Preliminary Results~31.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Public Notice Cooperative Purchase
- Solicitation number
- S-P34048-00005751
- Issued by
- Washington County, Barlow City, Oregon
About this file
This file is a preliminary results spreadsheet related to a cooperative purchase procurement conducted by the Beaverton School District in Oregon through OMNIA Partners, Region 4 Education Service Center Cooperative Contract. The procurement seeks to acquire band instruments and related services for the school district, with Music & Arts identified as the primary vendor. The estimated contract value is $975,000. The public notice established a protest deadline of February 16, 2023, for affected parties to submit written objections to the procurement method. The documentation does not provide specific details regarding quantities of individual instruments, response dates, bidder conferences, site visits, or contract term and renewal options.
The procurement utilizes Oregon's cooperative purchasing regulations, which allows public entities to leverage existing contract vehicles for efficient purchasing. No specific information is documented regarding pricing structures, set-aside designations, disadvantaged enterprise requirements, incumbent vendors, or funding sources. The cooperative procurement approach indicates an open and competitive process conducted under established cooperative contracting frameworks. The procurement jurisdiction covers Washington County and Barlow City in Oregon, with the Beaverton School District serving as the primary procuring agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Public Notice Cooperative Purchase.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| PRELIMINARY RESUTS S-73000-00005752 | ||||||||
| Bidder name: | LTM, Incorporated dba Knife River Materials | Freedom Builders | ||||||
| City, State: | Roseburg, OR | Azalea, OR | ||||||
| Item | Description | Unit | Est. Qty | Unit Price | Total | Unit Price | Total | |
| 1 | MOBILIZATION | LS | 1 | 29,833.00 | $29,833.00 | 62257 | $62,256.70 | |
| 2 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | LS | 1 | 12,500.00 | $12,500.00 | 7500 | $7,500.00 | |
| 3 | EROSION CONTROL | LS | 1 | 500.00 | $500.00 | 1500 | $1,500.00 | |
| 4 | POLLUTION CONTROL PLAN | LS | 1 | 500.00 | $500.00 | 1500 | $1,500.00 | |
| 5 | CONSTRUCTION SURVEY WORK | LS | 1 | 11,000.00 | $11,000.00 | 8000 | $8,000.00 | |
| 6 | ASPHALT PAVEMENT SAW CUTTING | FOOT | 290 | 8.00 | $2,320.00 | 6 | $1,740.00 | |
| 7 | GENERAL EXCAVATION | LS | 1 | 14,000.00 | $14,000.00 | 18350 | $18,350.00 | |
| 8 | SUBGRADE GEOTEXTILE | SQYD | 120 | 10.00 | $1,200.00 | 8 | $960.00 | |
| 9 | 24 INCH STORM SEWER PIPE, 5 FT DEPTH | FOOT | 27 | 250.00 | $6,750.00 | 200 | $5,400.00 | |
| 10 | PAVED CULVERT END SLOPES | SQFT | 37 | 23.00 | $851.00 | 50 | $1,850.00 | * |
| 11 | CONCRETE MANHOLES, SHALLOW | EACH | 1 | 2,200.00 | $2,200.00 | 4000 | $4,000.00 | |
| 12 | EXTRA FOR MANHOLES OVER EXISTING SEWERS | EACH | 1 | 2,200.00 | $2,200.00 | 2000 | $2,000.00 | |
| 13 | COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEP | SQYD | 3200 | 10.80 | $34,560.00 | 12 | $38,400.00 | |
| 14 | AGGREGATE BASE | TON | 140 | 175.00 | $24,500.00 | 55 | $7,700.00 | |
| 15 | LEVEL 3, 1/2 INCH ACP MIXTURE | TON | 420 | 157.20 | $66,024.00 | 200 | $84,000.00 | |
| 16 | CONCRETE CURBS, CURB AND GUTTER | FOOT | 120 | 53.00 | $6,360.00 | 40 | $4,800.00 | |
| 17 | CONCRETE CURBS, STANDARD CURB | FOOT | 150 | 48.00 | $7,200.00 | 30 | $4,500.00 | |
| 18 | CONCRETE ISLANDS | SQFT | 85 | 16.00 | $1,360.00 | 22 | $1,870.00 | |
| 19 | CONCRETE WALKS | SQFT | 620 | 12.00 | $7,440.00 | 9 | $5,580.00 | |
| 20 | GROUTED ROUND ROCK | SQFT | 860 | 23.00 | $19,780.00 | 30 | $25,800.00 | |
| 21 | EXTRA FOR NEW CURB RAMPS | EACH | 6 | 980.00 | $5,880.00 | 600 | $3,600.00 | |
| 22 | TRUNCATED DOMES ON NEW SURFACES | SQFT | 120 | 45.00 | $5,400.00 | 30 | $3,600.00 | |
| 23 | TRUNCATED DOMES ON EXISTING SURFACES | SQFT | 37 | 55.00 | $2,035.00 | 40 | $1,480.00 | |
| 24 | BI-DIRECTIONAL YELLOW TYPE IAR MARKERS | EACH | 10 | 60.00 | $600.00 | 50 | $500.00 | |
| 25 | BI-DIRECTIONAL YELLOW TYPE IAR MARKERS, RECESSED | EACH | 15 | 350.00 | $5,250.00 | 30 | $450.00 | |
| 26 | PERMANENT SURFACE MOUNTED TUBULAR MARKERS | EACH | 6 | 300.00 | $1,800.00 | 150 | $900.00 | |
| 27 | THERMOPLASTIC, SPRAYED, SURFACE, NON-PROFILED | FOOT | 1800 | 4.30 | $7,740.00 | 4 | $7,200.00 | |
| 28 | PAVEMENT LEGEND, TYPE AB: ARROWS | EACH | 2 | 300.00 | $600.00 | 600 | $1,200.00 | |
| 29 | PAVEMENT BAR: TYPE B-HS | SQFT | 200 | 22.00 | $4,400.00 | 15 | $3,000.00 | |
| 30 | REMOVE EXISTING SIGNS | LS | 1 | 300.00 | $300.00 | 500 | $500.00 | |
| 31 | REMOVE AND REINSTALL EXISTING SIGNS | LS | 1 | 500.00 | $500.00 | 2500 | $2,500.00 | |
| 32 | WOOD SIGN POSTS | FBM | 270 | 20.00 | $5,400.00 | 30 | $8,100.00 | |
| 33 | SIGNS, STANDARD SHEETING, SHEET ALUMINUM | SQFT | 101 | 50.00 | $5,050.00 | 30 | $3,030.00 | |
| 34 | REMOVAL OF ELECTRICAL SYSTEMS | LS | 1 | 2,500.00 | $2,500.00 | 13000 | $13,000.00 | |
| 35 | FLASHING BEACON INSTALLATION, NORTH UMPQUA HWY. AT SCHOOL ENTRANCE | LS | 1 | 38,000.00 | $38,000.00 | 34424 | $34,423.60 | |
| 36 | MULTIPLE MAILBOX SUPPORTS | EACH | 2 | 1,150.00 | $2,300.00 | 1200 | $2,400.00 | |
| BID TOTAL | $338,833.00 | $373,590.30 | ||||||
| *Calculation on Bid Pricing form was incorrect. |