Price Breakdown Worksheet (Blank).docx
DOCX document 25 KB Posted
- Attached to
- Z2DZ--Sources Sought Notice | Project#: 612A4-23-005 | Building 650 2nd & 3rd Floors Windows | Mather
- Solicitation number
- 36C26123R0016
About this file
This document includes a price breakdown worksheet template and solicitation for a construction project at the Sacramento VA Medical Center in Mather, California.
The solicitation is for a firm-fixed price construction contract to remove and replace windows on the second and third floors of Building 650. The project is a total SDVOSB set-aside. Offerors must be verified in VIP/SBA at the time of proposal submission and prior to award. The period of performance is 326 days after notice to proceed. Proposals are due to Rosario Chaidez at the Department of Veterans Affairs no later than March 15, 2023 at 2:00pm Pacific time. The price breakdown worksheet template separates estimated costs into material, labor, equipment, and other categories by construction division and totals for the project.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 36C26123R0016 Attachment - Price Breakdown
| DESCRIPTION |
| MATERIAL |
| LABOR |
| EQUIPMENT |
| OTHER |
| TOTAL |
Division 01 -General Requirements
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division Total |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division 02 – Existing Conditions |
| MATERIAL |
| LABOR |
| EQUIPMENT |
| OTHER |
| TOTAL |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division Total |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division 07 – Therm/Moisture Prot. |
| MATERIAL |
| LABOR |
| EQUIPMENT |
| OTHER |
| TOTAL |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division Total |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division 08 – Doors and Windows |
| MATERIAL |
| LABOR |
| EQUIPMENT |
| OTHER |
| TOTAL |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division Total |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division 12 - Furnishings |
| MATERIAL |
| LABOR |
| EQUIPMENT |
| OTHER |
| TOTAL |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| $ |
| Division Total |
| $ |
| $ |
| $ |
| $ |
| $ |
| SUB TOTAL |
| $ |
| $ |
| $ |
| $ |
| $ |
| Overhead |
| $ |
| $ |
| $ |
| $ |
| $ |
| Profit |
| $ |
| $ |
| $ |
| $ |
| $ |
| Bonds and Insurance |
| $ |
| $ |
| $ |
| $ |
| $ |
| TOTAL Proposal |
| $ |
| $ |
| $ |
| $ |
| $ |
NOTE: All other costs may be included as a separate item and shall be specified in this breakdown.