This document provides details for a federal contract opportunity to perform road work on Ochoco Ranger Station Road in Oregon. The solicitation number is 69056722B000009 and is being issued by the Department of Transportation Federal Highway Administration for work that includes hot asphalt concrete, shoulder aggregate, asphalt milling, raising existing guardrail, new guardrail terminals, striping, and temporary traffic control. The opportunity type is listed as Pre-Solicitation, and the description provided indicates the work consists of an asphalt overlay on Crook County Route 123(1).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Project Description.pdf | ||
| Prelim Letter_Ochoco Ranger Station Road Overlay Project.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL HIGHWAY ADMINISTRATION
U. S. DEPARTMENT OF TRANSPORTATION
Project Location
Projects, FP-14 US Customary Units of Roads and Bridges on Federal Highway
Standard Specifications for Construction
APPROVED:
DATE
TYPE OF CONSTRUCTION:
SPECIFICATION:
PROJECT MANAGER
PLANS FOR PROPOSED PROJECT
R
E N
O R
A I
N
N
ST F
R
I
D
D E P A
T
NTOFT A SP
T T
O
U
TE
ATESO
AM
E R
IC
A
M
N
Craig Sanders
Western Federal Lands Highway Division
Chief of Engineering, OREGON
CROOK COUNTY,
ROAD OVERLAY PROJECT
OCHOCO RANGER STATION
and pavement markings.
Paving, guardrail, OR FLAP CROOK 123(1)
PROJECT SITE
SEE VICINITY MAP
Scale in miles
43210
A.1
A.3
TITLE SHEET
PLAN SYMBOLS AND ABBREVIATIONS
A. GENERAL INFORMATION
INDEX TO SHEETS
VICINITY MAP
C.1 TYPICAL SECTIONS
E.1
A.2
D. SITE PLAN
E. DETAILS
APPROACH ROAD
C. TYPICAL SECTIONS
PLANS PREPARED BY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
VANCOUVER, WASHINGTON
WESTERN FEDERAL LANDS HIGHWAY DIVISION
COMMITMENT TO EXCELLENCE
FEDERAL LANDS HIGHWAY
E.3-6GUARDRAIL STANDARD DRAWINGS
F. TEMPORARY TRAFFIC CONTROL
F.2-6TEMPORARY TRAFFIC CONTROL DETAILS
D.2 SITE PLAN
P A
C F
I C
I O
E C
A N
C
OLUMBIA R
IV
ER
S N
A K
E R I V
E R
Lake
Malheur Lake
Harney
Lake
Summer
D E S
C H
U T
E S
R I
V E
R
Lake
Klamath
Upper
Abert
Lake
LAKE N.P.
CRATER
REFUGE
WILDLIFE
NATIONAL
MALHEUR
RANGE
ANTELOPE
NATIONAL
HART MT.
20 20
395197
Ashland
Roseburg
EUGENE
Bend
Corvallis
Newport
SALEM
PORTLAND
Astoria
Pendleton
La Grande
Ontario
Burns
Falls
Klamath
Bend
North
City
Baker
Dalles
The
WASHINGTON
I D
A H
O
NEVADACALIFORNIA
OREGON KEY MAP
Grants Pass
MEDFORD
G. PERMANENT TRAFFIC CONTROL
G.2-3PERMANENT TRAFFIC CONTROL DETAILS
LENGTH 8.12 MILES
DESIGN DESIGNATION
Match existinge (max)
55 mphV
2182ADT (2043)
1281ADT (2023)
T O M I T C
H E L L
WILDERNESS
MILL CREEK
TO PRINEVILLE
FOREST
NATIONAL
OCHOCO
ASPHALT PAVEMENT CRACK SEALING AND FILLINGC.2
FIBER ROLL DETAILD.3
A.1
STATE PROJECT
NUMBER
SHEET
:3
M
A u g u s t
S h e e t
.1 c p w w o r k
\d
\O R
C R
O O
K p ln g e n a a
.d g n
OR FLAP CROOK 123(1)
/2
/2
C h e c k e d b y
R o n L a r s o n
D e s ig n e d b y
K a it ly n
D o r r
PRELIMINARY - N
OT FOR CONSTRUCTION
BH TP
CUYD
culv.
CUFT
cubic yard(s) culvert cubic foot (feet) mon.
min.
MGAL
max.
matl.
M.P.
M.L.
monument minimum thousand gallon maximum material mile post main line
W
RIP
DI
G W G WV
CP GPS
36 31
36 31
N
E
N 1000
TP
SEC.
SEC.
NO SCALE
θs Ø ∆c spiral central angle diameter curve central angle total central angle approach ahead average daily traffic abutment appr.
AH
ADT
abut.
between bearing bridge balance point bench mark back face back btwn brg.
br.
BP
BM
b.f.
BK
ctrs.
CS
cont.
constr. jt.
conn.
conc.
col.
CMP
clr.
cc or c. to c.
centers point of curve to spiral continuous construction joint connection concrete column corrugated metal pipe clear centerline center to center
NOTE:
1.
on the appropriate plan sheet.
Other symbols used in the plans will be shown in a legend
W west drwg(s).
dist.
diaph.
dia.
DHV
D exp. jt.
exc.
EW
EQ or eq.
EOP
emb.
elev.
El. 94.16 e.f.
e E expansion joint excavation edge of water equation edge of pavement embankment elevation elevation in feet each face superelevation rate east drawing(s) distance diaphragm diameter design hourly volume diameter galv.
ga.
galvanized gage (gauge) jt.
