Print - Specifications _ Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal _27-179T Electrical.pdf
PDF 893 KB Posted
- Attached to
- Wakeman Town Farm Barn Electrical Work
- Solicitation number
- 27-179T
- Issued by
- Fairfield County, Connecticut
About this file
This is a Request for Proposal (RFP) issued by the Town of Westport, Connecticut Department of Public Works for electrical construction services at the Wakeman Farm Town Barn. The project encompasses all electrical work as noted on Drawings E-1 and E-2, including electrical requirements for heating and hot water (HW) and HVAC units, with the contractor required to supply all fixtures as specified. Work to be provided by others under separate agreements includes construction of the new structure, installation of construction fencing, erosion control measures, cultic units and underground roof drain piping, painting, temporary electrical service, demolition, and site work. Sealed bids are due by 11:00 AM on September 22, 2026, at the Town of Westport Controller's Office, Room 313, 110 Myrtle Avenue, Westport, Connecticut 06880. A non-mandatory site walkthrough is scheduled for Wednesday, September 9, 2026, at 10:00 AM. Written questions must be submitted by 4:00 PM on September 14, 2026, to bwatson@westportct.gov. The bid opening will occur via Zoom at 11:30 AM on September 22, 2026. The contract duration is 180 calendar days from receipt of the Notice to Proceed, commencing within ten calendar days after written authorization.
Bid security in the form of a bid bond is required at 15 percent of the total bid amount, including base bid and all alternates. Performance and payment bonds, each equal to 100 percent of the contract price, are required upon award. The Town of Westport is exempt from federal and Connecticut state sales and use taxes, and these taxes must not be included in bid prices. The contractor must maintain comprehensive insurance coverage including workers compensation with employer's liability limits of $500,000 each accident and $500,000 for disease, commercial general liability with occurrence limits of $1,000,000 and general aggregate limits of $2,000,000, commercial automobile insurance of $1,000,000 per accident, and umbrella/excess liability of $5,000,000 each occurrence and in aggregate. Liquidated damages are assessed at $200.00 per calendar day for failure to complete work within the contract time. The Town reserves the right to reject any and all bids and to waive any informalities or defects in the bidding process. Monthly progress payments will be made on the basis of completed, in-place work, with the Town retaining five percent until final completion.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical
Town of Westport Board of Selectmen
Department of Public Works
August 17, 2026
Town of Westport logo
Kevin Christie, First Selectman
Laurence Roberts, Director of Public Works
Keith S. Wilberg, PE, LS, Town Engineer
Engineering Division 110 Myrtle Ave, Room 210
Westport, CT 06880
(203) 341-1120
IRS ID #06-6002128
Town of Westport
Index
Town of Westport bidding and contract requirements
Scope of work Notice to bidders 00200 - Information for bidders
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 1/66
00300 - Proposal 00401 - Bid bond 00402 - Qualifications of bidder 00403 - Non-collusive bid statement 00404 - Agreement 00405 - Payment bond 00406 - Performance bond 00500 - General conditions 00700 – Supplementary conditions 01010 - Introduction to technical specifications 01530 – Dust control 01600 – Restoration
Division 1 - General requirements
01 23 00 Alternates
01 33 00 Submittals and Substitutions.
01 42 00 Applicable References
01 45 00 Quality Control
01 56 00 Temporary Barriers & Enclosures
01 74 19 Cleaning
01 75 00 Starting & Adjusting
01 77 00 Project Closeout
Scope of work
RFP 27-179T
Electrical
Scope of work RFP 27-179T Electrical
1. Scope of work
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 2/66
All work as noted on Drawings E-1 & E-2 All electrical as required for HW & HVAC units Supply all fixtures as specified
The following work will be provided by others under a separate agreement with the owner.
Construction of the new structure Installation of the construction fence Installation of all erosion control measures including the silt fence Installation of all cultic units and associated underground piping for the roof drains All painting Temporary electrical service All demolition All site work
Town of Westport, Connecticut Notice to bidders
Westport, Connecticut
Office of the Controller Town Hall, 110 Myrtle Ave.
Westport, Connecticut 06880
(203) 341-1080
Town of Westport, Connecticut
Notice to bidders
RFP 27-179T
Sealed bids for:
Wakeman Farm Town Barn electrical work will be received by the Town of Westport until
11:00 AM, September 22, 2026 at
Westport Town Hall Controller’s Office, Room 313
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 3/66
110 Myrtle Avenue Westport, CT 06880
No bids will be received after the hour specified above. Bid documents may be downloaded from the Town’s website:
www.westportct.gov/bids
The Town will hold a non-mandatory walkthrough at the site on Wednesday, September 9, 2026 at 10:00 AM
Questions in regards to the bid shall be submitted in writing to bwatson@westportct.gov by 4:00PM September 14th.
The Bid Opening will take place via ZOOM at 11:30 AM after the bid deadline. Bidders may request a ZOOM invitation by e-mailing Berit Watson at bwatson@westportct.gov, (203) 341-1047.
