This document provides a project description and related federal contract opportunity for the ID FS ERFO 2017(2)-81(1), Nez Perce-Clearwater Repairs 2017 project. The project description outlines the scope of work to consist of grading, rock embankment, aggregate surfacing, retaining walls, drainage and other minor items along a 17 mile stretch of road 10 to 40 miles east of Kamiah, Idaho. The work is broken down by engineering divisions and pay items. The related federal contract opportunity lists the solicitation number 69056720B000023 for this project, with an estimated price range of $3-5 million and tentative completion date of Fall 2021. This opportunity is designated as a small business set-aside and is offered through the Department of Transportation Federal Highway Administration.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID FS ERFO 2017(2)-81(1), Nez Perce-Clearwater Repairs 2017
The work consists of Grading, Rock Embankment, Aggregate surfacing, retaining walls, drainage and other small items of work.
Project length: 17 Miles
Tentative Fixed Completion Date: Fall 2021 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $3 million to $5 million
Location: 10 to 40 miles E of Kamiah, Idaho.
DESCRIPTION OF WORK in US CUSTOMARY UNITS | FP-14
On e S ch ed ul e Sc h Na m e
Ba se
Ad di tio na l S ch
Sc h Na m e
Op tio n X
Ad di tio na
Na m e
Op tio n Y
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes Yes Yes 153 Contractor Quality Control and Assurance
(yes/no) Yes Yes Yes 154 Contractor Sampling & Testing (yes/no) Yes Yes Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes Yes 157 Soil Erosion & Sediment Control (erosion control devices)
Temp Diversion 220
(LNFT)
Fiber Rolls 3,460
(LNFT)
Check Dams 58
(EACH)
Temp Diversion 160
(LNFT)
Fiber Rolls 1,900
(LNFT)
Check Dams 32
(EACH)
Fiber Rolls 1,300
(LNFT)
Check Dams 22
(EACH)
157 Watering for Dust Control 4,300 (MGAL) 2,700 (MGAL) 2,200 (MGAL)
DIVISION 200 – Earthwork 201 Clearing & Grubbing 2.9 (ACRE) 1.9 (ACRE) 0.9 (ACRE) 204 Excavation & Embankment
Roadway Excavation 4,470
(CUYD)
Select Borrow 560
(TON)
Roadway Excavation 1,230
(CUYD)
Unclassified Borrow
12,700 (TON)
Roadway Excavation 720
(CUYD)
207 Earthwork Geosynthetics 5,000 (SQYD) 5,000 (SQYD) 5,000 (SQYD) 208 Structure Excavation Foundation Fill 175
(CUYD)
Foundation Fill 70
(CUYD)
Foundation Fill 95
(CUYD)
ch ed ul e
Sc h
Na m e tio na
Na m e
Op tio n X
Ad di tio na
Na m e
Op tio n Y
DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap Class 3, 153 (CUYD) Class 3, 89 (CUYD) Class 3, 124 (CUYD) 252 Rockery, Special Rock Embankment, and Rock Buttress
Special Rock Embankment 2,760
(CUYD)
255 Mechanically Stabilized Earth Walls (retaining walls)
Welded Wire Face
2,790 (SQFT)
Select Granular Backfill 5,000
(CUYD)
Welded Wire Face
3,158 (SQFT)
Select Granular Backfill 5,000
(CUYD)
Welded Wire Face
4,740 (SQFT)
Select Granular Backfill 5,000
(CUYD)
257 Contactor-Designed Retaining Walls (contractor completed designs) LPSM 261 Reinforced Soil Slopes 4,540 (SQFT)
DIVISION 300 – Aggregate and Base Courses 302 Minor Crushed Aggregate Roadway Aggregate
2,440 (TON)
Roadway Aggregate
2,390 (TON)
Roadway Aggregate
1,340 (TON)
DIVISION 600 – Incidental Construction 602 Culverts & Drains (indicate one or both) 24-Inch Pipe Culvert
120 (LNFT)
36-Inch Pipe Culvert
37 (LNFT)
48-Inch Pipe Culvert
45 (LNFT)
72-Inch Pipe Culvert
53 (LNFT)
98-Inch Arch or
Elliptical Culvert 55
(LNFT)
24-Inch Pipe Culvert
137 (LNFT)
36-Inch Pipe Culvert
36 (LNFT)
120-Inch Pipe Culvert 130 (LNFT)
24-Inch Pipe Culvert
21 (LNFT)
36-Inch Pipe Culvert
147 (LNFT)
607 Clean Culvert in Place 2 (EACH) 622 Rental Equipment (yes/no) Yes Yes Yes 623 General Labor (yes/no) Yes Yes Yes 624 Topsoil (landscaping & related items) Conserve Topsoil, 4-inch Depth 1.5
(ACRE)
Conserve Topsoil, 4-inch Depth 1.0
(ACRE)
Conserve Topsoil, 4-inch Depth 0.7
(ACRE)
625 Turf Establishment (indicate seeding or mulching separately) 1.5 (ACRE) 1.0 (ACRE) 0.7 (ACRE) 635 Temporary Traffic Control – Flagger 1,920 (HRS) 240 (HRS) 240 (HRS) ch ed ul e
Sc h
Na m e tio na
Na m e
Op tio n X
Ad di tio na
Na m e
Op tio n Y
635 Temporary Traffic Control – Traffic Control Supervisor 120 (DAY) 15 (DAY) 15 (DAY) 635 Temporary Traffic Control – Construction Sign 500 (SQFT) 635 Temporary Traffic Control – Barricades 13 (EACH) 9 (EACH) 9 (EACH) 635 Temporary Traffic Control – Cone 260 (EACH)
| DIVISION 200 – Earthwork |
| DIVISION 250 – Slope Reinforcement and Retaining Walls |
| DIVISION 300 – Aggregate and Base Courses |