IE
ID
joint invert elevation inside diameter ftg.
flg.
fin.
f.f.
footing flange finish front face
LW
lt. or LT Ls
LPSM
long.
LNFT
lat.
L low water left length of spiral lump sum longitudinal linear foot (feet) latitude length of curve rte.
rt. or RT reqd.
reinf.
rdwy.
R/W R.
R route right required reinforcement roadway right-of-way range radius typ.
Ts
TS
thd.
TBM
T.
T typical tangent distance (spiraled curve) point of tangent to spiral thread temporary bench mark township tangent distance
VPI
vph V vertical point of intersection vehicles per hour design speed (velocity)
STS
struc.
stiff.
stgr.
std.
STA, Sta.
ST
SS
SRS
SQYD
SQFT
spa.
SLRY
shldr.
sect.
SC
SADT
S point of spiral to tangent spiral structural stiffener stringer standard station point of spiral to tangent point of spiral to spiral (no curve) point of spiral to reverse spiral square yard square foot spacing, spaces or spaced slurry unit shoulder section point of spiral to curve seasonal average daily traffic south
KSI
square inch thousand pounds per pvmt.
PT
PST
PSC
PSI
PSF
PS
POT
POS
POC
pl.
PI
PCS
PCC
PC
pavement point of tangent point of spiral to tangent point of spiral to curve pounds per square inch pounds per square foot point of tangent to spiral point on tangent point on spiral point on curve plate point of intersection point of curve to spiral point of compound curve point of curve
OHWM
OG
OD
o. to o.
o.c.
ordinary high water mark original ground outside diameter out to out on center
NC
N normal crown north
A A
DI
National Boundary
State Boundary
County Boundary
City Boundary
Township or Range Line
Section Line
Section Corner (Found, Projected)
Control Point (Terrestrial and GPS)
Gas & Water Meter; Gas & Water Valve
Flagpole; Fire Hydrant
Cooking Grate; Garbage Can; Picnic Table
Boulder; Well; Antenna; Grave
Above Ground Tank; Underground Tank
Spot Elevation; Coordinate Grid Tick
Material Source; Bore Hole; Test Pit
Treeline; Individual Trees
Spring or Seep
Section Line 4
Section Corner (Found, Projected) 4
Section Line 16
Section Corner (Found, Projected)16
Property Line
Parcel Number
National Park Boundary
National Forest Boundary
National Wildlife Refuge Boundary
BLM Lands Boundary
Indian Reservation Boundary
Existing Roadway (Paved, Gravel)
Railroad
Trail
Fiber Roll
Silt Fence
Sandbag
Intermittent Drainage or Small Creek
Large Creek or River
Lake, Pond or Reservior; Marshland
North Arrow
Slope Stake Limits Top of Cut
Toe of Fill
Construction Limits
Bottom of Ditch
Fence
Gate with Fence
Cattleguard
Guardrail
Concrete Barrier and Guard Wall
Retaining Wall wall face
Signs (single, double post; portable)
Delineators
Pipe Culvert (arrow shows flow)
Pipe Culvert with End Section
Pipe Culvert with Headwall
Pipe Culvert with Drop Inlet
Box Culvert
Underdrain
Overhead/Above Ground Utilities
Underground Utilities
Light, Support w/Anchor) Poles (Power, Telephone, Joint Use, Miscellaneous Utility Features
Building
Right-of-Way Line
Permanent Easement
Construction Easement
Riprap
- no symbol -
Section A-A
EXISTING PROPOSED
STEAM = steam, T = telephone, TV = CATV, W = water P = power, SA = sanitary sewer, SD = storm drain, SS = storm sewer, FM = force main, FO = fiber optic, G = gas, IRR = irrigation, O = oil, UP = transformer or junction box, WF = water fountain EM = electric meter, TP = telephone pedestal, TV = CATV pedestal,
- no symbol -
11/2001 DETAIL APPROVED FOR USE
6/2022
10/2014 10/2009 1/2007 9/2005 REVISED: 101-1W
WFLHD DETAIL
ABBREVIATIONS
PLAN SYMBOLS AND
:5 u g u s t
D e t W
-1 p w
-w o rk \d
\W
-1
.d g n
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
NUMBER
SHEET
BEGIN PROJECT
E. 4905032.2709 N. 975005.4217
880+50
END PROJECT
E. 4940436.1224 N. 994824.3395
1309+00
U S -2
Scale in miles
N
STATION
OCHOCO RANGER
FOREST
NATIONAL
OCHOCO
32 33 34 35
87 9
T13S
T14S
T13S
T14S
R
E
R
E
R
E
R
E
R
E
R
E
R
E
R
E
STATE PROJECT
NUMBER
SHEET
VICINITY MAP
:0
A u g u s t c p w w o r k
\d
\O R
C R
O O
K p ln g e n a a
.d g n /2
/2
R o n L a rs o n
C h e c k e d b y
D e s ig n e d b y
K a it ly n
D o r r
A.4FLAP CROOK 123(1)OR
12' 12'1' 1'
CL
Existing ground
Match existing slope Match existing slope
Tack Coat
OCHOCO RANGER STATION ROAD TYPICAL
880+50 to 1309+00 shoulder finishing
Roadway aggregate, (Type I smoothness)
2-inch compacted depth
0.3 to <3 million ESAL nominal mazium size aggregate
Gyratory mix, 1/2-inch or 3/4-inch
Asphalt concrete pavement, Existing asphalt concrete pavement
NOTE:
1. See Section E for guardrail locations and details.
STATE PROJECT
NUMBER
SHEET
TYPICAL SECTION
:0
A u g u s t c p w w o r k
\d
\O R
C R
O O
K p ln ts c c
.d g n /2
/2
R o n L a rs o n
C h e c k e d b y
D e s ig n e d b y
K a it ly n
D o r r
C.1FLAP CROOK 123(1)OR
Greater than 1"
CRACK SEALING AND FILLING
existing surface.