The Town of Westport reserves the right to waive any defects and informalities in the bidding or in any bid, to reject any or all bids for any reason whatsoever, and to accept that bid deemed to be in the best interest of the Town of Westport.
Berit Watson Westport Purchasing Officer
Wakeman Farm Barn Westport CT
RFP-27-179T
Electrical
00200 Information for bidders
Bids will be received by The Town of Westport (herein called the "Owner"), at the Office of the Controller, Room 313 Town Hall - 110 Myrtle Avenue, Westport, Connecticut, 06880 until:
11:00 AM, September 22, 2026
No bids will be received after the hour specified above. The Bid Opening will take place via ZOOM at 11:30 AM after the bid deadline. Bidders may request a ZOOM invitation by e-mailing Berit Watson, Westport Purchasing Officer, at bwatson@westportct.gov, (203) 341-1047.
Each Bid must be submitted in a sealed envelope, addressed to The Town of Westport, Office of the Controller, Room 313 at 110 Myrtle Avenue, Westport, Connecticut. Each sealed envelope containing a Bid must be plainly marked on the outside as:
RFP #27-179T
Wakeman Farm Town Barn
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 4/66 http://www.westportct.gov/bids mailto:bwatson@westportct.gov mailto:bwatson@westportct.gov mailto:bwatson@westportct.gov tel:+12033411047
Electrical
The bid envelope should also bear on the outside the name of the Bidder, the Bidder's address, and license number if applicable. If forwarded by mail, the sealed envelope containing the Bid must be enclosed in another envelope addressed to the Owner at the Office of the Controller, Room 313, Town Hall, 110 Myrtle Avenue, Westport, Connecticut, 06880.
All Bids must be made on the required Bid form. All blank spaces for Bid prices must be filled in, in ink or typewritten, and the Bid form must be fully completed and executed when submitted. Only ONE hard (paper) copy of the Bid form is required, and ONE electronic copy (CD or memory stick).
The Owner may waive any informalities or minor defects or reject any and/or all Bids. Any Bid may be withdrawn prior to the above scheduled time for the opening of Bids or authorized postponement thereof. Any Bid received after the time and date specified shall not be considered. No Bidder may withdraw a Bid within 90 days after the actual date of the opening thereof. Should there be reasons why the contract cannot be awarded within the specified period, the time may be extended by mutual agreement between the Owner and the Bidder.
Bidders must satisfy themselves of the accuracy of estimated quantities in the Bid Schedule by an examination of the site and a review of the Contract Drawings and Specifications including Addenda. After Bids have been submitted, the Bidder shall not assert that there was a misunderstanding concerning the quantities of Work or of the nature of the Work to be done.
Purchases made by the Town of Westport are exempt from payment of Federal Taxes and Connecticut Sales and Use Taxes, and such tax must not be included in the bid price of any items or materials permanently incorporated into the work or furnished to the Town under the contract.
Wakeman Farm Barn Westport CT
RFP-27-179T
Electrical
00200
Information for bidders
The Contract Documents contain the provisions required for the construction of the Project. Information obtained from an officer, agent, or employee of the Owner or any other person shall not affect the risks or obligations assumed by the Contractor or relieve the Bidder from fulfilling any of the conditions of the contract.
Each Bidder must include completed Qualifications of Bidder and Non-Collusive Bid Statement forms with his Bid. The low Bidder is required to submit completed Qualifications of Subcontractors, and non-collusion Affidavit of Subcontractor forms within ten (10) days of the Bid.
Each Bid must be accompanied by a Bid Bond payable to the Owner for fifteen (15) percent of the total amount of the Bid, including both the base bid amount and all alternates. As soon as the Bid prices have been compared, the Owner will return the bonds of all except the three lowest responsible Bidders. When the Agreement is executed the bonds of the two remaining unsuccessful Bidders will be returned. The Bid Bond of the successful Bidder will be retained until the payment bond and performance bond have been executed and approved, after which it will be returned. The surety on the Bid
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 5/66
Bond must be a corporate surety licensed to sign surety bonds in the State of Connecticut and also listed by the United States Treasury Department in its latest list as a qualified surety acceptable to the United States Government. No bid bond will be accepted if the amount is less than 15% of the total estimated bid, including both the base bid and all alternates, or if the amount exceeds the limit for which the United States Treasury Department has qualified the surety for any one bond. A certified check may be used in lieu of a Bid Bond.
A Performance Bond and a Payment Bond, each in the amount of 100 percent of the Contract Price, with a corporate surety approved by the owner, will be required for the faithful performance of the contract. The surety on the bond must meet the requirements stated under Bid Security except that the amount of the bond may exceed the limit for which the United States Treasury Department has qualified the surety if the excess is reinsured with surety companies that are qualified on the United States Treasury Department list for an amount equal to the amount of the reinsurance. Written evidence of how any excess suretyship has been placed by the surety signing the bond must accompany the bond.
Attorneys-in-fact who sign the Bid Bonds or Payment Bonds and Performance Bonds must file with each bond a certified and effective dated copy of their power of attorney.
