- Solicitation number
- 69056722B000024
About this file
This document package includes a project description and related federal contract opportunity notice for the AK FNSB TANANA(1) Tanana River Recreation Access Improvements project. The project description outlines the scope of work to improve access to the Tanana Lake Recreation Area and federally-managed lands along the Tanana River in Fairbanks, Alaska. Specific improvements include reconstructing and extending existing roads, expanding and paving parking lots, installing new restrooms and electric vehicle charging stations, and other site amenities. The estimated price range for the sealed bid contract is between $7-10 million, with a tentative completion date in fall 2023. The related federal contract opportunity posted on SAM.gov provides additional details on the pre-solicitation notice issued by the Department of Transportation Federal Highway Administration for the AK FNSB TANANA(1) project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| aka-fnsb-tanana_ preliminary plans_presol.pdf | ||
| Tanana_Prelim Letter_2022.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project number/name: AK FNSB TANANA(1), Tanana River Recreation Access Improvements.
PROJECT: AK FNSB TANANA(1), Tanana River Recreation Access Improvement.
LOCATION: Fairbanks, Alaska.
WORK: This project consists of The proposed project consists of improving access to the Tanana Lake Recreation Area (TLRA) and to federally-managed lands along the Tanana River. The scope of the project includes:
• The project will begin at the South Lathrop Street and Sanduri Avenue intersection where an existing at-grade road/rail crossing will be replaced.
• Reconstructing South Lathrop Street to the Tanana flood control levee with a 32 foot wide, paved driving surface.
• Extending South Lathrop Street approx. 1,700 feet beyond the Tanana flood control levee with a new 32 foot wide, paved driving surface.
• Extending Northlake Lane approx. 500 feet to a new 4-way intersection with the new South Lathrop Street extension.
• Parking lot resurfacing and expansion of the Swim Beach Parking Lot, paving of the Motorized Boat Launch and Non-Motorized Boat Launch, new restroom installation, and 1500’ of ADA compliant pathway.
• Vehicle plug-in installation at the Motorized Boat Launch and Non-Motorized Boat Launch.
LENGTH: 1.3 Miles.
TENTATIVE COMPLETION DATE: Fall 2023.
CONTRACT TYPE: Sealed Bid.
ESTIMATED PRICE RANGE: Between $7 million and $10 million.
To view the INTERESTED VENDORS LIST you must register as an SAM user and be logged in. Go to https://www.SAM.gov.
THIS SOLICITATION IS OFFERED AS A SMALL BUSINESS SET-ASIDE.
PRELIMINARY PLANS and a letter with additional project information are in electronic format only and are posted with this synopsis. Registering at ADD TO WATCHLIST box insures notification when solicitation documents are posted. When solicitation documents are issued, the INVITATION FOR BIDS/REQUEST FOR PROPOSAL (specifications and plans) will be posted at this link.
O ne
S ch ed ul e Sc h N am e
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance
(yes/no) Yes 154 Contractor Sampling & Testing (yes/no) Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes 157 Soil Erosion & Sediment Control (erosion control devices) – Fiber roll 13,000 LNFT
DIVISION 200 – Earthwork 201 Clearing & Grubbing 5.8 ACRE 203 Removal of Structures & Obstructions (Pipe culvert) 6 EACH 204 Roadway Excavation 9,750 CUYD 204 Subexcavation 20,000 CUYD 204 Select Borrow 115,000 CUYD 207 Earthwork Geosynthetics 83,000 SQYD 208 Structure Excavation 160 CUYD 211 Roadway Obliteration 5000 SQYD
DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap 150 CUYD
DIVISION 300 – Aggregate and Base Courses 301 Untreated Aggregate Courses (crushed aggregate) 33,000 TON 302 Minor Crushed Aggregate 13,000 TON 311 Stabilized Aggregate Surface Course 5,800 TON 312 Dust Palliative 110 TON 313 Aggregate-Topsoil Course 170 CUYD
O ne
S ch ed ul e Sc h N am e
DIVISION 400 – Asphalt Pavements & Surface Treatments 403 Asphalt Concrete 5,200 TON
DIVISION 600 – Incidental Construction 602 Culverts 700 LNFT 609 Wheel Stop, Concrete 250 EACH 619 Fences 360 LNFT 621 Monuments & Markers (construction survey & staking) (yes/no) No 622 Rental Equipment (yes/no) Yes 623 General Labor (yes/no) Yes 625 Turf Establishment (indicate seeding or mulching separately) 5.6 ACRES 627 Sod 3,000 SQYD 633 Permanent Traffic Control (signs) 670 SQFT 634 Permanent Pavement Markings (traffic pavement markings) 50,000 LNFT 635 Temporary Traffic Control – Flagger 500 HOUR 635 Temporary Traffic Control – Signs 715 SQFT 636 Traffic Signal, Traffic Counter, Lighting, & Electrical Systems LPSM 646 Roadside Development (vault toilet) 3 EACH