studied Contract documents and other related data identified in Request For Competitive Sealed Proposals or Competitive Sealed Bids.
5.1.2 Contractor has visited the site and become familiar with and is satisfied as to general, local, and site conditions that may affect cost, progress, and performance of the Work.
5.1.3 Contractor is familiar with and is satisfied as to all federal, state, and local laws and regulations that may affect cost, progress, and performance of the Work.
5.1.4 Contractor has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) which have been identified in Contract documents and (2) reports and drawings of a hazardous environmental condition, if any, at the site which has been identified in Contract documents.
5.1.5 Contractor has obtained and carefully studied (or assumes responsibility for having done
so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, including applying specific means, methods, techniques, sequences, and procedures of construction, if any, expressly required by the Contract to be employed by Contractor, and safety precautions and programs incident thereto
5.1.6 Contractor does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for performance of the Work at Contract Price, within Contract Time, and in accordance with the Contract.
5.1.7 Contractor is aware of general nature of work to be performed by the City and others at the site that relates to the Work as indicated in Contract documents.
5.1.8 Contractor has correlated information known to Contractor, information and observations obtained from visits to the site, reports and drawings identified in the Contract, and all additional examinations, investigations, explorations, tests, studies, and data with the Contract.
5.1.9 Contractor has given City Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract, and written resolution thereof by City Engineer is acceptable to Contractor.
5.1.10 Contract documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
ARTICLE 6
MISCELLANEOUS PROVISIONS
6.1 The Contract may be terminated by either Party as provided in the General Conditions of the
Contract.
00520WO-4
05-27-2026
6.2 The Work may be suspended by the City as provided in the General Conditions of the Contract.
ARTICLE 7
ENUMERATION OF CONTRACT DOCUMENTS
7.1 The following documents are incorporated into this Agreement:
[ X ] Bid Form/Proposal Form
Document No. Title [ X ] 00610 Performance Bond [ X ] 00611 Statutory Payment Bond [ X ] 00612 One-year Maintenance Bond [ X ] 00613 One-year Surface Correction Bond [ ] 00623 Contractor�s Act of Assurance (SRF Form ED-103) [ ] 00628 Affidavit of Compliance with Disadvantaged Business Enterprise
(DBE) Program for Project Funded By AIP Grant [ X ] 00700 General Conditions.
[ ] 00800 Supplementary Conditions for Project CIP or AIP Funded [ ] 00801 Supplementary Conditions for Project AIP Funded [ ] 00802 SRF Supplementary Conditions [ X ] 00803 Supplementary Conditions for Project CIP or AIP Funded [ ] 00807 Bidder/Contractor Requirements for DBE Program [ X ] 00808 Minority and Women-owned Business Enterprise (MWBE) &
Persons with Disabilities Business Enterprise (PDBE) Program [ ] 00810 Federal Wage Rate - Highway [ ] 00811 Federal Wage Rate - Building [ ] 00812 Federal Wage Rate - Heavy [ X ] 00820 Wage Rate for Engineering Construction [ ] 00821 Wage Rate for Building Construction [ ] 00830 Trench Safety Geotechnical Information [ ] 00912 Rider [ ] 00943 Monthly Subcontractor Payment Reporting Form [ ] 00946 Payment Notification � Explanation of Withholding
[ X ] Addenda [and Riders] which apply to the Contract, are as follows:
Addendum No. 1, dated
Addendum No. 2, dated
Addendum No. 3, dated
Rider No. [ ], dated
[ X ] 00010 Table of Contents (sealed) [ X ] Drawings listed in Document 00015, List of Drawings [ X ] Division 01 - General Requirements.
[ X ] Divisions 02 through 50 of Specifications.
00520WO-5
05-27-2026
ARTICLE 8
SIGNATURES
8.1 The Parties have executed this Agreement in multiple copies, each of which is an original. Each person signing this Agreement represents and warrants that he or she is duly authorized and has legal capacity to execute and deliver this Agreement. Each Party represents and warrants to the other that the execution and delivery of this Agreement and the performance of such Party�s obligations hereunder have been duly authorized and that the Agreement is a valid and legal agreement binding on such Party and enforceable in accordance with its terms. The Parties hereby agree that each Party may sign and deliver this Agreement electronically or by electronic means and that an electronic transmittal of a signature, including but not limited to, a scanned signature page, will be as good, binding, and effective as an original signature.
