This document package includes a project description and related federal contract opportunity for the WA FLAP JEFFER 150009(1) Undi Road Bypass Improvements project. The project consists of relocating approximately 3,500 feet of Undi Road due to landslide threats, requiring new road construction to join existing DNR roads. Work includes grading, drainage, base, chip seal, and other minor items. The estimated price range is between $1 million to $2 million. The tentative completion date is late fall 2023. The contract will be a sealed bid firm-fixed price contract offered as a small business set-aside through the Department of Transportation Federal Highway Administration, anticipated for solicitation in spring 2023.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT DESCRIPTION
WA FLAP JEFFER 150009(1), Undi Road Bypass Improvements, Jefferson and Clallam Counties, Washington
This project consists of relocating Undi Road (currently unstable) to an area that is free of landslide threat. This will require approximately 3,500 feet of new road construction to join to existing DNR roads. Work includes grading, drainage, base, chip seal, and other small items of work.
Project length: 0.7 miles
Tentative Fixed Completion Date: Late Fall 2023
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $1 million to $2 million
Location: 5 miles south of Forks, Washington
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
S c h e d u le
A
DIVISON 150-Project Requirements
152 Construction Survey & Staking (yes/no) Yes
153 Contractor Quality Control and Assurance (yes/no) Yes
154 Contractor Sampling & Testing (yes/no) Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no)
Yes
157 Soil Erosion & Sediment Control (Fiber Roll) 1,966 LNFT
157 Soil Erosion & Sediment Control (Check Dam) 14 EACH
157 Soil Erosion & Sediment Control (Inlet Protection) 1 EACH
DIVISION 200 – Earthwork
201 Clearing & Grubbing 5,600 SQYD
204 Excavation & Embankment 7,000 CUYD
207 Earthwork Geosynthetics 4,320 SQYD
211 Roadway Obliteration 38 SQYD
S c h e d u le
A
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Riprap 21 CUYD
251 Riprap Ditch 576 LNFT
DIVISION 300 – Aggregate and Base Courses
302 Minor Crushed Aggregate 2,300 TON
DIVISION 400 – Asphalt Pavements & Surface Treatments
407 Chip Seal 9,300 SQYD
DIVISION 600 – Incidental Construction
602 Culverts 195 LNFT
604 Catch Basins 1 EACH
605 Underdrain System 140 LNFT
621 Monuments & Markers (construction survey & staking) No
622 Rental Equipment No
623 General Labor No
625 Turf Establishment 5,922 SQYD
625 Mulching, Hydraulic Method 5,922 SQYD
629 Rolled Erosion Control Products 3,665 SQYD
633 Signs 39 SQFT
634 Permanent Pavement Markings (traffic pavement markings) 5,850 LNFT
634 Permanent Pavement Markings (White Stop Bar) 28 LNFT
635 Temporary Traffic Control, Drum 195 EACH
635 Temporary Traffic Control, Construction Signs 697 SQFT
635 Temporary Traffic Control, Flagger 1,432 HOUR