Preliminary Bid Results~69.xlsx
XLSX spreadsheet 18 KB Posted
- Solicitation number
- S-73000-00015486
- Issued by
- Clackamas County, Oregon
About this file
This is a Preliminary Bid Results tabulation for the Oregon Department of Transportation's NB Boone Bridge (I-5 Over Willamette River at MP 283.11) Joint Rehabilitation Project, ITB No. S-73000-00015486. The project encompasses comprehensive bridge joint rehabilitation work including removal of existing structures, construction of temporary and permanent bridge joints, installation of a premixed polymer concrete overlay, pavement marking placement, and associated incidental work. Seven contractors submitted bids for the project, with the bid closing occurring on January 14, 2026 at 2:00 p.m. The work includes 19 distinct bid items ranging from mobilization and traffic control to specialized tasks such as modular bridge joint system installation, steel repairs, and surface treatments. Contractors were required to submit bids by January 6, 2026, with substantial completion mandated by September 24, 2026 and final completion by October 8, 2026. The project is located in Clackamas County and falls under the jurisdiction of the Oregon Department of Transportation.
The seven bidders—MJ Hughes Construction, HP Civil Inc, Wildish Standard Paving Co, Lee Contractors LLC, Legacy Contracting Inc, Combined Construction Inc, and Granite Construction Company—submitted total bids ranging from $1,926,390.00 to $2,695,597.00, with most bids falling within the estimated project cost range of $2,000,000 to $2,500,000. Bidders were required to comply with prevailing wage rates, submit bid security equal to 10% of their total bid amount, and furnish performance and payment bonds at 100% of contract price. The contract is funded from state sources and includes liquidated damages provisions of $1,100 per day for missed substantial completion dates and $500 per 15 minutes per lane for unauthorized lane closures. All contractors must be licensed with the Oregon Construction Contractors Board and comply with State Buy America requirements mandating domestically produced steel, iron, coatings, and manufactured products. This bid tabulation serves as a preliminary record and is not an indicator of award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 1/14/26 | ||||||||
| ITB No. | S-73000-00015486 | BIDDER | |||||||
| NAME: | MJ Hughes Construction | HP Civil Inc | Wildish Standard Paving Co | Lee Contractors, LLC | Legacy Contracting Inc | Combined Construction Inc | Granite Construction Company | ||
| Bid Closing: | January 14, 2026 at 2:00 pm | CITY/STATE: | |||||||
| Description: | NB Boone Bridge (I-5 Over Willamette River at MP 283.11) Joint Rehabilitation Project | CCB#: | |||||||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1 | LS | $ 190,000.00 | $ 190,000.00 | $ 194,075.58 | $ 194,075.58 | $ 197,000.00 | $ 197,000.00 | $ 195,000.00 | $ 195,000.00 | $ 219,147.00 | $ 219,147.00 | $ 260,000.00 | $ 260,000.00 | $ 240,000.00 | $ 240,000.00 |
| 2 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | 1 | LS | $ 325,000.00 | $ 325,000.00 | $ 300,000.00 | $ 300,000.00 | $ 400,000.00 | $ 400,000.00 | $ 130,000.00 | $ 130,000.00 | $ 288,564.00 | $ 288,564.00 | $ 321,250.00 | $ 321,250.00 | $ 251,927.00 | $ 251,927.00 |
| 3 | MOBILE BARRIER | 30 | DAY | $ 2,650.00 | $ 79,500.00 | $ 1,600.00 | $ 48,000.00 | $ 300.00 | $ 9,000.00 | $ 1,000.00 | $ 30,000.00 | $ 1.00 | $ 30.00 | $ 4,430.00 | $ 132,900.00 | $ 2,990.00 | $ 89,700.00 |
| 4 | TEMPORARY WORK ACCESS AND CONTAINMENT | 1 | LS | $ 140,000.00 | $ 140,000.00 | $ 61,500.00 | $ 61,500.00 | $ 50,000.00 | $ 50,000.00 | $ 130,000.00 | $ 130,000.00 | $ 194,053.00 | $ 194,053.00 | $ 94,160.00 | $ 94,160.00 | $ 130,000.00 | $ 130,000.00 |