CONTRACTOR: (If Joint Venture)
By: By:
Name: Name:
Title: Title:
Title: Title:
Tax Identification Number: Tax Identification Number:
CITY OF HOUSTON, TEXAS
ATTEST/SEAL: SIGNED:
By: By:
City Secretary Mayor
APPROVED: COUNTERSIGNED:
By: By:
Director, Houston Public Works City Controller
By: Date Countersigned:
Chief Procurement Officer
8.2 This Contract and Ordinance have been reviewed as to form by the undersigned Assistant City Attorney and have been found to meet established Legal Department criteria. Legal Department has not reviewed the content of these documents.
Assistant City Attorney Date
CONTRACTOR�S REVISED
MWSBE PARTICIPATION PLAN
<<Contractor Name>> 00570-Pg 1 of 4 Edition Date: 03-16-2026
Document 00570
BIDDER�S REVISED MWSBE PARTICIPATION PLAN
MWSBE ADVERTISED GOALS
MBE WBE SBE
The Bidder or Proposer shall submit this completed form with the bid to demonstrate the Bidder/Proposer�s plan to meet the M/W/SBE contract goal(s). If the Bidder/Proposer cannot meet the contract goal(s), the Bidder/Proposer has the burden to demonstrate �Good Faith Efforts,� which shall include correctly and accurately preparing and submitting this form, a Record of Post-Bid Good Faith Efforts (Document 00571), a Post Award Plan Deviation Request (Document 00572), and supporting documentation evidencing their �Good Faith Efforts,� as required by the City of Houston�s Good Faith Efforts Policy (Document 00808).
The City will review the Participation Plan and Good Faith Efforts at the time of bid opening. Visit http://www.houstontx.gov/obo for more information.
MBE, WBE, and SBE Goals are all separate Contract Goals, to be met individually on all contracts.
Any excess of one Goal cannot be applied to meet another Goal.
Hispanic-owned Firms are capped at 16% MBE in Construction & 7% MBE in Professional Services, Asian-owned Firms are capped at 6% MBE in Professional Services, and Women-owned Firms are capped at 8% WBE in Goods.
Any excess of SBE participation to meet other goal types must be explained via Good Faith Efforts (Documents 00471 &
00472).
All other locally certified firms (PDBE, VOSB, DVOSB, LGBTQ) may be utilized for up to 4% in lieu of MBE or WBE or combination of the two.
Up to 50% of the Bidder�s Participation plan may be met using Suppliers.
Up to 50% of the advertised goal may be met at the Prime level if the Prime is a City of Houston-certified firm. Bidder must select one (1) certification type for Prime-level credit. Prime-level credit must not exceed the individual MBE or WBE advertised goal. Prime-level credit does not apply to SBE-certified firms.
NAICS
Code
(6 digit)
Description of Work (Plan Sheet #, Unit Price #, Scope of
Work #, as applicable)
% of Total Bid Price
(2 decimal places; for example:
5.00%)
Services or
Supplier
Cert. Type for Goal: MBE, WBE, SBE or
OTHER LOCAL
CERTIFICATION
Certified Firm Name Firm Address Contact Name
Phone No. and E-Mail
MBE
WBE
USE THIS LINE FOR
PRIME LEVEL CREDIT ONLY.
CREDIT MUST NOT EXCEED
50% OF THE ADVERTISED
GOAL.
MBE
WBE
SBE
OTHER
PLEASE ELECTRONICALLY COMPLETE THIS FORM OR PRINT LEGIBLY
<<Contractor Name>> 00570-Pg 2 of 4 Edition Date: 03-16-2026
By submitting this form, your firm agrees to enter into formal subcontracting agreement(s) with the MWSBE subcontractors/subconsultants listed on this participation plan upon award of a contract from the City.