The party to whom the contract is awarded will be required to execute the Agreement and obtain the Performance Bond and Payment Bond within ten calendar days from the date when Notice of Award is delivered to the Bidder. The Notice of Award shall be accompanied by the necessary Agreement and bond forms. In case of failure of the Bidder to execute the Agreement, the Owner may at his option consider the Bidder in default, in which case the Bid Bond accompanying the proposal shall become the property of the Owner.
The Owner, upon receipt of acceptable Performance Bond, Payment Bond, and Agreement signed by the Contractor shall sign the Agreement and return to the Contractor an executed duplicate of the Agreement within a 10-day period. The returned executed Agreement by the Owner to the Contractor shall be accompanied with a Notice to Proceed.
Wakeman Farm Barn Westport CT
RFP-27-179T
Electrical
00200
Information for bidders
The Owner may make such investigation as he deems necessary to determine the ability of the Bidder to perform the Work, and the Bidder shall furnish to the Owner all such information and data for this purpose as the Owner may request. The Owner reserves the right to reject any Bid if the evidence submitted by, or investigation of, such Bidder fails to satisfy the Owner that such Bidder is properly qualified to carry out the obligations of the Agreement and to complete the Work contemplated therein.
A conditional or qualified Bid will not be accepted.
The Owner reserves the right to reject the use of the Bidders subcontractor if the evidence submitted by, or investigation of, such subcontractor fails to satisfy the Owner that such subcontractor is properly qualified to complete the work contemplated herein. Rejection of the Bidders subcontractor shall not
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 6/66 relieve the Bidder of any requirements of the Bid or this Contract nor provide grounds for the Bidder to request compensation for his use of an alternate qualified subcontractor.
All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout.
Each Bidder is responsible for inspecting the site and for reading and being thoroughly familiar with the Contract Documents. The failure or omission of any Bidder to do any of the foregoing shall in no way relieve any Bidder from any obligation in respect to his Bid.
The low Bidder must supply the name and addresses of major material suppliers and subcontractors when requested to do so by the Owner.
Procedure for determining the lowest responsible, qualified bidder:
The Town shall determine the “Lowest Responsible Qualified Bidder” on the basis of the Bidder’s submission of the lowest “Total Base Bid”;
responsiveness of the Bidder’s proposal; demonstration of a history of ability and integrity necessary to perform the required work; and certification of the Bidder’s performance of the required work in accordance with the contract documents.
In the event of any discrepancies between this Information for Bidders and other sections of the contract documents, this Information for Bidders shall govern.
- End of Section -
Note about transcribed forms: this format exists to remove accessibility barriers, but some recipients prefer the original printed format. If you'd like help moving your entries into the original form, please use the live assistance options in the sidebar or contact the author.
00300
Proposal
The Board of Selectman Town Hall Westport, Connecticut
Project: Wakeman Farm Barn Town RFP # 27-179T Electrical
The undersigned declares he/she has carefully examined the Information for Bidders, Form of Proposal, Plans, Specifications, Addenda listed below, any other contract documents, and the site of work for the above project and hereby proposes to furnish all plant, labor, materials and equipment and perform all work necessary to complete the project in strict accordance with the requirements of the contract documents.
Accompanying this proposal is security for 15% of the contract bid upon, in the form of a bid bond in the amount of:
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 7/66
The names and addresses of all partners, officers or parties interested in the foregoing bid are as follows:
Name Address Phone # Email
The undersigned hereby designates at his office to which all notices and letters may be delivered or mailed.
Signature of bidder Contact information
(Name of Corporation, Firm or Individual)
In signing this Bid, I agree that I have received all the Bid Documents entitled dated in the Invitation to Bid, List of Drawings and Addenda numbered and dated as follows:
Addenda received
Addendum No.: Dated:
mm/dd/yyyy
Addendum No.:
Dated:
mm/dd/yyyy
Addendum No.: Dated:
mm/dd/yyyy
Addendum No.: Dated:
mm/dd/yyyy
Name row 1 Address row 1 Phone number row 1 Email row 1
Name row 2 Address row 2 Phone number row 2 Email row 2
Name row 3 Address row 3 Phone number row 3 Email row 3
Name of Corporation, Firm or Individual
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 8/66
PR-1
00300
Proposal
Base bid
1. Base bid:
The Base Bid shall include the cost of materials, labor, equipment, overhead, profit and taxes necessary to complete the work to the Owner’s satisfaction.
This includes, but is not limited to, temporary work, submittals, subcontractors, and other efforts required to affect the work. It also includes all materials, labor, and equipment for incidental work associated with the installation of the item, such as hardware, welding, curing and protection, and any other item implicit to the proper installation of the item subject to the acceptance by the Owner. The cost in the Base Bid shall include the quantities reflected in the Bid Documents.
Base bid
General Conditions including permits (no cost)
Trade costs including temporary electrical service ($) Total Base Bid ($)
The following costs shall be added to all change orders that increase the cost of the project:
Construction will commence 10 calendar days after written authorization to proceed and will be completed 180 calendar days after commencement.
