This pre-solicitation notice and project description outline a construction contract opportunity for the seismic retrofit of four bridges along Oregon State Route 58 for the Oregon Department of Transportation. Work includes structure repair, seismic retrofit, excavation, riprap, and repair or replacement of structural components. The fixed completion date is late fall 2025. The contract is firm-fixed price with a base schedule and single option. The estimated price range is between $15 million and $20 million. Interested vendors must register in SAM.gov to view the vendor list. Upon solicitation release, full and open competition will be provided on an unrestricted basis.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OR DOT 18(1), OR58: Coast Fork Willamette River to Lower Salt Cr Bridges Lane County, Oregon
The proposed contract action is for a firm-fixed-priced construction contract with a
Base schedule plus 1 Option. The primary objective of the proposed contract is to seismically retrofit four bridges on OR-58 between US-97 and I-5. OR-58 is included in the first phase of the Oregon Department of Transportation (ODOT)
Seismic Plus program to create lifelines that will be used to transport supplies following a major seismic event. The project provides access to the Willamette
Valley from Central Oregon. The following bridges are included in the project:
Bridge #05286 (MP 2.46), Bridge #07894 (MP 33.24), Bridge #02073C (MP
35.98), and Bridge #01519A (MP 38.25).
This work consists of: structure repair, structure seismic retrofit, excavation, and riprap.
Project length: 35.88 miles, Schedule A; 0.11 miles, Option Z
Tentative Fixed Completion Date: November 2025
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: Between $15,000,000 and $20,000,000
Location: Approximately 5 Miles SE of Springfield, Oregon
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
S ch ed u le A
O p ti o n Z
DIVISION 150 – Project Requirements
152 Construction Survey & Staking (yes/no) Yes Yes
153 Contractor Quality Control and Assurance (yes/no) Yes Yes
154 Contractor Sampling & Testing (yes/no) Yes Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes
157 Soil Erosion & Sediment Control
Silt Fence 970 LNFT 230 LNFT
Fiber Roll 1430 LNFT 770 LNFT
Stabilized Construction Entrance 6 EACH 2 EACH
DIVISION 200 – Earthwork
201 Clearing & Grubbing Removal, Individual Tree 0 30 EACH
203 Removal of Structures & Obstructions
Remove of Bridge Superstructure (End Frames) ALL 0 ed u ti o
Removal of Building (USGS Gage Station) ALL 0
Removal of Concrete 52 CUYD 38 CUYD
205 Blasting Consultant (Consultant/Engineering Services) (yes/no) No No
208 Structure Excavation
Structure Excavation 2117 CUYD 1972 CUYD
Shoring and Bracing 550 SQFT 0
Cofferdams ALL ALL
Dewatering ALL ALL
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Riprap Placed Riprap, Method A, Class 3 1695 CUYD 1620 CUYD
DIVISION 300 – Aggregate and Base Courses
302 Roadway Aggregate, Method 2 98 TON 0
DIVISION 400 – Asphalt Pavements & Surface Treatments
403 Asphalt Concrete 818 SQYD 0
414 Asphalt Pavement Crack Sealing & Filling 350 LNFT 0
DIVISION 500 – Rigid Pavement
502 Concrete Pavement Restoration 20 SQYD 45 SQYD
DIVISION 550 – Bridge Construction
551 Driven Piles
Sheet Pile 0 ALL
Sheet Pile (Tie-back) 0 ALL
552 Structural Concrete (concrete – major structures)
Class A (AE) 743 CUYD 467 CUYD
Class S (Seal) 0 186 CUYD
Repair Concrete 40 SQYD 0
Clean and Reseal Joints 80 LNFT 0
Expansion Joints 78 LNFT 78 LNFT
554 Reinforcing Steel 203,120 LB 70,220 LB
555 Steel Structures Structural Steel (Bolt Replacement) 0 ALL Structure Steel (Rivet Replacement) ALL 0 Miscellaneous Steel (Jacketing) 4 EACH 8 EACH Miscellaneous Steel (End Anchorage) 8 EACH 0 Miscellaneous Steel (End Frame) 6 EACH 0 Miscellaneous Steel (Truss Anchoring System) 4 EACH 0 Miscellaneous Steel (Seat Bracket) 72 EACH 0 559 Waterproofing (concrete – major structures) Membrane Waterproofing 818 SQYD 0 561 Structural Concrete Injection & Crack Repair 850 LNFT 0 562 Temporary Works Temporary Support Structure (Bridge Jacking) 6 EACH 0 563 Painting (structures, painting) Painting, Steel Structure 7200 SQFT 1800 SQFT 564 Bearing Devices 6 EACH 0 567 Micropiles ed u ti o
Micropile 2684 LNFT 1800 LNFT Micropile Load Verification Test 2 EACH 2 EACH Micropile Proof Load Test 4 EACH 4 EACH 569 Concrete Overlays For Bridge Decks
SQYD
575 Minor Bridge Work ALL 0 577 Plastic Structures Fiber Reinforced Polymer (FRP), Strengthening System 2460 SQFT 2160 SQFT
DIVISION 600 – Incidental Construction
601 Concrete, Plank 4 EACH 0 605 Underdrains, Sheet Drains & Pavement Edge Drains (culverts & drains) 4-Inch Collector Pipe 3900 LNFT 0 616 Slope Paving 350 SQYD 0
621 Monuments & Markers (construction survey & staking) (yes/no) No No
622 Rental Equipment (yes/no) Yes No
623 General Labor (yes/no) Yes No
625 Turf Establishment 1.5 ACRE 1.0 ACRE
626 Plants, Trees, Shrubs, Vines & Groundcovers
Plantings, Trees, Balled and Burlapped 0 60 EACH
Cutting, Willow Pole 490 EACH 0
633 Permanent Traffic Control Sign System 32 SQFT 0
634 Permanent Pavement Markings (traffic pavement markings)
Type B, Solid 1880 LNFT 2380 LNFT
Type B, Broken 0 1200 LNFT
635 Temporary Traffic Control
Traffic Signal System ALL 0
Arrow Board, Type C 2 EACH 0
Barricade Type 2 5 EACH 2 EACH
Barricade Type 3 10 EACH 2 EACH
Cone 212 EACH 28 EACH
Drum 126 EACH 24 EACH
Portable Changeable Message Sign 6 EACH 2 EACH
Construction Sign 317 SQFT 83 SQFT
Flagger 1148
HOUR
192 HOUR
Pilot Car 574 HOUR 96 HOUR
Traffic Control Supervisor ALL 0
646 Roadside Development
Remove and Reset Boat Ramp ALL 0
Access Road 0 ALL