Authorized Signature:
Printed Name:
Company Name:
Date:
Phone: Email:
Bidder�s Participation
Plan Total
MBE WBE SBE
(up to 4%)
<<Contractor Name>> 00570-Pg 3 of 4 Edition Date: 03-16-2026
DOCUMENT 00570
BIDDER�S REVISED MWSBE PARTICIPATION PLAN
CONTINUATION PAGE
NAICS
Code
(6 digit)
Description of Work (Plan Sheet #, Unit Price #, Scope of
Work #, as applicable)
% of Total Bid Price
(2 decimal places; for example:
5.00%)
Services or
Supplier
Cert. Type for Goal: MBE, WBE, SBE or
OTHER LOCAL
CERTIFICATION
Certified Firm Name Firm Address Contact Name
Phone No. and E-Mail
MBE
WBE
*I understand that supplying inaccurate information may violate Texas Penal Code Section 37.10 and lead to City sanctions.
<<Contractor Name>> 00570-Pg 4 of 4 Edition Date: 03-16-2026
FOR CITY USE ONLY
MWBE Plan Compliant? YES NO
If no, date sent to OBO:
SPD Signature:
Date:
POST-BID
GOOD FAITH EFFORTS
00571-1 Edition date: 03-16-2026
Document 00571
POST-BID GOOD FAITH EFFORTS
Bidder Name: Project Name
A Bidder or Proposer that may be unable to complete or follow a Participation Plan (Document 00470) to meet the Contract Goal in the Supplemental Conditions (Document 00800), must submit this completed form along with Post Award Plan Deviation Request (Document 00572), providing supporting documentation evidencing their �Good Faith Efforts�, as required by the City of Houston�s Good Faith Efforts Policy (see Document 00808).
The Bidder or Prime Contractor has the burden to demonstrate �Good Faith Efforts� to meet the MWSBE goal, which includes correctly and accurately preparing and submitting this form and other efforts described in the City�s Good Faith Efforts Policy (Document 00808). The Office of Business Opportunity will review Good Faith Efforts and Participation Plan after selection of an apparent low bidder.
UNLESS THE BIDDER�S/PROPOSER�S PARTICIPATION PLAN MEETS THE INDIVIDUAL
CONTRACT GOALS, FAILURE TO SUBMIT THIS FORM MAY RESULT IN THE BID BEING FOUND
NON-RESPONSIVE.
Plan Item No.
MWSBE/
OTHER
Type for
Goal
Certified Firm Name Address, Phone No. and
Certified Firm
Contact Person
Methods of
Contact
Prime Contact Dates
Certified Firm
Response
Results of Contact (why suitable or not suitable for work)
MBE
WBE
SBE
OTHER
Phone E-mail Other
SBE
OTHER
Phone
SBE
OTHER
Phone
SBE
OTHER
Phone
00571-2 Edition date: 03-16-2026
Authorized Signature: Date: Phone:
Print Name: Email Address:
Company Name:
00571-3
CONTINUATION PAGE
Plan Item No.
MWSBE/
OTHER
Type for
Goal
Certified Firm Name
Address, Phone No. and
Certified Firm
Contact Person
Method of
Contact
Prime Contact Dates
Certified Firm
Response
Results of Contact (why suitable or not suitable for work)
MBE
WBE
SBE
OTHER
Phone
SBE
OTHER
Phone
SBE
OTHER
Phone
SBE
OTHER
Phone
SBE
OTHER
Phone
SBE
OTHER
Phone
SBE
OTHER
Phone
PLEASE COMPLETE ELECTRONICALLY OR PRINT LEGIBLY!
Authorized Signature: Date: Phone:
Print Name: Email Address:
Company Name:
POST AWARD PLAN
DEVIATION REQUEST
00572-1
Document 00572
POST AWARD PLAN DEVIATION REQUEST
Company Name:
Project Name:
Department Approved
Contract Goals
MBE
WBE
SBE
Total
Bidder�s Proposed Participation Plan
MBE
WBE
SBE
OTHER
(PDBE, VOSBE,
DVOSBE,
LGBTBE)
(up to 4%)
Total
Justification: Please provide the reason the Bidder is unable to meet the Contract Goal in Document 00800.