2. Unit prices:
Unit Prices shall be used for adding, deducting or modifying base bid work as may be directed by the Town. The Unit Price shall include the cost of materials, labor and equipment, sales tax, and overhead and profit necessary to complete the work to the Owner’s satisfaction. This includes, but is not limited to, temporary work, submittals, subcontractors, and other efforts required to affect the work. It also includes all materials, labor, and equipment for incidental work associated with the installation of the item, and any other item implicit to the proper installation of the item subject to the acceptance by the Owner.
Unit prices
Item No. Work Item Description Units Unit Price
UP-1 Additional Receptacle One Unit price ($)
3. Conditions of submittal:
In submitting this bid, I agree as follows:
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 9/66
1. To hold open my bid for 120 days after bid opening.
2. To enter into and execute a contract, if awarded on the basis of this bid, according to the Agreement listed in the Bidding Documents.
3. To accomplish the work in accordance with the Contract Documents.
4. To begin work within ten (10) calendar days of receipt of Notice to Proceed, NTPC1.
5. To substantially complete the Work within the Contract Time.
6. By submission of this bid, each Bidder and each person signing on behalf of any Bidder certifies, and in case of a joint bid, each party thereto certifies, as to its own organization, under penalty of perjury, that to the best of knowledge and belief:
PR-2
00300
Proposal
6.1 The prices in this bid have been arrived at independently without collusion, consultation, communication, or agreement, for the purpose of restricting competition, as to any matter relating to such prices with any other bidder or with any competitor.
6.2 Unless otherwise required by law, the prices which have been quoted in this bid have not been knowingly disclosed by the bidder and will not knowingly be disclosed by the bidder prior to opening, directly or indirectly, to any other bidder or to any competitor; and
6.3 No attempt has been made or will be made by the bidder to induce any other person, partnership, or corporation to submit or not submit a bid for the purpose of restricting competition.
End of section
PR-3
Wakeman Farm Barn Westport CT
RFP-27-179T
00401
Bid Bond Town of Westport
Westport, Connecticut
Know all men by these presents
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 10/66
That we, of the Town of , County of , and
State of Connecticut, as Principal, and
, a corporation organized and existing under the laws of the State of
, and duly authorized to transact a surety business in the State of Connecticut (hereinafter called the “Surety”), as Surety, are held and firmly bound unto the Town of Westport, as Obligee, in the sum of:
Sum in words Sum in dollars lawful money of the United States of America, for the payment of which, well and truly to be made to the Obligee, we bind ourselves, our heirs, successors and assigns, jointly and severally, firmly by these presents.
The condition of this obligation is such that, whereas the Principal has submitted herewith to the Town of Westport, a Proposal dated mm/dd/yyyy attached, which is
Wakeman Farm Town Barn
RFP #27-179T
Now therefore,
(a) if such Proposal is rejected; or in the alternative,
(b) if such Proposal is accepted and the contract is awarded to the Principal, and the Principal enters into a written agreement when required by the Obligee, with such surety bonds as shall be acceptable
Wakeman Farm Barn Westport CT
RFP-27-179T
00401
Bid Bond
Principal name
Principal town Principal county
Surety corporation name
State where surety is organized
Proposal date
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 11/66 to the agreement and for the payment of all labor and material used in the performance of the work, then this obligation shall be null and void; otherwise the same shall remain in full force and effect, and the Principal and Surety hereto agree to pay to the Obligee all damages sustained by the agreement, including, but without limiting the generality of the foregoing, the difference between the amount of the Principal's Proposal submitted herewith and the amount for which the Obligee may contract with another party to perform the work covered by such Proposal if the latter amount is in excess of the former, subject, however, to the following conditions:
1. The liability of the Principal to pay to the Obligee the damages sustained by the Obligee as a consequence of the Principal's failure to enter into the agreement is not limited to the amount of this bond, and
2. The obligation of the Surety hereunder shall be the full amount of the Principal's liability, reduced by any amount paid by the Principal on account of such liability, but not more than the amount of this bond in any event.
3. The Surety, for value received, hereby stipulates and agrees that the obligation of said Surety and its bond shall in no way be impaired or affected by any extension of the time within which the Town of Westport may accept such bid; and such Surety does hereby waive notice of any such extension.
Wakeman Farm Barn Westport CT
RFP-27-179T
00401
Bid bond
In witness whereof, we have set our hands and seals this
Day of A.D. 20
Principal
Witness Principal (L.S.) Witness
Execution date
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 12/66
By (L.S.)
(If the Principal is a Corporation or Partnership, so indicate, as well as title of officer signing this bond on its behalf.)
Surety
Witness Surety (L.S.) Witness
By (L.S.)
Wakeman Farm Barn Westport, CT
RFP-27-179T
00401
Bid Bond Note: If an individual signs as agent for a surety company, he must also submit a power of attorney enabling him to act on behalf of the surety company, as well as a statement of its financial condition, and a copy of the corporate resolution authorizing the issuance of bonds.