4. Force crack repair material into cracks to ensure adhesion to
3. Seal and fill cracks at locations designated by the CO.
other methods approved by the CO.
2. Remove existing sealant from cracks to be filled by routing or cracks.
Follow manufacturer's recommendations for sealing and filling
1. Prepare cracks for sealing and filling according to Section 414.
NOTE:with existing surface
Strike off material to flush flush with the existing surface
Ensure all remaining overband is
414.06(a) and 712.01(a)(1) crack sealant. See Subsections
Seal crack with hot applied
CRACK SEALING CRACK FILLING
" to 1"4 with existing surface. See Subsection 414.06(b).
Fill crack with pre-formulated mastic material flush
STATE PROJECT
NUMBER
SHEET
CRACK SEALING AND FILLING
ASPHALT PAVEMENT 1
:0 u g u s t c p w w o r k
\d
\O R
C R
O O
K p ln ts c
.d g n /2
/2
R o n L a rs o n
C h e c k e d b y
D e s ig n e d b y
K a it ly n
D o r r
C.2FLAP CROOK 123(1)OR
STATE PROJECT
SHEET
SITE PLAN
:0
A u g u s t c p w w o r k
\d
\O R
C R
O O
K p ln lg d d
.d g n
/2
/2
R o n L a rs o n
C h e c k e d b y
D e s ig n e d b y
K a it ly n
D o r r
D.2FLAP CROOK 123(1)OR
BEGIN PROJECT
E. 4905032.2709 N. 975005.4217
END PROJECT
E. 4940436.1224 N. 994824.3395
RANGER
OCHOCO
S
TATI
O N
R O
A D
Scale in miles
N
Guardrail Site 01
Guardrail Site 02 Guardrail Site 03
Guardrail Site 05
Guardrail Site 04
Approach 1
Approach 2
Approach 4 Approach 5
Approach 8
Approach 10
Approach 11
Approach 12
Approach 14
Approach 17
Approach 18
Approach 20
Approach 21
Approach 3 Approach 6
Approach 9
Approach 7
Approach 13
Approach 16
Approach 19
Approach 15
1. Se Section E for guardrail and approach details
NOTE:
NO SCALE
Spacing Slope
STAKES REQUIRED
1:1
1:2
1:3
1:4 or flatter for each roll
Stakes required
FIBER ROLL SPACING
Fiber roll length
DRAFT: 7/2016
REVISED:
DETAIL APPROVED FOR USE 10/2014
WESTERN FEDERAL LANDS HIGHWAY DIVISION
FIBER ROLL
(FT)
(FT)
W157-21
U.S. CUSTOMARY DETAIL
DETAIL
STATE PROJECT
U.S. DEPARTMENT OF TRANSPORTATION
U S
C c m y fi le s p w p r o d u c ti o n d m s
W .d g n
J u ly
Fl ow
T o e o f fi ll s lo p e
ELEVATION
PLAN
disturbed areas
Runoff from
INSTALLATION BEYOND TOE OF SLOPE
INSTALLATION ALONG SLOPES
FIBER ROLL STAKING DETAIL
PROPERLY STAKED AND ENTRENCHED FIBER ROLL
Existing ground (typ.)
Fiber roll
Flow direction
Slope
Direction of runof f from distur bed area s sp ac in g ch ar t
S ee F ib er R ol l
Fiber roll ff o n ur f o n oi t c er i
D along contours
Install fiber rolls
Fiber roll
Slope
Fi ll slo pe
Direction of runoff ground
Existing soil to match ground level
Backfilled and compacted
Flow larger than fiber roll wood stakes. See Note 2.
Pay lim its
Pay lim its
SLOPE PROTECTION INSTALLATION
ALTERNATE FIBER ROLL JOINT DETAIL
FIBER ROLL LAPPING DETAIL
on uphill side of fiber roll
Place excavated material Stagger joints (typ.)
2.
1.
permanent installations. Do not crush fiber roll while staking.
roll is secure to slope. Live stakes may be used for and install fiber rolls
Step 1: Excavate trench Step 2: Backfill soil against fiber rolls
2" (min.) Excavate trench 2"
1" x 1" or 1" Ø ove rlap
12" (m in.)
t o m in m in
1" x 1" Wood stake as specified in plans
3' min. or
3' (min.)
Drive stakes at each end and at 4-foot spacing until fiber fiber roll and space stakes at 4-foot max.
6-inches from fiber roll end angles towards the adjacent
Overlap fiber rolls 12-inch minimum. Drive stakes at
NOTE:
E.1
STATE PROJECT
NUMBER
SHEET
D e f a u lt p w w o r k
\d
\O R
C R
O O
K p ln m is c e e
.d g n
OR FLAP CROOK 123(1)
:3
A u g u s t
/2
/2
C h e c k e d b y
R o n
L a r s o n D e s ig n e d b y
K a it ly n
D o r r
APPROACH ROAD
Width30 ft. typ.