Good Faith Efforts: Please list any efforts not listed in the Bidder�s Pre-Bid Good Faith Effort (Document 00571) and provide supporting documentation evidencing �Good Faith Efforts�, as required by the City of Houston�s Good Faith Efforts Policy (Document 00808).
Date: Company Name:
Email: Company Representative:
Phone Number: Title:
PLEASE ELECTRONICALLY COMPLETE OR PRINT LEGIBLY!
FOR OFFICIAL USE ONLY: Approved Not Approved
OBO Representative Date:
Title:
LIST OF PROPOSED SUBCONTRACTORS
AND SUPPLIERS
00600-1 07-01-2013
Document 00600
LIST OF PROPOSED SUBCONTRACTORS AND SUPPLIERS
PROJECT NAME:
ORIG. CONTRACT PRICE: $ TOTAL DBE AWARD: $
PROJECT NO.: TOTAL MWSBE AWARD: $
DATE OF REPORT: TOTAL HUB AWARD: $
TOTAL PDBE AWARD: $
(6 digits)
SUBCONTRACTOR OR
SUPPLIER (INCLUDE
�MWSBE�, �PDBE�, �DBE�, OR
�HUB� DESIGNATION)2
ADDRESS
SCOPE OF
WORK3
NOTES: 1. RETURN FOR ALL PROJECTS AS REQUIRED IN DOCUMENT 00800 � SUPPLEMENTARY CONDITIONS.
RETURN WITHIN THE SPECIFIED NUMBER OF DAYS AFTER RECEIPT OF NOTICE OF INTENT TO AWARD
2. DESIGNATE FIRMS CERTIFIED BY THE CITY OFFICE OF BUSINESS OPPORTUNITY ON THIS FORM.
3. DESCRIBE THE WORK TO BE PERFORMED, FOR WHICH THE FIRM IS CERTIFIED, SUCH AS �PAVING�, �ELECTRICAL�, ETC.
4. CONTRACTOR SHALL EXECUTE CONTRACTS WITH APPROVED SUBCONTRACTORS AND SUPPLIERS
WITHIN 30 DAYS AFTER THE DATE OF THE NOTICE TO PROCEED. COPIES OF CONTRACTS WITH
DESIGNNATED FIRMS MUST BE SENT TO THE OFFICE OF BUSINESS OPPORTUNITY.
SIGNATURE: COMPANY NAME:
NAME: TITLE:
(Type or Print)
LIST OF PROPOSED SUBCONTRACTORS
AND SUPPLIERS
00600-2 07-01-2013
Document 00600
Continuation Page
PROJECT NAME:
DATE OF REPORT:
PROJECT NO.:
(6 digits)
SUBCONTRACTOR OR
SUPPLIER (INCLUDE
�MWSBE�, �PDBE�, �DBE�, OR
�HUB� DESIGNATION)2
ADDRESS
SCOPE OF
WORK3
SIGNATURE: COMPANY NAME:
NAME: TITLE:
(Type or Print)
PERFORMANCE BOND
00610-1 07-30-2020
Document 00610
THAT WE, , as Principal, (the �Contractor�), and the other subscriber hereto, , as Surety, do hereby acknowledge ourselves to be held and firmly bound to the City of Houston (the �City�), a municipal corporation, in the penal sum of $ for the payment of which sum, well and truly to be made to the City, its successors and assigns, Contractor and Surety do bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally.
THE CONDITIONS OF THIS OBLIGATION ARE SUCH THAT:
WHEREAS, the Contractor has on or about this day executed a Contract in writing with the City for , all of such work to be done as set out in full in said Contract documents therein referred to and adopted by the City Council, all of which are made a part of this instrument as fully and completely as if set out in full herein.
NOW THEREFORE, if the said Contractor shall faithfully and strictly perform the Contract in all its terms, provisions, and stipulations in accordance with its true meaning and effect, and in accordance with the Contract documents referred to therein and shall comply strictly with each and every provision of the Contract and with this Bond, then this obligation shall become null and void and shall have no further force and effect; otherwise the same is to remain in full force and effect. Should the Contractor fail to faithfully and strictly perform the Contract in all its terms, including but not limited to the indemnifications thereunder, the Surety shall be liable for all damages, losses, expenses and liabilities that the City may suffer in consequence thereof, as more fully set forth herein.