| 5 | POLLUTION CONTROL PLAN | 1 | LS | $ 600.00 | $ 600.00 | $ 500.00 | $ 500.00 | $ 3,000.00 | $ 3,000.00 | $ 1,000.00 | $ 1,000.00 | $ 1,419.00 | $ 1,419.00 | $ 10,000.00 | $ 10,000.00 | $ 1,500.00 | $ 1,500.00 |
| 6 | WORK CONTAINMENT PLAN | 1 | LS | $ 600.00 | $ 600.00 | $ 5,000.00 | $ 5,000.00 | $ 5,000.00 | $ 5,000.00 | $ 1,000.00 | $ 1,000.00 | $ 17,127.00 | $ 17,127.00 | $ 50,000.00 | $ 50,000.00 | $ 3,000.00 | $ 3,000.00 |
| 7 | BRIDGE REMOVAL WORK | 1 | LS | $ 65,000.00 | $ 65,000.00 | $ 200,000.00 | $ 200,000.00 | $ 50,000.00 | $ 50,000.00 | $ 100,000.00 | $ 100,000.00 | $ 103,705.00 | $ 103,705.00 | $ 153,000.00 | $ 153,000.00 | $ 140,000.00 | $ 140,000.00 |
| 8 | CLASS 2 PREPARATION | 25 | SQYD | $ 200.00 | $ 5,000.00 | $ 0.01 | $ 0.25 | $ 0.01 | $ 0.25 | $ 650.00 | $ 16,250.00 | $ 1,182.00 | $ 29,550.00 | $ 500.00 | $ 12,500.00 | $ 1,300.00 | $ 32,500.00 |
| 9 | PPC REMOVAL | 468 | SQYD | $ 75.00 | $ 35,100.00 | $ 55.00 | $ 25,740.00 | $ 25.00 | $ 11,700.00 | $ 150.00 | $ 70,200.00 | $ 78.00 | $ 36,504.00 | $ 111.00 | $ 51,948.00 | $ 70.00 | $ 32,760.00 |
| 10 | FURNISH PREMIXED POLYMER CONCRETE | 12 | CUYD | $ 4,900.00 | $ 58,800.00 | $ 4,500.00 | $ 54,000.00 | $ 2,500.00 | $ 30,000.00 | $ 15,000.00 | $ 180,000.00 | $ 4,500.00 | $ 54,000.00 | $ 4,203.00 | $ 50,436.00 | $ 4,500.00 | $ 54,000.00 |
| 11 | CONSTRUCT PPC OVERLAY | 468 | SQYD | $ 155.00 | $ 72,540.00 | $ 130.00 | $ 60,840.00 | $ 50.00 | $ 23,400.00 | $ 200.00 | $ 93,600.00 | $ 140.00 | $ 65,520.00 | $ 108.00 | $ 50,544.00 | $ 150.00 | $ 70,200.00 |
| 12 | PRECOMPRESSED FOAM SILICONE JOINT SEAL | 1 | LS | $ 20,000.00 | $ 20,000.00 | $ 7,500.00 | $ 7,500.00 | $ 30,000.00 | $ 30,000.00 | $ 60,000.00 | $ 60,000.00 | $ 31,681.00 | $ 31,681.00 | $ 30,000.00 | $ 30,000.00 | $ 76,400.00 | $ 76,400.00 |
| 13 | MODULAR BRIDGE JOINT SYSTEMS | 1 | LS | $ 600,000.00 | $ 600,000.00 | $ 800,000.00 | $ 800,000.00 | $ 800,000.00 | $ 800,000.00 | $ 943,000.00 | $ 943,000.00 | $ 556,940.00 | $ 556,940.00 | $ 827,130.00 | $ 827,130.00 | $ 1,011,640.00 | $ 1,011,640.00 |
| 14 | TEMPORARY JOINT SYSTEM | 1 | LS | $ 125,000.00 | $ 125,000.00 | $ 150,000.00 | $ 150,000.00 | $ 300,000.00 | $ 300,000.00 | $ 120,000.00 | $ 120,000.00 | $ 426,423.00 | $ 426,423.00 | $ 390,185.00 | $ 390,185.00 | $ 480,000.00 | $ 480,000.00 |
| 15 | PRESSURE WASHING | 1 | LS | $ 12,000.00 | $ 12,000.00 | $ 15,000.00 | $ 15,000.00 | $ 50,000.00 | $ 50,000.00 | $ 30,000.00 | $ 30,000.00 | $ 8,670.00 | $ 8,670.00 | $ 41,760.00 | $ 41,760.00 | $ 35,000.00 | $ 35,000.00 |
| 16 | COPE EXISTING STEEL | 16 | EACH | $ 2,600.00 | $ 41,600.00 | $ 800.00 | $ 12,800.00 | $ 300.00 | $ 4,800.00 | $ 1,000.00 | $ 16,000.00 | $ 1,782.00 | $ 28,512.00 | $ 2,150.00 | $ 34,400.00 | $ 690.00 | $ 11,040.00 |
| 17 | SUPPORT BAR REPAIR | 36 | EACH | $ 4,200.00 | $ 151,200.00 | $ 400.00 | $ 14,400.00 | $ 100.00 | $ 3,600.00 | $ 100.00 | $ 3,600.00 | $ 3,486.00 | $ 125,496.00 | $ 1,360.00 | $ 48,960.00 | $ 880.00 | $ 31,680.00 |
| 18 | MONO-DIRECTIONAL WHITE TYPE IAR MARKERS | 10 | EACH | $ 25.00 | $ 250.00 | $ 25.00 | $ 250.00 | $ 25.00 | $ 250.00 | $ 100.00 | $ 1,000.00 | $ 25.00 | $ 250.00 | $ 50.00 | $ 500.00 | $ 26.00 | $ 260.00 |
| 19 | METHYL METHACRYLATE, EXTRUDED, SURFACE, PROFILED | 210 | FOOT | $ 20.00 | $ 4,200.00 | $ 15.00 | $ 3,150.00 | $ 20.00 | $ 4,200.00 | $ 10.00 | $ 2,100.00 | $ 18.50 | $ 3,885.00 | $ 37.00 | $ 7,770.00 | $ 19.00 | $ 3,990.00 |
| TOTAL | $ 1,926,390.00 | $ 1,952,755.83 | $ 1,971,950.25 | $ 2,122,750.00 | $ 2,191,476.00 | $ 2,567,443.00 | $ 2,695,597.00 |