Wakeman Farm Barn Westport CT
RFP-27-179T
00401
Bid bond
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 13/66
Acknowledgement of principal
State of County of SS
Date , 20
Personally appeared For signer(s) and sealer(s) of the foregoing instrument and acknowledged the same to be free act and deed, before me.
Commissioner of the Superior Court Notary Public
My Commission Expires
Acknowledgement of surety
State of County of SS
Date , 20
Personally appeared For signer(s) and sealer(s) of the foregoing instrument, Date before 20
Date after 20
Word or phrase before free act and deed
Date before 20
Date after 20
Word or phrase before being thereunto duly authorized
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 14/66 being thereunto duly authorized, and acknowledged the same to be free act and deed, and the free act and deed of said corporation, before me.
Commissioner of the Superior Court Notary Public
My Commission Expires
Wakeman Farm Barn Westport CT
RFP-27-179T
00402
Qualifications of Bidder Wakeman Farm Town Barn
RFP #27-179T
The bidder is required to submit on the following pages the information required in regard to qualifications for the work.
(Use back of this sheet if necessary)
A. The location, character, cost, date and names of engineers or officials of similar work previously constructed by the undersigned are as follows:
Similar work previously constructed
Word or phrase before free act and deed 9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 15/66
B. The equipment which will be available for performing the work under this contract is as follows:
Own Equipment Rented Equipment
C. The undersigned has failed to complete satisfactorily the following contracts, including also those in which the surety has participated. (If there have been no contracts which the bidder has failed to complete satisfactorily, including also those in which the surety has participated, the bidder shall definitely so state.)
Contracts not completed satisfactorily
Bidder information
Name of Bidder Address
Address line 2
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 16/66
Wakeman Farm Barn Westport CT
RFP-27-179T
00403
Non-collusive bid statement Wakeman Farm Town Barn
RFP #27-179T
All bidders are required to sign a Non-Collusive Bid Statement with all public bids as follows:
1. The bid has been arrived at by the bidder independently and has been submitted without collusion with, and without any agreement, understanding, or planned common course of action with any other vendor or materials, supplies, equipment, or services described in the Advertisement for Bids, designed to limit independent bidding or competition, and
2. The contents of the bid have not been communicated by the bidder or its employees or agents to any person not an employee or agent of the bidder or its surety on any bond furnished with the bid, and will not be communicated to any such person prior to the official opening of the bid.
Bidder information and signature
Name of bidder Address Address continued
Signature Title Date mm/dd/yyyy
Wakeman Farm Barn Westport, CT
RFP-27-179T
00404
Agreement
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 17/66
Agreement details
This agreement, made this day of , , by and between THE TOWN OF WESTPORT, a municipal corporation in the COUNTY OF FAIRFIELD and the State of Connecticut (hereinafter called the "Owner") and
Contractor legal name Contractor business name doing business as a (an individual), or (a partnership), or (a corporation) (hereinafter called the "Contractor") organized and existing under the laws of the State of Connecticut.
WITNESSETH: That for and in consideration of payments and agreements hereinafter mentioned:
1. The Contractor will commence and complete the construction of:
Wakeman Farm Town Barn
RFP #27-179T
within 180 consecutive calendar days of receipt of the Notice to Proceed. Any exceptions to this must be noted in the bid proposal.
2. The Contractor will furnish all of the material, supplies, tools, equipment, labor, and other services necessary for the construction and completion of the project described herein.
3. The Contractor agrees to perform all of the work described in the Contract Documents for the sum arrived at by multiplying the unit prices of the respective items in the Bid Schedule by the total quantities of the items completed and accepted, subject to additions and deductions as provided in the General Conditions.
4. The term "Contract Documents" means and includes the following:
Advertisement for Bids Information for Bidders Proposal Agreement
Wakeman Farm Barn Westport CT
RFP-27-179T
00404 Agreement
Day of month
Month Year
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 18/66
General Conditions Special Provisions Specifications Contract Drawings
Addenda as herein enumerated:
Addenda entries
No.
Dated mm/dd/yyyy
Year suffix after 20
No.
Dated mm/dd/yyyy
Year suffix after 20
No.
Dated mm/dd/yyyy
Year suffix after 20
Wakeman Farm Barn Westport CT
RFP-27-179T
00404
Agreement
5. The Owner will pay to the Contractor in the manner and at such times as set forth in the General Conditions such amounts as required by the
Contract Documents.
6. This Agreement shall be binding upon all parties hereto and their respective heirs, executors, administrators, successors, and assigns.
Wakeman Farm Barn Westport CT
RFP-27-179T
00404
Agreement
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 19/66
In witness whereof, the parties hereto have executed, or caused to be executed by their duly authorized officials, 4 copies of this Agreement, each of which shall be deemed an original on the date first above written.
Contractor
(Seal)
Attest
Contractor
By (L.S.)
Attest printed name
Name Title Date mm/dd/yyyy
Town of Westport
(Seal)
Attest
Town of Westport
By (L.S.)