It is further understood and agreed that the Surety does hereby relieve the City or its representatives from the exercise of any diligence whatever in securing compliance on the part of the Contractor with the terms of the Contract, and the Surety agrees that it shall be bound to take notice of and shall be held to have knowledge of all acts or omissions of the Contractor in all matters pertaining to the Contract. The Surety understands and agrees that the provision in the Contract that the City will retain certain amounts due the Contractor until the expiration of 30 days from the acceptance of the Work is intended for the City's benefit, and the City will have the right to pay or withhold such retained amounts or any other amount owing under the Contract without changing or affecting the liability of the Surety hereon in any degree.
00610-2
It is further expressly agreed by Surety that the City or its representatives are at liberty at any time, without notice to the Surety, to make any change in the Contract documents and in the Work to be done thereunder, as provided in the Contract, and in the terms and conditions thereof, or to make any change in, addition to, or deduction from the Work to be done thereunder; and that such changes, if made, shall not in any way vitiate the obligation in this Bond and undertaking or release the Surety therefrom.
It is further expressly agreed and understood that the Contractor and Surety will fully indemnify and save harmless the City from any liability, loss, cost, expense, or damage arising out of Contractor�s performance of the Contract.
If the City gives Surety notice of Contractor�s default, Surety shall, within 45 days, take one of the following actions:
1. Arrange for Contractor, with consent of the City, to perform and complete the Contract; or
2. Take over and assume completion of the Contract itself, through its agents or through independent contractors, and become entitled to the payment of the balance of the Contract Price.
If the Surety fails to take either of the actions set out above, it shall be deemed to have waived its right to perform and complete the Contract and receive payment of the balance of the Contract Price and the City shall be entitled to enforce any remedies available at law, including but not limited to completing the Contract itself and recovering any cost in excess of the Original Contract Price from the Surety.
This Bond and all obligations created hereunder shall be performable in Harris County, Texas. This Bond is given in compliance with the provisions of Chapter 2253, Texas Government Code, as amended, which is incorporated herein by this reference.
Notices required or permitted hereunder shall be in writing and shall be deemed delivered when actually received or, if earlier, on the third day following deposit in a United States Postal Service post office or receptacle, with proper postage affixed (certified mail, return receipt requested), addressed to the respective other Party at the address prescribed in the Contract documents, or at such other address as the receiving party may hereafter prescribe by written notice to the sending party.
00610-3
IN WITNESS THEREOF, the said Contractor and Surety have signed and sealed this instrument on the respective dates written below their signatures and have attached current Power of Attorney.
ATTEST, SEAL: (if a corporation) WITNESS: (if not a corporation) Name of Contractor
Name: Name:
Title: Title:
Date:
ATTEST/SURETY WITNESS:
Full Name of Surety
(SEAL)
Address of Surety for Notice
Telephone Number of Surety
Title: Title: Attorney-in-Fact Date: Date:
This Ordinance or Contract has been reviewed as to form by the undersigned legal assistant and have been found to meet established Legal Department criteria. The Legal Department has not reviewed the content of these documents.
Legal Assistant Date
STATUTORY PAYMENT BOND
00611-1
Document 00611
THAT WE, , as Principal, hereinafter called Contractor and the other subscriber hereto, , as Surety, do hereby acknowledge ourselves to be held and firmly bound unto the City of Houston, a municipal corporation, in the sum of $ for the payment of which sum, well and truly to be made to the City of Houston, and its successors, the said Contractor and Surety do bind themselves, their heirs, executors, administrators, successors, jointly and severally.
WHEREAS, the Contractor has on or about this day executed a contract in writing with the City of Houston for all of such work to be done as set out in full in said Contract documents therein referred to and adopted by the City Council, all of which are made a part of this instrument as fully and completely as if set out in full herein;
NOW, THEREFORE, if the said Contractor shall pay all claimants supplying labor and materials to him or a Subcontractor in the prosecution of the Work provided for in the Contract, then, this obligation shall be void; otherwise the same is to remain in full force and effect;
PROVIDED HOWEVER, that this Bond is executed pursuant to the provisions of Chapter 2253, Texas Government Code, as amended, and all liabilities on this Bond shall be determined in accordance with the provisions of said Article to the same extent as if it were copied at length herein.