ROAD
of pavement
Existing edge
Width20 ft. typ.
of pavement
Existing edge
DRIVEWAY
R=match existing
R=match existing.
nominal maximum size aggregate, 0.3 to <3 million ESAL
Asphalt concrete pavement,Gyratory mix 1/2-inch OR 3/4-inch pavement, type 1 2-inch compacted depth
Roadway aggregate, method 1 or asphalt concrete
For details, see Sheet E.5
Overlay EP to 2" at sawcut.
Approach Location table.
Sawcut for milling as noted in
Existing pvmt.
Asphalt concrete pavement milling, 0 - 2" depth
Project paving limit
AT PROJECT PAVING LIMITS
ASPHALT CONCRETE PAVEMENT
2-inch compacted depth
Asphalt concrete pavement, type 1 200' taper (1" per 100') on highway
*30' taper on road approach
Match existing grade
Existing pvmt.
5.
4.
3.
2.
1.
Case 1: Overlying material Case 2: Overlying material between drilled holes
Excavate area between drilled holes
Excavate area
Overlying material Overlying material
Rock material Rock material backfill or overlying material
Crushed coarse aggregate backfill or overlying material
Crushed coarse aggregate aggregate backfill
Crushed coarse aggregate backfill
Crushed coarse
Finished gradeFinished grade depth (A) is 18" or less depth (A) is greater than 18"
NOTE:
the base metal with two coats of zinc-oxide paint.
Treat field cut galvanized steel post surfaces that expose requirements in Section 617.
Place crushed coarse aggregate according to the post underdrain pipe with geotextile" in Section 703.
"coarse aggregate for concrete" or "granular backfill for
Use crushed coarse aggregate backfill that conforms to oblong hole configuration for Case 1 conditions.
Unless otherwise specified, use either the circular or the
Use this standard when posts cannot be embedded to the
ELEVATION
PLAN VIEWPLAN VIEW
ELEVATION
Steel Post
Wood Post
Wood Post
Steel Post
POST EMBEDMENT DIMENSIONS
B A
E m b e d m e n t D e p th
B A
E m b e d m e n t D e p th
23"
23"
21"
21"
12"
8"
617-31 or 617-32.
minimum depth shown on Standard 617-10, 617-11, f o r
M G
S f o r G f o r
M G
S f o r G
21" or 23" 8" or 12"
DEPTH
EMBEDMENT
Case 1
Case 2
DEPTH (B)
DRILLING
MATERIAL (A)
OVERLYING
TYPE
HOLE
42”
30" to 42”
24" to 42”
> 30”
> 18" to 30”
0 to 18”
42" - A
12”
24”
6/2022 STANDARD APPROVED FOR USE
REVISED: 617-13
INSTALLATION IN ROCK
W-BEAM GUARDRAIL
MGS AND G4
:5
J u ly
S td p w
-w o rk
\d \S td -1
.d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
STATE PROJECT
6.
5.
4.
3.
2.
1.
embankment
Edge of widened post section. See Note 4 face of the rail in the standard
Tangent line projected from the embankment
Edge of widened post section. See Note 4 face of the rail in the standard
Tangent line projected from the
Varies by manufacturer end of terminal not shown.
Terminal posts and
Varies by manufacturer end of terminal not shown.
Terminal posts and
NOTE:
terminal grading extents where practical.
Construct a 1V:4H slope outside of the guardrail terminal.
Install a reflectorized object marker on the end of the according to the manufacturer's recommendations.
end farther from the edge of shoulder, or use a taper
Install terminal at a 1:25 taper or flatter to position the the manufacturer's recommendations.
necessary to install the tangent terminal according to manufacturer for a specific product. Adjust grading as begin at post 3. Verify the length of need with the
For design purposes, the length of need is assumed to of site limitations, use the alternative grading layout.
as practical within site constraints. If necessary because are provided, use the preferred grading layout as much staking notes or model. If no staking notes or model
Construct the terminal grading layout as shown in the other details.
recommendations. See manufacturer's drawings for
Install tangent terminal according to the manufacturer's
See Note 6
Guardrail terminal grading o r f la tt e r
V
:1
H
Front of rail face
PLAN
PREFERRED GRADING
Post section
Standard
L
See Note 6
Guardrail terminal grading o r f la tt e r
V
:1 H
Hinge point line
See Note 3
Length of Need
Guardrail system
Pay limits
Pay limits terminal section type tangent or type MGS tangent
Back of post
Back of post
Front of rail face
Hinge point line
PLAN
ALTERNATIVE GRADING
post section
Standard
Guardrail system
Pay limits
Pay limits terminal section type tangent or type MGS tangent
See Note 3
Length of Need
12'-6"
(min.)
10'-0" m in m in m in
12'-6" m in
TEST LEVEL
L
50 (for MGS)
37.5 or 50 (for G4)
(FT)
3 (> 45 mph)
2 (≤ 45 mph)
6/2022 REVISED: 617-20
AND GRADING
TYPE TANGENT TERMINAL
W-BEAM GUARDRAIL
MGS AND G4
6/2005 STANDARD APPROVED FOR USE
:2
J u ly
S td
-2 p w
-w o rk
\d \S td -2
.d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
STATE PROJECT
guardrail post bolt
3" x 4" (min.)
NOTE:
fill slope
Variable
TOP
symmetry of�
FRONTSIDE SIDE
TOP
PLAN VIEW
BLOCK
steeper than fill slope Variable slope but not
W beam rail
(See Note 2) Modified Block on terminal sections All posts except those
DETAIL
POST AND BLOCK
4.
3.
2.
1.
SHAPE POST
STRUCTURAL
Note 4 See terminal sections approach and departure Widening required for Subgrade shoulder.
