Project Description_WA FWS LPO MULTI(1).pdf

PDF 570 KB Posted

Attached to
WA FWS LPO MULTI(1) Little Pend Oreille NWR Culvert Improvements
Solicitation number
69056726B000007
Issued by

About this file

This is a Project Description document for a federal construction contract opportunity issued by the U.S. Fish and Wildlife Service.

The project, titled "WA FWS LPO MULTI(1) Little Pend Oreille NWR Culvert Improvements," involves the replacement of six Aquatic Organism Passage (AOP) culverts within the Little Pend Oreille National Wildlife Refuge located approximately 75 miles north of Spokane, Washington. The project spans 0.23 miles and carries an estimated price range between $2,000,000 and $5,000,000. The solicitation is anticipated for Spring/Summer 2026 under a sealed bid, firm-fixed-price contract structure. Three schedule options are available with fixed completion dates of Fall 2027 (Schedule A) or Fall 2028 (Schedules B and C).

The work scope, detailed using FP-14 specifications, encompasses multiple construction divisions including project requirements (construction survey and staking, quality control, sampling and testing, erosion control, dust control), earthwork (clearing and grubbing, cattle guard removal, excavation and embankment, riprap placement), aggregate and base courses, and incidental construction (concrete box culverts, structural plate structures, seeding, fertilizer application, willow pole cuttings, traffic control, and stream mitigation measures including rock weirs, log barriers, root wads, fish passage boulders, streambed material placement, and channel realignment). Specific quantities vary across the three schedule options, with Schedule A representing the baseline scope and Schedules B and C requiring progressively larger quantities of materials and labor.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Description Project name and Number: WA FWS LPO MULTI(1) Little Pend Oreille NWR Culvert Improvements

WA FWS LPO MULTI(1) Little Pend Oreille NWR Culvert Improvements

Little Pend Oreille National Wildlife Refuge

Pend Oreille, Washington

This Work consists of replacement of 6 Aquatic Organism Passage (AOP) culverts within the Wildlife refuge

Project Location: approximately 75 Miles North of Spokane, Washington (city).

Project Length: 0.23 Miles

Estimated Price Range: between $2,000,000 and $5,000,000

Tentative Solicitation Date: Spring/ Summer 2026

Contract Type: Sealed Bid; Firm-Fixed-Price

Tentative Fixed Completion Date: this project has multiple schedules

Schedule A, fixed completion date: Fall 2027

Schedule B, fixed completion date: Fall 2028

Schedule C, fixed completion date: Fall 2028

DESCRIPTION OF WORK in US CUSTOMARY UNITS

USING FP-14 SPECS

O n e S ch ed u le

S ch N am e

_B as e_

A d di ti on al

N am e O p ti

X

A d di ti

N am e

O p ti on

Y

DIVISION 150 – Project Requirements

152 Construction Survey & Staking (yes/no) Yes

Yes Yes

153 Contractor Quality Control and Assurance (yes/no) Yes Yes Yes

154 Contractor Sampling & Testing (yes/no) Yes Yes Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes Yes

157 Soil Erosion & Sediment Control (erosion control devices)

Fiber Roll/ Temp Stream Diversion

Fiber Roll/Temp

Stream Diversion

Fiber Roll/temp

Stream Diversion

158 Watering for Dust Control Yes Yes Yes

DIVISION 200 – Earthwork

201 Clearing & Grubbing 1 acre

1.2 acre 1.5 acre

203 Removal of Cattle Guard 2 each 2 each 2 each

204 Excavation & Embankment 380 CUYD 499 CUYD 590 CUYD

251 Place Riprap 650 CUYD 740 CUYD 830 CUYD

DIVISION 300 – Aggregate and Base Courses

302 Roadway Aggregate 523 CUYD 649 CUYD 776 CUYD

DIVISION 600 – Incidental Construction

602 Concrete Box Culverts 109 LNFT 109 LNFT 148 LNFT

O n e S ch ed u le

N am e

_B as e_

A d di ti

N am e O p ti

X

A d di ti

N am e

O p ti on

Y

603 Structural Plate Structures (culverts & drains) 76 LNFT

619 Remove and Reset Gate 1 1 1

622 Rental Equipment (yes/no) Yes Yes Yes

623 General Labor (yes/no) Yes Yes Yes

625 Seeding 2129 SQYD 2935 SQYD 3428 SQYD

625 Fertilizer 0.5 Acre 0.7 Acre 0.8 Acre

626 Cuttings, Willow Pole 1100 Each 1100 each 1100 each

629 Rolled Erosion Control Products 715 sqyd 715 sqyd 715 sqyd

633 Permanent Traffic Control – sign systems 24 each 30 each 36 each

635 Temporary Traffic Control - Barricade 10 each 14 each 14 each

635 Temporary Traffic Control – Construction Signs 14 each 22 each 22 each

635 Temporary Traffic Control – TCS 64 day 127 day 154 day

647 Mitigation, Rock weir 4 each 10 each 15 each

647 Mitigation, Log Barrier 2 each 2 each 2 each

647 Mitigation, Root Wad 6 each 8 each 8 each

647 Mitigation, Fish Passage Boulder 38 each 51 each 60 each

647 Mitigation, Streambed Material 490 CUYD 655 CUYD 725 CUYD

647 Mitigation, Streambed Channel Realignment 237 CUYD 237 CUYD 237 CUYD