00611-2
IN WITNESS THEREOF, the said Contractor and Surety have signed and sealed
Title: Title:
Date:
ATTEST/SURETY WITNESS
Full Name of Surety assistant and have been found to meet established Legal Department criteria. The Legal Department has not reviewed the content of these documents.
ONE-YEAR MAINTENANCE BOND
00612-1 05-17-2005
Document 00612 hereinafter called Contractor, and the other subscriber hereto, , as Surety, do hereby acknowledge ourselves to be held and firmly bound to the City of Houston, a municipal corporation, in the sum of $ , for the payment of which sum well and truly to be made to the City of Houston and its successors, the said Contractor and Surety do bind themselves, their heirs, executors, administrators, successors, jointly and severally.
WHEREAS, the Contractor has on or about this day executed a Contract in writing with the City of Houston for all of such work to be done as set out in full in said Contract documents therein referred to and adopted by the City Council, all of which are made a part of this instrument as fully and completely as if set out in full herein.
NOW THEREFORE, if the said Contractor shall comply with the provisions of Paragraph 11.5.1 of the General Conditions, and correct work not in accordance with the Contract documents discovered within the established one-year period, then this obligation shall become null and void, and shall be of no further force and effect;
otherwise, the same is to remain in full force and effect.
delivered when actually received or, if earlier, on the third day following deposit in a United States Postal Service post office or receptacle, with proper postage affixed (certified mail, return receipt requested), addressed to the respective other party at the address prescribed in the Contract documents, or at such other address as the receiving party may hereafter prescribe by written notice to the sending party.
00612-2
IN WITNESS THEREOF, the said Contractor and Surety have signed and sealed
By: By:
Name: Name:
Title: Title:
ATTEST/SURETY WITNESS:
Full Name of Surety assistant and have been found to meet established Legal Department criteria. The Legal Department has not reviewed the content of these documents.
ONE-YEAR
SURFACE CORRECTION BOND
00613-1
Document 00613
ONE-YEAR SURFACE CORRECTION BOND
hereinafter called Contractor, and the other subscriber hereto, , as Surety, do hereby acknowledge ourselves to be held and firmly bound to the City of Houston, a municipal corporation, in the sum of $ , such sum being equal to four percent of the Original Contract Price, for the payment of which sum to be made to the City of Houston and its successors, Contractor and Surety do bind themselves, their successors, jointly and severally.
WHEREAS, the Contractor has entered into a Contract in writing with the City of Houston, Texas, dated of even date herewith, for all of such work to be done in accordance with the Contract documents therein referred to, and adopted by the City Council of the City of Houston.
NOW THEREFORE, if the Contractor shall comply with the provisions of Paragraph 11.5.1 of the General Conditions, and repair, replace, restore, and correct surface work associated with backfill operations of subsurface work not in accordance with the Contract documents discovered within one year from the date that the One-year Maintenance Bond has expired, then this obligation shall become null and void, and shall be of no further force and effect; otherwise, the same is to remain in full force and effect.
delivered when actually received or, if earlier, on the third day following deposit in a United States Postal Service post office or receptacle, with proper postage affixed (certified mail, return receipt requested), addressed to the respective other party at the address prescribed in the Contract documents, or at such other address as the receiving party may hereafter prescribe by written notice to the sending party.
ONE-YEAR
SURFACE CORRECTION BOND
00613-2
IN WITNESS THEREOF, the said Principal and Surety have signed and sealed this instrument on the respective dates written below their signatures.
By: By:
Name: Name:
Title: Title:
ATTEST/SURETY WITNESS:
Full Name of Surety assistant and have been found to meet established Legal Department criteria. The Legal Department has not reviewed the content of these documents.
