Project Description.pdf

PDF 103 KB Posted

Attached to
PN082001 ERCIP Microgrid, Mountain View, CA
Solicitation number
W912P720S0015
Issued by

View the file

Other files

File Type Posted
Survey.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers, San Francisco District Market Research Reference Sheet for 63rd Readiness Division Microgrid Requirements

Customer: 63rd Readiness Division

Location: Mountain View, CA

Timeline: TBD

Estimated Cost: $1M-$10M

REQUIREMENTS:

• PRIMARY FACILITY

Electric Power, Photovoltaic KW 750 Cyber Security EA 1 Electric Power, Generators (2x400kW) KW 800 Fuel Storage Tank GA 10,000 Fuel Containment Concrete + Enclosure EA 1

• SUPPORTING FACILITIES

Electric Service Information Systems

Purpose:

This project provides energy resilience for 14+ days for mission critical functions, utilizing renewable and fossil fuel energy sources. Microgrid supports the United States Army Reserve 63rd Readiness Division headquarters (which provides command for 7 states), the Defense Innovation Unit, and the California National Guard. The entire headquarter campus, consisting of the three buildings, is critical for the 63d Readiness Division since they support intelligence, medical, emergency, and Defense Support to Civil Authorities operations. The 63rd Reserve Division has recently participated DSCA (Defense Support of Civil Authorities) training - OPORD 19-004 Operations Order. Units assigned to Mountain View that would be likely to assemble and respond to a local disaster situation include a 32-bed Mobile Field hospital (166 staff) and Military Police (163 staff).

Install a microgrid system that will have full islanding capability. The microgrid system will incorporate a roof-mounted 750kW photovoltaic (PV) solar system with low voltage switchgear for building energy shifting; a 750kWh battery energy storage system (BESS); an 800kW diesel backup generation system, with a 10,000-gallon fuel storage tank. The photovoltaic system will be installed on the roofs of the headquarters building. The microgrid system will include a master microgrid controller, and automatic smart switches controlling the generation resources within the Reserve Center. Microgrid will be installed on a closed restricted network (CRN) requiring an Authority to Operate (ATO) IAW DODI 8510.01. System cybersecurity requirements will be designed IAW UFC 4-010-06.

File details come from the government source that posted it. Updated .