Presol Snug Harbor.pdf

PDF 246 KB Posted

Attached to
AK PFH 59(2), Snug Harbor Road Paving and Bike Lane, Phase 2
Solicitation number
69056720B000012
Issued by

About this file

This document outlines the scope of work for a federal construction project. The project involves road paving and bike lane construction along 0.5 miles of Snug Harbor Road near Cooper Landing, Alaska. Work includes excavation, grading, slope stabilization, retaining wall installation, and drainage structure rehabilitation. An estimated price range between $2-3 million is provided. The project is scheduled for completion in fall 2020. Required work is organized into standard construction divisions including earthwork, slope reinforcement, aggregate base courses, asphalt paving, drainage, erosion control, traffic control, and landscaping/turf establishment. The related federal contract opportunity lists the solicitation and agency details as the Alaska PFH 59(2), Snug Harbor Road Paving and Bike Lane, Phase 2 project through the Federal Highway Administration.

View the file

Other files

File Type Posted
AK PFH 59(2) Prelim Letter_10-Sept-2020.pdf PDF
af05902_Pre-Ad Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AK PFH 59(2), Snug Harbor Road Paving and Bike Lane, Phase II

The work consists of excavation grading, slope stabilization, retaining wall work and ditch reestablisthment.

Project length: .5 miles

Tentative Fixed Completion Date: Fall 2020

(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: Between $2,000,000.00 and $3,000,000.00

Location: 2 Miles S of Cooper Landing, Alaska

DESCRIPTION OF WORK IN US CUSTOMARY UNITS

FP-14

On e S ch ed ul e

Sc h

Na m e

DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance

(yes/no) Yes

154 Contractor Sampling & Testing (yes/no) Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes

157 Soil Erosion & Sediment Control (erosion control devices) Fiber Roll, check dams

158 Watering for Dust Control

DIVISION 200 – Earthwork

201 Clearing & Grubbing 3.7 acres 202 Additional Clearing & Grubbing (clearing & grubbing) ch ed ul e

Sc h

Na m e

203 Removal of Structures & Obstructions (structures, demolition) Riprap blanket removal

204 Excavation & Embankment 62,000 CUYDS

205 Rock Blasting: Controlled Blast Hole (rock blasting)

205 Blasting Consultant (Consultant/Engineering Services) (yes/no) No

207 Earthwork Geosynthetics

208 Structure Excavation

211 Roadway Obliteration

212 Linear Grading

213 Subgrade stabilization

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 Riprap 2,600 LNFT of ditch 252 Rockery, Special Rock Embankment, and Rock Buttress

253 Gabions & Revet Mattresses

255 Mechanically Stabilized Earth Walls (retaining walls) 2,200 SQFT.

256 Permanent Ground Anchors

(ground anchors)