CITY OF HOUSTON - CONDITIONS OF THE CONTRACT Page 1 of 55 DOCUMENT 00700 - GENERAL CONDITIONS 27 February 2026
Document 00700
GENERAL CONDITIONS
February 27, 2026 EDITION
TABLE OF ARTICLES
1. GENERAL PROVISIONS
2. THE CITY
3. CONTRACTOR
4. ADMINISTRATION OF THE CONTRACT
5. SUBCONTRACTORS AND SUPPLIERS
6. CONSTRUCTION BY THE CITY OR BY SEPARATE CONTRACTORS
7. CHANGES IN THE WORK
8. TIME
9. PAYMENTS AND COMPLETION
10. SAFETY PRECAUTIONS
11. INSURANCE AND BONDS
12. WARRANTIES AND CORRECTION OF THE WORK
13. MISCELLANEOUS PROVISIONS
14. TERMINATION OR SUSPENSION OF THE CONTRACT
Page 00700/2 of 55 CITY OF HOUSTON - CONDITIONS OF THE CONTRACT
DOCUMENT 00700 - GENERAL CONDITIONS
ARTICLE 1 � GENERAL PROVISIONS 5
1.1 DEFINITIONS
1.2 EXECUTION, CORRELATION AND INTENT
1.3 OWNERSHIP OF DOCUMENTS AND CONFIDENTIALITY
1.4 INTERPRETATION
ARTICLE 2 � THE CITY 11
2.1 LIMITATIONS OF THE CITY�S OFFICERS AND EMPLOYEES
2.2 DUTIES OF THE CITY
2.3 AVAILABILITY OF LAND AND USE OF SITE
2.4 THE CITY�S RIGHT TO STOP THE WORK
2.5 THE CITY�S RIGHT TO CARRY OUT WORK
ARTICLE 3 � CONTRACTOR 12
3.1 RESPONSIBILITIES
3.2 REVIEW OF CONTRACT AND FIELD CONDITIONS BY CONTRACTOR
3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
3.4 SUPERINTENDENT
3.5 LABOR; MINORITY AND WOMEN BUSINESS ENTERPRISE COMPLIANCE
3.6 PREVAILING WAGE RATES
3.7 LABOR CONDITIONS
3.8 DRUG DETECTION AND DETERRENCE
3.9 MATERIALS & EQUIPMENT
3.10 PRODUCT OPTIONS AND SUBSTITUTIONS
3.11 CASH ALLOWANCES
3.12 TITLE AND RISK OF LOSS
3.13 TAXES
3.14 PERMITS, FEES, AND NOTICES
3.15 CONSTRUCTION SCHEDULES
3.16 DOCUMENTS AND SAMPLES AT THE SITE
3.17 MANUFACTURER�S SPECIFICATIONS
3.18 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
3.19 CULTURAL RESOURCES AND ENDANGERED SPECIES
3.20 CUTTING AND PATCHING
3.21 CLEANING
3.22 SANITATION
3.23 ACCESS TO WORK AND TO INFORMATION
3.24 TRADE SECRETS
3.25 INDEMNIFICATION
3.26 RELEASE AND INDEMNIFICATION � PATENT, COPYRIGHT, TRADEMARK, AND TRADE SECRET INFRINGEMENT
3.27 INDEMNIFICATION PROCEDURES
3.28 CONTRACTOR DEBT
3.29 PRESERVATION OF CONTRACTING INFORMATION
3.30 COMPLIANCE WITH EQUAL OPPORTUNITY ORDINANCE
ARTICLE 4 � ADMINISTRATION OF THE CONTRACT 24
4.1 CONTRACT ADMINISTRATION
4.2 COMMUNICATIONS IN ADMINISTRATION OF THE CONTRACT
4.3 CONDITION PRECEDENT TO SUIT; WAIVER OF ATTORNEY FEES AND INTEREST
ARTICLE 5 � SUBCONTRACTORS AND SUPPLIERS 25
5.1 AWARD OF SUBCONTRACTS OTHER CONTRACTS FOR PORTIONS OF THE WORK
5.2 CONTRACTOR RESPONSIBILITY FOR SUBCONTRACTORS