TYPICAL GUARDRAIL ELEVATION OMITTED POST DETAIL
See Note 1
POST FACE
terminal sections approach and departure Widening required for Subgrade shoulder.
Hinge point Hinge point
1V:2H or flatter slope shown on Typical Section Aggregate base or as groundline at face of rail Edge of pavement or
1V:10H or flatter slope block (typ.)
Post and rail as applicable ground line at face of Edge of pavement or splice Mid-span
See Note 2
See Note 2
TYPICAL GUARDRAIL CROSS SECTION TYPICAL GUARDRAIL CROSS SECTION
o s t le n g th
P o s t le n g th
GUARDRAIL MOUNT
FLEXIBLE DELINEATOR
1V:10H or flatter slope groundline at face of rail Edge of pavement or shown on Typical Section Aggregate base or as terminal sections approach and departure Widening required for Subgrade shoulder.
1V:2H or flatter slope
Hinge point shown on Typical Section Aggregate base or as
1V:10H or flatter slope
TYPICAL GUARDRAIL CROSS SECTION
manufacturer's recommendations.
an adhesive or mechanical means according to the Fasten delineator to the web of the steel post using either Install a flexible hinged delineator every fourth post.
practices.
part, including its appearance, and accepted manufacturing to be those consistent with the proper functioning of the Dimensional tolerances not shown or implied are intended consistent material throughout the length of guardrail run.
may be wood, plastic, or composite material. Use Size of block shown elsewhere on the plans. Modified block guardrail post and the hinge point. For all other locations, be omitted in locations where the typical guardrail cross When encountering impenetrable material, one post may
Traffic
(one omitted post) Unsupported span
(max.)
Note 2 See
N o te
S e e sheeting Retroreflective
Note 2
See
" x 10" or 14" guardrail bolt8
(ty p.)
6"
8" or 12"
(t y p
" dia. (typ.)4
" plain round washer4
" recess nut8
6"
"4
" dia.4
W6 x 9 or W6 x 8.5
8" or 12"
"4 o r
6"
"4
5" (max.)
see Section 617 and Standard 617-13 or 617-37.
section includes 2-feet (min.) between the back of the
8" or 12" block
6' Post 8' Post
8" Block
8' POST ON SLOPE, 8" BLOCK6' POST CENTERED ON HINGE, 8" OR 12" BLOCK
56'-3" (min.) Distance between omitted posts
43'-9" (min.)
12'-6" bolts and nuts (8 per splice)
" guardrail splice4 1" x 18
5 Post spacing 6'-3""2 13'-1
6' Post
6' POST, 8" OR 12" BLOCK
(typ.)
2'-0"
8" or 12" block
(t y p
" x 10" or 14"8
Lap in direction of traffic
REVISED: 617-32
STEEL POSTS
MGS W-BEAM GUARDRAIL
7/2022 STANDARD APPROVED FOR USE
:3
J u ly
S td
-3 p w
-w o rk
\d \S td -3
.d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
STATE PROJECT
NOTE:
SPAN WITH HEADWALL DETAIL
WOOD POST DETAIL STEEL POST DETAIL CRT POST DETAIL
PLAN
ELEVATION
Finished grade
PLAN VIEW
See Note 1
POST AND
BURIED OBSTRUCTION
BURIED OBSTRUCTION
See Note 3 See Note 3
Hinge point line
Rail splice (typ.)
(no nesting required)
Single W-beam rail element
Slope varies
Slope varies
Slope varies the face of the headwall flush (zero offset) with
Back of post may be See Note 4
Headwall the face of the headwall flush (zero offset) with
Back of post may be
Hinge point line
CRT WOOD POST
FRONT SIDE
TOP
the maximum height of the culvert headwall above the the finished grade to act as a vertical roadway curb, In locations where the culvert headwall extends above upstream and downstream of posts 2 and 7 is
The minimum length of guardrail, including the end terminals, Use wood posts for CRT posts.
Posts 1 and 8 may be wood or steel.
5.
4.
3.
2.
1.
See Note 1
POST AND
See Note 2
POST AND
12" (min.)12" (min.)
8"
24"
6"
24"
12"
8"
24" hole (typ.)
" dia.2
8"
" dia.4
6"
6"
See Standard 617-31 or 617-32 for other assembly details.
finished grade is 2-inches.
62.5-feet.
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
2 3 4 5 6 7 8
8 1 8 2 7 or 25'-0" (3 omitted posts)
18'-9" (2 omitted posts)
6'-3"
REVISED:
617-37
LONG-SPAN SYSTEM
MGS W-BEAM GUARDRAIL
:5
J u ly
S td p w w o r k
\d
\S td
.d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
STANDARD APPROVED FOR USE 7/2022
STATE PROJECT
ROAD WORK
END
WORK
ROAD
AHEAD
ROAD NAME
WORK
ROAD
AHEAD
ROAD WORK
END
WORK
ROAD
xxxxx
WORK
ROAD
xxxxxxx
ROAD WORK
NEXT xx MILES
WORK
ROAD
AHEAD
xx
MPH
ROAD NAME
ROAD WORK
END
WORK
ROAD
xxxxxxx
ROAD WORK
END
xx
MPH
WORK
ROAD
xxxxxxx
ROAD WORK
NEXT xx MILES
13.
12.
11.
10.
9.
8.
7.
6.
5.
4.
3.
2.
1.