Attest printed name
Name Kevin Christie, First Selectman Date mm/dd/yyyy
Approved as to form
Signature Asst. Town Attorney
I certify that the foregoing Contract has been examined and found to conform to the requirements of Chapter 11 of the Town Charter.
Wakeman Farm Barn Westport CT
RFP-27-179T
00404
Agreement
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 20/66
Controller Date mm/dd/yyyy
Wakeman Farm Barn Westport CT
RFP-27-179T
00405
Payment bond
Town of Westport Westport, Connecticut
Know all persons by these presents
That we, Principal name City or town of principal County of principal and state of Connecticut; as Principal, Surety name as Surety, are held and firmly bound unto the Town of Westport, hereinafter called Owner in the sum of:
Bond sum written out Bond sum in dollars
In lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, successors and assigns, jointly and severally, firmly by these presents.
The condition of this obligation is such that, whereas the Principal has entered into a certain written contract with the Owner, dated the
Day Month Year
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 21/66
(“Contract”) a copy of which is hereto attached and made a part hereof for the construction of:
Wakeman Farm Town Barn
RFP #27-179T
Now therefore, if the Principal and each of its Subcontractors shall promptly make payment to persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the work provided for in such Contract, and any authorized extension or modification thereof, including all amounts due for materials, lubricants, oil, gasoline, repairs on machinery, equipment and tools, consumed or used in connection with the construction of such work, and all insurance premiums on said work, and for all labor, performed in such work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect.
Wakeman Farm Barn Westport CT
RFP-27-179T
00405
Payment Bond
PROVIDED, FURTHER, that the said Surety, for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract or to the work or to the specifications.
PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.
Every person furnishing material or performing labor in the performance of the contract, either as an individual, as a subcontractor, or otherwise, shall have the right to sue on this bond.
In witness whereof
We have set our hands and seals this day of , 20 .
Day
Month Year last two digits
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 22/66
Witness for principal
Witness
Print name
Principal
Name of principal
Second witness for principal
Witness
Print name
Principal representative
By
Print name
Print title
Witness for surety
Witness
Print name
Surety
Name of surety
Wakeman Farm Barn Westport, CT
RFP-27-179T
00405 Payment Bond
Witness
Print Name:
By:
Print Name:
Print Title:
Note: Date of bond must not be prior to date of contract. If contractor is a partnership, all partners should execute bond.
Important: Surety companies executing bonds must appear on the Treasury Department's most current list (Circular 570, as amended) and be authorized to transact business in the State of Connecticut.
Witness information Signer information
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 23/66
RFP-27-179T
00406
Performance Bond
Town of Westport
Westport, Connecticut
Performance bond details
Know all persons by these presents
That we Of the City/Town of
County of
And State of
As Principal, and
Surety name Of the City/Town of
County of
And State of
As Surety, are held and firmly bound unto the Town of Westport, hereinafter called Owner in the sum of:
Sum of Dollar amount ($)
In lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, successors and assigns, jointly and severally, firmly by these presents. The liability of the Surety under this bond shall in no event exceed the bond amount set forth above or in any additions, riders or endorsements properly issued by the Surety.
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 24/66
The condition of this obligation is such that, whereas the Principal has entered into a certain written contract with the Owner, dated the
Contract date
Day Month Year (A.D./20__)
(“Contract”) a copy of which is hereto attached and made a part hereof for the construction of:
Wakeman Farm Town Barn
Request for Proposal #27-179T
Now therefore, if the Principal shall well and truly keep, and perform its duties, all the undertakings, covenants, terms, conditions and agreements of said Contract during the original term thereof, and any extensions thereof which may be granted by the Owner, with or without notice to the Surety, and during any additional guaranty period after the original term of the Contract, and if he shall satisfy all claims and demands incurred under such Contract, and shall fully indemnify and
Wakeman Farm Barn Westport CT
RFP-27-179T
00406
Performance Bond Save harmless the Owner from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect.
Provided, further, that the said Surety, for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract or to the work or to the specifications.
Provided, further, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 25/66
RFP-27-179T
00406
Performance bond
In witness whereof, we have set our hands and seals this day of , 20 .
Principal witness signatures
Witness
Print name
Witness
Print name
Principal
Principal name
[Insert name of principal], Principal
By
Print name
Print title
Surety witness signatures
Witness
Print name
Witness
Print name
Surety
Surety name
[Insert name of surety], Surety
By
Print name
Print title
Note: Date of bond must not be prior to date of contract. If contractor is a partnership, all partners should execute bond.
Month Year last two digits
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 26/66
Important: Surety companies executing bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State of Connecticut.