CITY OF HOUSTON - CONDITIONS OF THE CONTRACT Page 3 of 55
ARTICLE 6 � CONSTRUCTION BY THE CITY OR BY SEPARATE CONTRACTORS 26
6.1 THE CITY�S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS .. 26
6.2 COORDINATION
6.3 MUTUAL RESPONSIBILITY
6.4 THE CITY�S RIGHT TO CLEAN UP
ARTICLE 7 � CHANGES IN THE WORK 27
7.1 CHANGES
7.2 WORK CHANGE DIRECTIVES
7.3 ADJUSTMENTS IN CONTRACT PRICE
7.4 MINOR CHANGES IN THE WORK
7.5 CONCEALED OR UNKNOWN CONDITIONS
7.6 CONTRACTOR REQUESTED CHANGES
7.7 REVIEW AND DETERMINATION BY CITY ENGINEER
ARTICLE 8 � TIME 31
8.1 PROGRESS AND COMPLETION
8.2 DELAYS AND EXTENSIONS OF TIME
ARTICLE 9 � PAYMENTS AND COMPLETION 32
9.1 UNIT PRICE WORK
9.2 ESTIMATES FOR PAYMENT, UNIT PRICE WORK
9.3 STIPULATED PRICE WORK
9.4 APPLICATIONS FOR PAYMENT, STIPULATED PRICE WORK
9.5 CERTIFICATES FOR PAYMENT
9.6 COMPUTATIONS OF CERTIFICATES FOR PAYMENT
9.7 DECISIONS TO WITHHOLD CERTIFICATION
9.8 PROGRESS PAYMENTS
9.9 DATE OF SUBSTANTIAL COMPLETION
9.10 PARTIAL OCCUPANCY OR USE
9.11 FINAL COMPLETION AND FINAL PAYMENT
9.12 LIQUIDATED DAMAGES
ARTICLE 10 � SAFETY PRECAUTIONS 38
10.1 SAFETY PROGRAMS
10.2 POLLUTANTS AND POLLUTANT FACILITIES
10.3 SAFETY OF THE ENVIRONMENT, PERSONS, AND PROPERTY
10.4 EMERGENCIES
ARTICLE 11 � INSURANCE AND BONDS 40
11.1 GENERAL INSURANCE REQUIREMENTS
11.2 INSURANCE TO BE PROVIDED BY CONTRACTOR
11.3 PROOF OF INSURANCE
11.4 PERFORMANCE AND PAYMENT BONDS
11.5 MAINTENANCE BONDS
11.6 SURETY
11.7 DELIVERY OF BONDS
ARTICLE 12 -- WARRANTIES AND CORRECTION OF THE WORK 47
12.1 WARRANTIES
12.2 ACCEPTANCE OF NONCONFORMING WORK
ARTICLE 13 � MISCELLANEOUS PROVISIONS 49
13.1 GOVERNING LAW AND VENUE
13.2 SUCCESSORS
13.3 BUSINESS STRUCTURE AND ASSIGNMENTS
Page 00700/4 of 55 CITY OF HOUSTON - CONDITIONS OF THE CONTRACT
13.4 WRITTEN NOTICE
13.5 RIGHTS AND REMEDIES
13.6 TESTS AND INSPECTIONS
13.7 INTEREST
13.8 PARTIES IN INTEREST
13.9 ENTIRE CONTRACT
13.10 WRITTEN AMENDMENT
13.11 COMPLIANCE WITH LAWS
13.12 SEVERABILITY
13.13 COMPLIANCE WITH CERTAIN STATE LAW REQUIREMENTS
13.14 ZERO TOLERANCE POLICY FOR HUMAN TRAFFICKING & RELATED ACTIVITIES
ARTICLE 14 - TERMINATION OR SUSPENSION OF THE CONTRACT 52
14.1 TERMINATION BY THE CITY FOR CAUSE
14.2 TERMINATION BY THE CITY FOR CONVENIENCE
14.3 SUSPENSION BY THE CITY FOR CONVENIENCE
14.4 TERMINATION BY CONTRACTOR
CITY OF HOUSTON - CONDITIONS OF THE CONTRACT Page 5 of 55
ARTICLE 1
GENERAL PROVISIONS
1.1 DEFINITIONS.
1.1.1 Agreement: Document signed by the Parties and binding the Parties, containing the…