ROAD TYPE
DISTANCE BETWEEN
A B C
NOTE:
M in o r R o a d
M a jo r R o a d
B as de ter mi ne d b y t he C
O
Wor k z on e A re a o f I nfl ue nc e
(S ee S ign S pa cin g T ab le)
ADVANCE W
ARNI
NG
AREA
(S ee S ign S pa cin g T ab le)
ADVANCE W
ARNI
NG
AREA
A
B
C
A
A
A
A
Pr oje ct Lim its
See Note 8 W16-8P W20-1 over
W20-1
G20-2
See Note 9 W20-1
See Note 9 W20-1
(optional) W13-1P
See Note 10 G20-1
G20-2
See Note 8 W16-8P W20-1 over
G20-2
G20-2
See Note 9 W20-1
See Note 9 W20-1
(optional) W13-1P
See Note 10 G20-1 the distance to the work area in feet or in miles. Install an additional W20-1 The message on the W20-1 signs may be ROAD WORK AHEAD or may specify of the road on which the construction does occur (applies to major roads only).
construction work occurs, include a supplementary plaque indicating the name If W20-1 is placed on a roadway other than that on which the actual
Cover post-mounted signs when not applicable.
Do not store traffic control devices along the roadway when not in use.
the CO.
Maintain two-way traffic during all non-work hours except as approved by
NCHRP-350 or MASH for crashworthiness.
Ensure all sign supports exposed to impact by traffic meet the requirements of indicate a maximum recommended speed through the construction area.
Install advisory speed plates under the W20 series warning signs as needed to
Vary messages as required.
signs, locate the warning signs to fit field conditions as approved by the CO.
Where advance warning signs, placed as shown, interfere with permanent this traffic control plan as necessary to accommodate actual operations.
to this project. The Contractor may add or delete information and details in Not all details shown on the temporary traffic control sheets may be applicable
Erect all project advance warning signs before starting construction work.
retroreflective sheeting types.
Refer to Section 635 of the Special Contract Requirements for allowable
State standards may be used as an alternative if approved by the CO.
verify that an encroachment permit has been obtained.
If signing on a roadway under a jurisdiction other than the client agency, whole mile.
each end of the project. Show the distance on the G20-1 sign to the nearest
Ro ad N ame
SIGN SPACING TABLE
For work zones that are 2 miles or more in length, install G20-1 signs at signs "B" feet apart according to the Sign Spacing Table.
sign when approach speeds exceed 50 MPH. When used, place the two W20-1
Expressway / Freeway
SIGNS IN FEET
Rural greater than 50 MPH
Urban and Rural 35 MPH to 50 MPH
Urban and Rural 30 MPH and less
6/2005 STANDARD APPROVED FOR USE
7/2022 REVISED: 635-1
ADVANCE SIGNING
TEMPORARY TRAFFIC CONTROL
:1 u g u s t
S td
-1
C p w
-w o rk \d m s
\S td
-1
.d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
2.
1.
Traffic flow yellow centerline yellow centerline solid yellow centerline and solid yellow centerline
Traffic flow
Traffic flow
Traffic flow
Traffic flow
Traffic flow
Traffic flow
Traffic flow
Traffic flow
Traffic flow
Traffic flow
Traffic flow
4" Broken yellow centerline
4" Broken yellow centerline
NOTE:
Two-way traffic
No passing zone one direction
DETAIL A2
Two-way traffic
No Passing zone one direction
DETAIL B2
Two-way traffic
No passing zone both directions
DETAIL A3
Two-way traffic
No Passing zone both directions
DETAIL B3
Shoulder
Shoulder
Shoulder Shoulder
Shoulder
Shoulder
On two- or three-lane roads, signs may be used instead of temporary patterns:
To substitute raised pavement markers for lines, use the following
Double solid line: two pavement markers, side by side, spaced on allowed by the gap shown based on curvature.
Two-way traffic
Passing zone both directions
DETAIL B1
Two-way traffic
Passing zone both directions
DETAIL A1
DETAIL A DETAIL B
2' 18'
20'
40'
2' 38'
2' 18'
20'
2' 38'
40'
4" Broken yellow and
4" Broken yellow
4" Solid double
4" Solid double
2' broken line: two pavement markers spaced 2' apart
Single solid line: pavement markers spaced on 10' centers.
10' centers.
pavement markings as shown on Standard 635-3.
Curves < 500' Radius Tangents or Curves ≥ 500' Radius
STANDARD APPROVED FOR USE 6/2005
7/2022
REVISED: 635-2
PAVEMENT MARKINGS
TEMPORARY
:1 u g u s t
S td
-2
C p w
-w o rk \d m s
\S td
-2
.d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
Traffic flow
Traffic flow not the advisory speed.
Approach speed based on the regulatory posted speed, *
Device spacing
Spacing Table)
(See Length and Channelizing devices
(optional)
BUFFER SPACE
Flagger location
(See Length and Spacing Table)ADVANCE WARNING AREA (See Sign Spacing Table)
ATAPER AREABUFFER SPACEVARIABLEBUFFER SPACETAPER AREAABC
WORK
ROAD
AHEAD
See Note 4
W20-1
ONE LANE
ROAD
AHEAD
xx
MPH
W20-4
(optional)
W13-1P xxx
FEET
W20-7
(optional)
W16-2P
Flagger location
WORK SPACE
TERMINATION AREA
ROAD WORK
END
See Note 4
G20-2 the buffer space.
Do not allow equipment, materials, or vehicles to be parked or stored in
Requirements, Section 156.
For project specific minimum width, refer to the Special Contract
For night time flagging operation, provide floodlighting at flagger stations.
WORK AHEAD (W20-1) and END ROAD WORK (G20-2) signs.
