WA ERFO FS OLYMP609 2022-1(1), Olympic FS ERFO Repairs 2022
Solicitation number
69056725B000016
Issued by

About this file

This is a Base Schedule document for an Emergency Relief for Federally Owned (ERFO) road repair project in the Olympic National Forest, Clallam County, Washington. The project involves nine repair sites covering 0.35 miles and includes comprehensive infrastructure work such as drainage improvements, slope stabilization, reinforced soil slopes, special rock embankment, and pavement repairs. The estimated price range is $2 million to $5 million, with a tentative solicitation date in Fall 2025 and a projected completion date in Fall 2026.

The detailed Base Schedule breaks down work into six divisions: Project Requirements, Earthwork, Slope Reinforcement and Retaining Walls, Aggregate and Base Courses, Asphalt Pavements, and Incidental Construction. Key quantitative elements include 2 acres of clearing and grubbing, 1,000 cubic yards of roadway excavation, 850 cubic yards of mechanically-placed special rock embankment, 2,500 square feet of reinforced soil slope with welded wire face, 480 tons of asphalt concrete pavement, and various pipe culvert installations ranging from 24-inch to 120-inch diameters. The project also includes provisions for temporary traffic control, erosion management, and equipment usage.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA ERFO FS OLYMP609 2022-1(1), Olympic FS ERFO Repairs 2022

Olympic National Forest

Clallam County, Washington

The work consists of drainage, slope stabilization, reinforced soil slopes, special rock embankment, and pavement repairs.

Project length: 0.35 miles

Tentative Fixed Completion Date: Fall 2026

(Once solicitation is issued, see SF-1442 continuation, Block 11 for exact date.)

Tentative Solicitation Date: Fall 2025

Estimated Price Range: $2 million to $5 million

Location: This project includes nine Emergency Relief for Federally Owned

(ERFO) sites within the Olympic National Forest in Clallam County, Washington.

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-24

B as e S ch ed u le

DIVISION 150 – Project Requirements

151 Mobilization LPSM

152 Construction Survey & Staking LPSM

153 Contractor Quality Control LPSM

154 Contractor Testing LPSM

155 Construction Schedule LPSM

157 Soil Erosion Control, Silt Fence 520 LNFT

157 Soil Erosion Control, Fiber Roll 2,400 LNFT

157 Soil Erosion Control, Check Dam (Fiber Roll) 60 EACH

157 Soil Erosion Control, Check Dam (Filter Rock) 3 EACH

157 Soil Erosion Control, Check Dam (Sandbag) 10 EACH e S ch ed

DIVISION 200 – Earthwork

201 Clearing & Grubbing 2 ACRE

202 Selective Clearing 0.3 ACRE

203 Removal of Delineator 1 EACH

203 Removal Pipe Culvert 4 EACH

203 Removal Pipe Culvert 44 EACH

204 Roadway Excavation 1,000 CUYD

204 Subexcavation 100 CUYD

204 Unclassified Borrow 4,700 CUYD

204 Ditch, Excavation 240 CUYD

204 Backfill, Select Granular 750 CUYD

207 Stabilization Geotextile 435 SQYD

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 Placed Riprap, Class 2 40 CUYD

251 Placed Riprap, Class 3 170 CUYD

251 Placed Riprap, Class 4 210 CUYD

252 Special Rock Embankment, Mechanically- Placed 850 CUYD

261 Reinforced Soil Slope, Welded Wire Face 2,500 SQFT

DIVISION 300 – Aggregate and Base Courses

302 Roadway Aggregate, Method 2 1,590 TON

302 Roadway Aggregate, Method 2, Surface Course 530 TON

303 Ditch Reconditioning 35 LNFT

DIVISION 400 – Asphalt Pavements & Surface Treatments

403 Asphalt Concrete Pavement 480 TON

403 Tack Coat 210 GAL

DIVISION 600 – Incidental Construction

602 24-INCH Pipe Culvert 120 LNFT e S ch ed

602 36-INCH Pipe Culvert 110 LNFT

602 48-INCH Pipe Culvert 50 LNFT

602 120-INCH Pipe Culvert 80 LNFT

602 48-INCH Equivalent Diameter Arch or Elliptical Pipe Culvert 110 LNFT

602 60-INCH Equivalent Diameter Arch or Elliptical Pipe Culvert 190 LNFT

602 End Section for 48-INCH Pipe Culvert 1 EACH

605 Standard Underdrain System 390 LNFT

622 Dump Truck, 10 Cubic Yard Minimum Capacity 80 HOUR

622 Wheel Loader, 3 Cubic Yard Minimum Capacity 80 HOUR

622 Hydraulic Excavator, 1 Cubic Yard Minimum Capacity with Thumb Attachment 80 HOUR

624 General Labor 80 HOUR

624 Providing and Topsoil, 6-INCH Depth 240 SQYD

625 Turf Establishment 2 ACRE

628 Temporary Stream Diversion LPSM

629 Rolled Erosion Control Product 2,000 SQYD

635 Temporary Traffic Control, Barricade Type 3 (10’ Boards) 20 EACH

635 Temporary Traffic Control, Warning Light Type C 20 EACH

635 Temporary Traffic Control, Construction Sign 180 SQFT

635 Temporary Traffic Control, Traffic Control Supervisor 105 DAY