This document includes a project description and related federal contract opportunity for rehabilitation work at Glacier National Park headquarters in Montana. The project consists of pavement removal, clearing and grubbing, drainage, curb and gutter, sidewalk and signage installation along 0.85 miles of roadway near West Glacier. The estimated price range is $2-5 million and work must be completed in fall 2024. This will be a sealed bid small business set-aside awarded under two bid schedules, with only one schedule receiving the award. Interested vendors should monitor the opportunity on SAM.gov for issuance of the invitation for bids containing plans and specifications. The federal agency is the Department of Transportation Federal Highway Administration.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT NP GLAC P HQ(1), GLAC HQ Parking Area Rehabilitation
Glacier National Park, Flathead County, Montana
The work consists of pavement removal, removal of unsuitable material, clearing and grubbing, import of borrow material, drainage, curb and gutter, sidewalks, pavement, signage, and other small items of work.
Project length: 0.85 miles
Tentative Fixed Completion Date: Fall 2024
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $2 million to $5 million
Location: 0.5 miles N of West Glacier
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
S ch ed u le A
S ch ed u
B
DIVISION 150 – Project Requirements
152 Construction Survey & Staking (yes/no) Yes Yes
153 Contractor Quality Control and Assurance (yes/no) Yes Yes
154 Contractor Sampling & Testing (yes/no) Yes Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes
157 Soil Erosion & Sediment Control (Fiber Roll) 3000 LNFT 900 LNFT
157 Soil Erosion & Sediment Control (Inlet Protection) 2 EACH 1 EACH
DIVISION 200 – Earthwork
201 Clearing & Grubbing 4000 SQYD 1000 SQYD
202 Removal, Individual Tree 7 EACH 2 EACH
203 Removal of Drainage Structures 3 EACH 1 EACH
203 Removal of Curb & Gutter 992 LNFT 248 LNFT
203 Removal of Sidewalk 520 SQYD 130 SQYD
204 Excavation & Embankment 9360 CUYD 2340 CUYD
204 Subexcavation 202 CUYD 51 CUYD
204 Select Borrow 6320 TON 1580 TON
204 Granular Backfill 80 CUYD 20 CUYD
207 Earthwork Geosynthetics 104 SQYD 26 SQYD ch ed u ed u
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Riprap 2 CUYD 1 CUYD
DIVISION 300 – Aggregate and Base Courses
302 Minor Crushed Aggregate 6535 TON 1635 TON
313 Aggregate-Topsoil Course 752 SQYD 188 SQYD
DIVISION 400 – Asphalt Pavements & Surface Treatments
403 Asphalt Concrete 2867 TON 717 TON
412 Asphalt Tack Coat (asphalt surface treatment) 11 TON 3 TON
DIVISION 600 – Incidental Construction
604 Manholes, Inlets, & Catch Basins (Catch Basin) 2 EACH
604 Manholes, Inlets, & Catch Basins (Manhole Adjustment) 6 EACH 1 EACH
604 Manholes, Inlets, & Catch Basins (Inlet) 2 EACH
607 Cleaning, Relaying, & Repairing Existing Drainage Structures 3 EACH 1 EACH
609 Curb & Gutter (concrete – minor structures) (Curb & Gutter, 12” Depth) 1008 LNFT 252 LNFT
609 Curb & Gutter (concrete – minor structures) (Wheelstop) 33 EACH 8 EACH
611 Water Systems (Valve Adjustment) 7 EACH 2 EACH
615 Sidewalks, Pads & Paved Medians (concrete – minor structures) 520 SQYD 130 SQYD
621 Monuments & Markers (construction survey & staking) (yes/no) No No
622 Rental Equipment (yes/no) No No
623 General Labor (yes/no) No No
625 Turf Establishment (Seeding) 3632 SQYD 908 SQYD
633 Permanent Traffic Control (traffic control devices) Sign System 3 SQFT
633 Permanent Traffic Control (traffic control devices) Remove & Reset Sign 4 EACH 1 EACH
633 Permanent Traffic Control (traffic control devices) Snow Pole Holder 55 EACH 14 EACH
634 Permanent Pavement Markings (traffic pavement markings) Linear Markings 2144 LNFT 536 LNFT ch ed u ed u
634 Permanent Pavement Markings (traffic pavement markings) Symbols 4 EACH 1 EACH
635 Temporary Traffic Control – Barricade, Type 3 4 EACH 1 EACH
635 Temporary Traffic Control – Warning Light, Type B 4 EACH 1 EACH
635 Temporary Traffic Control – Plastic Fence 1120 LNFT 280 LNFT
635 Temporary Traffic Control – Construction Sign 95 SQFT 24 SQFT
646 Roadside Development (Remove & Reset Mailbox) 1 EACH