If closure is completely within the project limits, eliminate the ROAD name of the Contractor on the pilot car.
a conspicuous location on the rear of vehicle. Prominently display the
For pilot car operation, mount the PILOT CAR FOLLOW ME (G20-4) sign at as approved by the CO.
Final location and spacing of devices may be changed to fit field conditions those depicted for the opposite direction of travel.
Signs are shown for one direction of travel only. Place signs similar to
7.
6.
5.
4.
3.
2.
1.
(optional)(optional)
NOTE:SIGN SPACING TABLELENGTH AND SPACING TABLE
50' - 100' 50' - 100'
See Note 6
10' min.
ROAD TYPE
DISTANCE BETWEEN
A B C
Expressway / Freeway
SPEED*
APPROACH
AREA
TAPER
SPACE
BUFFER
SPACE
WORK
CHANNELIZING DEVICE
LENGTH
SPACE
BUFFER
Rural greater than 50 MPH
Urban and Rural 35 MPH to 50 MPH
Urban and Rural 30 MPH and less
SIGNS IN FEET
100MPH FEET SPACING IN FEET
7/2022 REVISED:
635-6
(WITH FLAGGERS)
SINGLE LANE CLOSURE LAYOUT
TEMPORARY TRAFFIC CONTROL
:4 u g u s t
S td p w w o r k
\d m s
\S td
.d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
See post detail (typ.)
Break-away holes.
See table for hole size parallel to sign face.
Field drill holes through post
Bottom of sign panel
Post�
Local tangent
< 10
" dia. bolts 4 1Attach sign panels with a minimum of 2 -a minimum lateral distance of 1' behind the face of lateral offset of 2' may be used. In areas with curbs, 6" x 6" or larger.
Use 7' minimum spacing between posts for sign posts and 6' minimum mounting height for secondary sign.
use 7' minimum mounting height for main sign
NOTE:
90°
93°
WOOD POST SELECTION TABLE
X X
0.75X
H
H
X
0.2X0.6X 0.2X
Y
H
D
H
D
H
D
Long side of post
D
7.
6.
5.
4.
3.
2.
1.
In areas where lateral distance is limited, a minimum
D = Post embedment depth for average soil conditions.
Select post lengths to fit field conditions.
H1 and H2 = Overall post length.
per post.
In pedestrian locations, or in areas with obstructed views, the curb may be used.
by the CO.
State standards may be used as an alternative if approved
SINGLE POST SIGN TWO POST SIGN
SIGN INSTALLATION ANGLE
POST DETAIL
E d g e o f p a v e d s h o u ld e r
E d g e o f tr a v e le d w a y
S e e N o te m in
S e e N o te m in
See Note 4
6' - 12'
On tangent alignment
200'
"X"
WIDTH AREA
OF POSTS
NUMBER POST SIZE D HOLE SIZE
(SQFT)
Other Shapes ≤ 48" Diamond ≤ 36"
Other Shapes ≤ 12' Diamond ≤ 48"
(INCH) (INCH) (INCH)
Diamond ≤ 48"
65 - 95
65 - 95
50 - 65
50 - 65
20 - 50
10 - 20
10 - 20
> 30'
> 17'
12' - 16'
> 13'
6 x 6
4 x 6
4 x 6
6 x 6
4 x 6
4 x 4
6 x 6
4 x 6
4 x 4
1.5
1.5
1.5
1.5
7/2022 REVISED: 635-14
WOOD POSTS
SIGN INSTALLATION
TEMPORARY TRAFFIC CONTROL
:1 u g u s t
S td p w
-w o rk
\d m s \S td -1
.d g n
FLH STANDARD
STANDARD
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
LL
LL
LL
LL
LL
Direction of Traffic, Increasing Stationing or Thru Traffic Side
L E G E N D:
SOLID (WHITE)
PAVEMENT MARKINGS, TYPE B,
Increasing Stationing Increasing Stationing
BROKEN, (YELLOW)
PAVEMENT MARKINGS, TYPE B,
SOLID (WHITE STOP BAR)
PAVEMENT MARKINGS, TYPE B,
LL
LL For centerline
(thru traffic side
For left turn lane
SOLID (DOUBLE NO-PASS YELLOW)
PAVEMENT MARKINGS, TYPE B,
SOLID, 6" YELLOW NO-PASS RIGHT
PAVEMENT MARKINGS, TYPE B
SOLID, 6" YELLOW NO-PASS LEFT
PAVEMENT MARKINGS, TYPE B
Lane line dimensions are shown on typical sections
STATE PROJECT
NUMBER
SHEET
DETAILS
PERMANENT TRAFFIC CONTROL 3
:5
A u g u s t c p w w o r k
\d
\O R
C R
O O
K p ln p tc g g
.d g n
/2
/2
R o n L a rs o n
C h e c k e d b y
D a n
I li y n
D e s ig n e d b y
G.2FLAP CROOK 123(1)OR
40'40'
30'10'
40'40'
30'10' s p a c e
S p a c e
10' 30'
40'40'
S p a c e
W634-2
REVISED: 10/2012
DETAIL APPROVED FOR USE 10/2007
WESTERN FEDERAL LANDS HIGHWAY DIVISION
PAVEMENT MARKINGS
LINEAR
U.S. CUSTOMARY DETAIL
DETAIL
STATE PROJECT
U.S. DEPARTMENT OF TRANSPORTATION
B o r d e r .U
S c m y fi le s p w p r o d u c ti o n d F L
H C e ll s .d g n li b
F e b r u a r y required by the maintaining agency.
pavement markings when specified on the plans or when
Typical pavement marking widths are shown. Use wider for curve widening transition locations.
throughout the curve widening area. See staking details the roadway. Maintain a constant shoulder width "s" curve widening "w" to achieve equal lane widths within
Paint centerline pavement markings on curves with curb interface when curb is present.