Wakeman Farm Barn Westport CT
RFP-27-179T
00500
General conditions
Table of contents
Article title Page
1. Definitions GC-1
2. Agreement and Contract Documents GC-1
3. Shop Drawings and Submittals GC-1
4. Work Area, Materials Storage, Temporary Services and Facilities GC-2
5. Inspection, Testing and Certificates of Conformance GC-2
6. Substitutions GC-2
7. Surveys, Layout of Work GC-2
8. Permits, Ordinances, and Regulations GC-3
9. Supervision by Contractor GC-3
10. Protection of Work, Property, Persons GC-3
11. Night and Sunday Work GC-3
12. Blasting and Explosives GC-3
13. Job Meetings GC-3
14. Changes in the Work GC-3
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 27/66
Article title Page
15. Changed Conditions GC-4
16. Changes in Contract Price GC-4
17. Time for Completion and Liquidated Damages GC-4
18. Suspension of Work, Termination and Delay GC-4
19. Measurement and Payments to Contractors GC-5
20. Partial Use of Site Improvements GC-6
21. Acceptance of Final Payment as Release GC-6
Wakeman Farm Barn Westport CT
RFP-27-179T
00500
General conditions
Article title Page
22. Insurance GC-6
23. Contract Security GC-7
24. Assignments GC-7
25. Indemnification GC-7
26. Separate Contracts GC-8
27. Private Utility Lines GC-8
28. Work by Others GC-8
29. Subcontracting GC-8
30. Engineer's Authority GC-8
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 28/66
Article title Page
31. Land and Rights of Way GC-8
32. Guaranty GC-8
33. Taxes GC-8
34. Provisions Required by Law Deemed Inserted GC-9
35. Safety Provisions GC-9
36. Wage Rates GC-9
00500
General Conditions
1. Definitions
ADDENDA - Written or graphic instruments issued prior to the execution of the Agreement which modify or interpret the Contract Documents, Contract Drawings and Specifications, by additions, deletions, clarifications or corrections.
AGREEMENT - The written agreement entered into between the Owner and the Contractor covering the Work to be performed, including without limitation the Contract Documents.
CHANGE ORDER - A written order to the Contractor authorizing an addition, deletion or revision in the Work within the general scope of the Contract Documents, or authorizing adjustment in the Contract Price or Contract Time.
CONTRACT – The Agreement, including without limitation the Contract Documents.
CONTRACT DOCUMENTS – The documents listed as “Contract Documents” in the Agreement.
CONTRACT DRAWINGS – A part of the Contract Documents consisting of the plans for Work.
CONTRACT PRICE - The total monies payable to the Contractor under the terms and conditions of the Contract Documents.
CONTRACT TIME - The number of calendar days stated in the Contract Documents for the completion of the Work.
CONTRACTOR - The person, firm or corporation with whom the Owner has executed the Agreement.
ENGINEER - The Westport Town Engineer.
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 29/66
FIELD ORDER - A written order effecting a change in the Work not involving an adjustment in the Contract Price or an extension of the Contract Time, issued by the Engineer to the Contractor during construction.
NOTICE OF AWARD - The written notice of the acceptance of the Bid from the Owner to the successful Bidder.
NOTICE TO PROCEED - Written communication issued by the Owner to the Contractor authorizing him to proceed with the Work and establishing the date of commencement of the Work.
OWNER - The Town of Westport
PROJECT - The undertaking to be performed as provided in the Contract Documents.
RESIDENT PROJECT REPRESENTATIVE - The authorized representative of the Owner who is assigned to the Project site or any part thereof.
SPECIAL PROVISIONS - Modifications, additions and clarifications to the Contract Documents.
SPECIFICATIONS - A part of the Contract Documents consisting of written descriptions of a technical nature of materials, equipment, construction systems, standards and workmanship.
WORK - All labor necessary to produce the construction required by the Contract Documents, and all materials and equipment incorporated or to be incorporated in the Project.
WRITTEN NOTICE - Any notice to any party of the Agreement relative to any part of the Agreement in writing and considered delivered and the service thereof completed, when posted by certified or registered mail to the said party at his last given address, or delivered in person to said party or his authorized representative on the Work.
2. Agreement and contract documents
The Contract Documents and all addenda shall form the Agreement, and provisions thereof shall be as binding upon the parties hereto as if they were herein fully set forth.
The Owner will furnish the Contractor, without charge, five copies of the Contract Documents, including Specifications and Contract Drawings.
Additional copies will be furnished at nominal cost to the Contractor, upon request.
In case of conflict between the Contract Drawings and Specifications, the Specifications shall govern. Figure dimensions on Contract Drawings shall govern over scale dimensions, and detailed drawings shall govern over general drawings. Any discrepancies found between the Contract Drawings and Specifications and site conditions, or any inconsistencies or ambiguities in the Contract Drawings or Specifications, shall be immediately reported to the Engineer, in writing, who shall promptly correct such inconsistencies or ambiguities in writing. Work done by the Contractor after his discovery of such discrepancies, inconsistencies or ambiguities shall be done at the Contractor's risk.
The Contractor may be furnished additional instructions and detail drawings by the Engineer as necessary to carry out the Work required by the Contract Documents. The additional drawings and instructions thus supplied will become a part of the Contract Documents.