257 Contactor-Designed Retaining Walls (contractor completed designs)

258 Reinforced Concrete Retaining Walls (retaining walls)

259 Soil Nail Retaining Walls

260 Rock Bolts & Dowels

261 Reinforced Soil Slopes

270 Compaction Grouting

271 Geotechnical Exploration ch ed ul e

Sc h

Na m e

273 Polyurethane Resin Injection (PUR)

274 Vibro Columns

275 Geofoam

DIVISION 300 – Aggregate and Base Courses

301 Untreated Aggregate Courses (crushed aggregate) 302 Minor Crushed Aggregate

303 Road Reconditioning

304 Full Depth Reclamation

305 Full Depth Reclamation With Cement

306 Full Depth Reclamation With Asphalt

307 Cement Treated Aggregate Course

309 Emulsified Asphalt Treated Base Course (crushed aggregate)

310 Cold In-Place Recycled Asphalt Base Course

311 Stabilized Aggregate Surface Course

312 Dust Palliative

313 Aggregate-Topsoil Course

314 Stockpiled Aggregates

DIVISION 400 – Asphalt Pavements & Surface Treatments

401 Asphalt Concrete Pavement By Gyratory Mix Design Method 403 Asphalt Concrete 160 ton

405 Open-Graded Asphalt Friction Course

406 Fog Seal ch ed ul e

Sc h

Na m e

407 Chip Seal

408 Cold Recycled Asphalt Base Course

409 Micro Surfacing

410 Slurry Seal

411 Asphalt Prime Coat (asphalt surface treatment)

412 Asphalt Tack Coat (asphalt surface treatment)

413 Asphalt Pavement Milling

414 Asphalt Pavement Crack Sealing & Filling

415 Paving Geotextiles

418 Asphalt Concrete Pavement Patching

429 Bonded Wearing Course

DIVISION 500 – Rigid Pavement

501 Minor Concrete Pavement

502 Concrete Pavement Restoration

DIVISION 550 – Bridge Construction

551 Driven Piles

552 Structural Concrete (concrete – major structures)

553 Prestressed Concrete

554 Reinforcing Steel

555 Steel Structures (structures, steel)

556 Bridge Railing

557 Timber Structures (structures, timber) ch ed ul e

Sc h

Na m e

558 Dampproofing

559 Waterproofing (concrete – major structures)

560 Removal of Concrete By Hydrodemoltion

561 Structural Concrete Injection & Crack Repair

562 Temporary Works

563 Painting (structures, painting)

564 Bearing Devices

565 Drilled Shafts

566 Shotcrete

567 Micropiles

568 High Performance Concrete

569 Concrete Overlays For Bridge Decks

574 Geosynthetic Reinforced Soil Integrated Bridge System

575 Minor Bridge Work

576 Pile Encapsulation

577 Plastic Structures

580 Alternate Bridge

582 Helical Piles

DIVISION 600 – Incidental Construction

601 Minor Concrete Structures (concrete – minor structures)

602 Culverts & Drains (indicate one or both)

603 Structural Plate Structures (culverts & drains)

604 Manholes, Inlets, & Catch Basins(culverts & drains) (indicate which) ch ed ul e

Sc h

Na m e

605 Underdrains, Sheet Drains & Pavement Edge Drains (culverts & drains) (indicate which) 2,700 LNFT

606 Corrugated Metal Spillways

607 Cleaning, Relaying, & Repairing Existing Drainage Structures

608 Paved Waterways (culverts & drains)

609 Curb & Gutter (concrete – minor structures) (indicate which)

610 Horizontal Drains

611 Water Systems

612 Sanitary Sewer Systems

613 Simulated Stone Masonry Surface (concrete – minor structures)

614 Lean Concrete Backfill

615 Sidewalks, Pads & Paved Medians

(concrete – minor structures)

616 Slope Paving

617 Guardrail

618 Concrete Barriers & Precast Guardwalls

619 Fences, Gates, Cattle Guards & Bollard Posts 130 LNFT

620 Stone Masonry

621 Monuments & Markers (construction survey & staking) (yes/no) No

622 Rental Equipment (yes/no) Yes

623 General Labor (yes/no) Yes

624 Topsoil (landscaping & related items) 24,000 SQYD.

625 Turf Establishment

(indicate seeding or mulching separately) 24,000 SQYD.

626 Plants, Trees, Shrubs, Vines & Groundcovers ch ed ul e

Sc h

Na m e

627 Sod

629 Rolled Erosion Control Products & Cellular Confinement Systems (turf establishment) 24,000 SQYD.

633 Permanent Traffic Control (traffic control devices)

634 Permanent Pavement Markings (traffic pavement markings)

635 Temporary Traffic Control – Flagger 2,500 hours

635 Temporary Traffic Control – Pilot Car 850 hours

635 Temporary Traffic Control – All Req’d

636 Traffic Signal, Traffic Counter, Lighting, & Electrical Systems

637 Facilities & Services (field offices, laboratories, & housing)

645 Locating Utilities

646 Roadside Development (use pay item description)

647 Environmental Mitigation (use pay item description)

650 Temporary Diversions

651 Rockfall Protection

DIVISION 200 – Earthwork
DIVISION 250 – Slope Reinforcement and Retaining Walls
DIVISION 300 – Aggregate and Base Courses
DIVISION 400 – Asphalt Pavements & Surface Treatments
DIVISION 500 – Rigid Pavement
DIVISION 550 – Bridge Construction