Place edge line pavement markings at asphalt/concrete
3.
2.
1.
TYPICAL PAVEMENT MARKING APPLICATIONS
CENTERLINE MODIFICATION FOR CURVES WITH WIDENING APPLIED ON INSIDE
CENTERLINE DETAIL
See Note 2 for treatment of curves when widening "w" is split equally on both sides of centerline
CL
CL
L a n e
L a n e s s w
Transition
Curve widening
Transition
S h o u ld e r s
T ra v e l
L
T ra v e l
L
S h o u ld e r s s L s
S o u ld e r
L a n e
T r a v e l
L a n e
T r a v e l
S o u ld e r
L w w w w when specified in plans required by the maintaining agency when specified in the plans or when
Increase spacing between parallel lines markings when specified
Approach road pavement break specified in plans extension when edge line line when specified in plans yellow centerline line extension
Turnout
Edge of pavement allow sufficient sight distance
Major approach road
Minor approach
Centerline as required
Edge line when specified in plans and location of top lift pavement joint
Offset centerline for pavement markings
Design
Edge line when specified in plans
4" solid white edge line
4" dotted white line 4" dotted white
4" solid white edge
4" solid double
Locate 12" wide stop line to 4" broken yellow centerline m a x m in
2' 10'30'10'30'10'
2' to 6'
NOTE:
| OR CROOK123(1)_pln_gen_a1-a4-Sheet A.1-000 |
| OR CROOK123(1)_pln_gen_a1-a4-Sheet A.2-000 |
| OR CROOK123(1)_pln_gen_a1-a4-Sheet A.3-000 |
| OR CROOK123(1)_pln_gen_a1-a4-Sheet A.4-000 |
| OR CROOK123(1)_pln_lg_d1-d2-D.1-000 |
| OR CROOK123(1)_pln_lg_d1-d2-D.2-000 |
| OR CROOK123(1)_pln_misc_e1-e6-Default-000 |
| OR CROOK123(1)_pln_misc_e1-e6-E.1-000 |
| OR CROOK123(1)_pln_misc_e1-e6-E.2-000 |
| OR CROOK123(1)_pln_misc_e1-e6-E.3-000 |
| OR CROOK123(1)_pln_misc_e1-e6-E.4-000 |
| OR CROOK123(1)_pln_ttc_f1-f6-F.1-000 |
| OR CROOK123(1)_pln_qtab_g1 |
| OR CROOK123(1)_pln_ptc_g2-g3-G.2-000 |
| OR CROOK123(1)_pln_ptc_g2-g3-G.3-000 |
| Std617-32.pdf |
| FLH Standard Drawings |
| 617-32: MGS W-Beam Guardrail, Steel Posts |
| Metric |
| US Customary |
| Designer Notes |
| Std617-37.pdf |
| FLH Standard Drawings |
| 617-37: MGS W-Beam Guardrail Long-Span System |
| Metric |
| US Customary |
| Designer Notes |
| Std617-11.pdf |
| FLH Standard Drawings |
| 617-11: G4 W-Beam Guardrail, Steel Posts |
| Metric |
| US Customary |
| Std617-13 (1).pdf |
| FLH Standard Drawings |
| 617-13: MGS and G4 W-Beam Guardrail, Installation in Rock |
| Designer Notes |
| Metric |
| US Customary |
| Std617-20 (1).pdf |
| FLH Standard Drawings |
| 617-20: MGS and G4 W-Beam Guardrail, Type Tangent Terminal and Grading |
| Designer Notes |
| Metric |
| US Customary |
| W157-20.pdf |
| WFLHD Detail Drawings |
| W157-20: Sediment Wattle |
| Metric |
| US Customary |
| fiber roll W157-21.pdf |
| WFLHD Detail Drawings |
| W157-21: Fiber Roll |
| Metric |
| US Customary |
| A.2 AW101-1.pdf |
| WFL Detail Drawings |
| W101-1: Plan Symbols and Abbreviations |
| Metric |
| US Customary |
| Std635-1.pdf |
| FLH Standard Drawings |
| 635-1: Advance Signing |
| Metric |
| US Customary |
| Std635-2.pdf |
| FLH Standard Drawings |
| 635-2: Temporary Pavement Markings |
| Metric |
| US Customary |
| Std635-6.pdf |
| FLH Standard Drawings |
| 635-6: Single Lane Closure Layout (with Flaggers) |
| Metric |
| US Customary |
| Std635-14.pdf |
| FLH Standard Drawings |
| 635-14: Sign Installation, Wood Posts |
| Metric |
| US Customary |
| W634-2.pdf |
| WFLHD Detail Drawings |
| W634-2: Linear Pavement Markings |
| Metric |
| US Customary |
| 617-32: E.5 |
| State: OR |
| Project: FLAP CROOK 123(1) |
| 617-37: E.6 |
| NPS: |
| 617-13: E.3 |
| 617-20: E.4 |
| W157-21: D.2 |
| W101-1: A.2 |
| Proj-Num: OR FLAP CROOK 123(1) |
| 635-1: F.2 |
| 635-2: F.3 |
| 635-6: F.4 |
| 635-14: F.5 |
| W634-2: G.3 |
File details come from the government source that posted it. Updated .