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 30/66
3. Shop drawings and submittals
The Contractor shall provide three (3) copies of all shop drawings and submittals as required by the Specifications. The Engineer will retain two (2) copies of all approved shop drawings and submittals, and return one to the Contractor. Shop drawings and submittals are to be submitted as detailed in the Special Provisions, and/or sufficiently in advance of requirements, to provide the Engineer time for review and correction if necessary. The Engineer's review
GC-1
General conditions
Additional content from previous item (3): of shop drawings and submittals shall not release the Contractor from responsibility for deviations from the Contract Documents. Certificates of conformance must be submitted on all material and/or equipment that will become the property of the Owner.
Portions of the Work requiring shop drawings or submittals shall not begin until after review by the Engineer. Any submittals not following this procedure will be rejected.
4. Work area, materials storage, temporary services and facilities
The Contractor shall provide and pay for all materials, labor, tools, equipment, water, light, power, transportation, supervision, temporary construction of any nature, and all other services and facilities of any nature whatsoever necessary to execute, complete, and deliver the Work within the specified time.
The Contractor shall confine his work/storage area to the limits as designated or approved and shall be responsible for the security of the work/storage area. Storage of materials or establishing temporary facilities on private property shall be solely up to the Contractor and he shall assume all responsibility and liability for same. Upon completion of the Agreement, the Contractor shall remove all equipment and materials except as otherwise specified and restore the site to its original condition.
5. Inspection, testing and certificates of conformance
The Owner reserves the right to require testing of any and all materials, equipment or samples delivered to the job site. Such testing shall be done by an independent testing laboratory at the expense of the Contractor. Any material so sampled and found not to meet the requirements of these specifications shall be rejected and the entire shipment removed from the site at the Contractor's expense. Furthermore, the Owner reserves the right to then require each material to be manufactured and tested in accordance with the standard specifications, (e.g. AWWA, ANSI, etc.), cited hereafter.
In addition to other requirements specified, the Contractor shall furnish to the Engineer, in the manner as directed, notarized certificates of conformance for all materials to be furnished under this Agreement. The notarized certificates of conformance shall state that the material to be furnished under this Agreement meets the specification requirements. When directed, each shipment of material shall be accompanied by the manufacturer's notarized certificates of conformance, certifying that the materials meet the requirements of the specifications.
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 31/66
All materials and equipment used in the construction of the Project shall be subject to adequate inspection in accordance with generally accepted standards. Neither observations by the Engineer nor inspections, tests or approvals by persons other than the Contractor shall relieve the Contractor from his obligations to perform the Work in accordance with the requirements of the Contract Documents.
The Engineer, the Owner and their representatives will at all times have access to the Work. The Contractor will provide proper facilities for access, inspection, and observation of the Work. If any Work is covered contrary to the written request of the Engineer, it must, if requested by the Engineer, be uncovered for his observation and replaced at the Contractor's expense.
If the Engineer considers it necessary or advisable that covered Work be re-exposed, due to suspicion of defective work, the Contractor will uncover, expose or otherwise make available for observation, inspection or testing as the Engineer may require, that portion of the Work in question, furnishing all necessary labor, materials, tools, and equipment. If it is found that such Work is defective, the Contractor will bear all the expenses of such uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction. If, however, such Work is not found to be defective, the Contractor will be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure, observation, inspection, testing and reconstruction and an appropriate Change Order shall be issued.
6. Substitutions
References to brand names or catalogue numbers in the Contract Documents are for the purpose of defining the performance or other salient requirements of materials and equipment. The Contractor may request to substitute materials or equipment of equal substance and function. If in the opinion of the Engineer, such material or piece of equipment is of equal substance and function to that specified, the Engineer may approve its substitution and use by the Contractor. Any cost differential shall be deductible from the Contract Price and the Contract Documents shall be appropriately modified by Change Order. The Contractor warrants that if substitutes are approved, no major changes in the function or general design of the Project will result. Incidental changes or extra component parts required to accommodate the substitute will be made by the Contractor without a change in the Contract Price or Contract Time.
7. Surveys, layout of work
The Engineer shall furnish initial land surveys and establish all base lines for locating the principal component parts of the Work together with a suitable number of bench marks adjacent to the Work as shown on the Contract Drawings.
The Contractor shall perform all layout work necessary for the satisfactory execution of the construction as shown on the Contract Drawings and all costs in connection therewith shall be included in the Contract Price(s).
The Contractor shall be held responsible for protecting and safeguarding all control points and bench marks set by the Engineer and his own forces. Any replacement or re-establishment of control points and bench marks set by the Engineer, shall be at the expense of the Contractor.
GC-2
9/8/26, 5:20 PM Print - Specifications & Project Manual for Wakeman Farm Town Barn Town of Westport Request for Proposal #27-179T Electrical about:blank 32/66
00500
General conditions
8. Permits, ordinances, and regulations
Permits and licenses of a temporary nature necessary for the prosecution of the Work shall be secured and paid for by the Contractor. The Contractor will be required to obtain a Road Opening permit from the Town of Westport. All fees will be waived.
Permits, licenses and easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified. The Contractor shall give all notices and comply with all laws, ordinances, rules and regulations bearing on the conduct of the Work as drawn and specified.
9. Supervision by contractor
The Contractor will supervise and direct the Work.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .