Preliminary Bid Results~18.xlsx
XLSX spreadsheet 22 KB Posted
- Solicitation number
- S-C03342-00011226
- Issued by
- Washington County, Oregon
About this file
This is a preliminary bid tabulation for the Hall Boulevard Pedestrian Improvements Project issued by an unnamed Oregon municipality on September 27, 2024. The project encompasses comprehensive pedestrian infrastructure enhancements including pavement removal and replacement, concrete curbs and sidewalks, bicycle lane markings, signage installation, traffic control measures, and erosion control. The bid included 42 line items with quantities ranging from individual units to thousands of linear feet and square feet, encompassing mobilization, temporary traffic control, surface removal, excavation, asphalt and concrete work, safety features such as curb ramps and truncated domes, thermoplastic markings, beacon installation, and landscape restoration. Seven contractors submitted bids by the September 27, 2024 closing date: Colton Homes, Western Construction, Brown Contracting, D&D Concrete and Utilities, Lee Contractors, MJ Hughes Construction, Wildish, and Standard Paving.
The total bid prices ranged significantly across the seven bidders, from a low of $439,197.30 submitted by Colton Homes to a high of $709,683.00 submitted by Standard Paving, indicating substantial variation in contractor pricing strategies and cost estimates. The bid tabulation explicitly notes that it does not constitute an award indication and serves only as a compilation of submitted bids for consideration. Individual line item pricing demonstrates considerable variance, particularly in specialized work such as flashing beacon installation (ranging from $58,000 to $95,000), unintegrated speed feedback assemblies (ranging from $60,000 to $100,000), and green bicycle lane thermoplastic film application. The document provides no information regarding set-asides, incumbent contractors, contract award dates, or funding sources.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| tile and grout Legal Advertisement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 9/27/24 | ||||||||
| ITB No. | S-73000-00011227 | BIDDER | |||||||
| NAME: | Colton Homes | Western Construction | Brown Contracting | D&D Concrete and Utilities | Lee Contractors | MJ Hughes Construction | Wildish Standard Paving | ||
| Bid Closing: | September 27, 2024 | CITY/STATE: | |||||||
| Description: | Hall Blvd Pedestrian Improvements Project | CCB#: | |||||||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1.0 | LS | $ 45,000.00 | $ 45,000.00 | $60,000.00 | $ 60,000.00 | $ 49,000.00 | $ 49,000.00 | $ 55,000.00 | $ 55,000.00 | $68,000.00 | $ 68,000.00 | $70,000.00 | $ 70,000.00 | $70,000.00 | $ 70,000.00 |
| 2 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | 1.0 | LS | $ 20,000.00 | $ 20,000.00 | $21,000.00 | $ 21,000.00 | $ 22,000.00 | $ 22,000.00 | $ 50,000.00 | $ 50,000.00 | $72,000.00 | $ 72,000.00 | $70,000.00 | $ 70,000.00 | $150,000.00 | $ 150,000.00 |
| 3 | STRIPE REMOVAL | 670.0 | FOOT | $ 5.00 | $ 3,350.00 | $4.00 | $ 2,680.00 | $ 3.75 | $ 2,512.50 | $ 4.00 | $ 2,680.00 | $10.00 | $ 6,700.00 | $4.00 | $ 2,680.00 | $4.00 | $ 2,680.00 |
| 4 | LEGEND REMOVAL | 23.0 | SQFT | $ 35.00 | $ 805.00 | $43.00 | $ 989.00 | $ 38.00 | $ 874.00 | $ 40.00 | $ 920.00 | $200.00 | $ 4,600.00 | $41.00 | $ 943.00 | $40.00 | $ 920.00 |
| 5 | BAR REMOVAL | 23.0 | SQFT | $ 35.00 | $ 805.00 | $25.00 | $ 575.00 | $ 38.00 | $ 874.00 | $ 40.00 | $ 920.00 | $200.00 | $ 4,600.00 | $41.00 | $ 943.00 | $40.00 | $ 920.00 |
| 6 | EROSION CONTROL | 1.0 | LS | $ 1,000.00 | $ 1,000.00 | $9,500.00 | $ 9,500.00 | $ 1,000.00 | $ 1,000.00 | $ 3,000.00 | $ 3,000.00 | $15,000.00 | $ 15,000.00 | $1,750.00 | $ 1,750.00 | $3,000.00 | $ 3,000.00 |
| 7 | INLET PROTECTION, TYPE 3 | 4.0 | EACH | $ 200.00 | $ 800.00 | $95.00 | $ 380.00 | $ 125.00 | $ 500.00 | $ 100.00 | $ 400.00 | $500.00 | $ 2,000.00 | $120.00 | $ 480.00 | $200.00 | $ 800.00 |
| 8 | STRAW BALE | 1.0 | EACH | $ 70.00 | $ 70.00 | $32.50 | $ 32.50 | $ 225.00 | $ 225.00 | $ 100.00 | $ 100.00 | $500.00 | $ 500.00 | $100.00 | $ 100.00 | $150.00 | $ 150.00 |
| 9 | POLLUTION CONTROL PLAN | 1.0 | LS | $ 1,000.00 | $ 1,000.00 | $1,150.00 | $ 1,150.00 | $ 935.00 | $ 935.00 | $ 500.00 | $ 500.00 | $500.00 | $ 500.00 | $1,250.00 | $ 1,250.00 | $1,000.00 | $ 1,000.00 |
| 10 | CONTAMINATED SOIL DISPOSAL | 33.0 | TON | $ 250.00 | $ 8,250.00 | $375.50 | $ 12,391.50 | $ 256.00 | $ 8,448.00 | $ 200.00 | $ 6,600.00 | $300.00 | $ 9,900.00 | $150.00 | $ 4,950.00 | $100.00 | $ 3,300.00 |
| 11 | LEAD COMPLIANCE PLAN | 1.0 | LS | $ 1,000.00 | $ 1,000.00 | $9,500.00 | $ 9,500.00 | $ 932.00 | $ 932.00 | $ 4,000.00 | $ 4,000.00 | $500.00 | $ 500.00 | $600.00 | $ 600.00 | $1,000.00 | $ 1,000.00 |
| 12 | CONSTRUCTION SURVEY WORK | 1.0 | LS | $ 3,500.00 | $ 3,500.00 | $12,000.00 | $ 12,000.00 | $ 5,000.00 | $ 5,000.00 | $ 10,000.00 | $ 10,000.00 | $24,000.00 | $ 24,000.00 | $10,000.00 | $ 10,000.00 | $5,000.00 | $ 5,000.00 |
| 13 | REMOVAL OF SURFACINGS | 25.6 | SQYD | $ 70.00 | $ 1,792.00 | $55.00 | $ 1,408.00 | $ 45.00 | $ 1,152.00 | $ 200.00 | $ 5,120.00 | $450.00 | $ 11,520.00 | $250.00 | $ 6,400.00 | $200.00 | $ 5,120.00 |
| 14 | GENERAL EXCAVATION | 63.8 | CUYD | $ 90.00 | $ 5,742.00 | $48.00 | $ 3,062.40 | $ 151.00 | $ 9,633.80 | $ 100.00 | $ 6,380.00 | $300.00 | $ 19,140.00 | $250.00 | $ 15,950.00 | $200.00 | $ 12,760.00 |
| 15 | COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEP | 82.5 | SQYD | $ 60.00 | $ 4,950.00 | $105.00 | $ 8,662.50 | $ 210.00 | $ 17,325.00 | $ 60.00 | $ 4,950.00 | $130.00 | $ 10,725.00 | $225.00 | $ 18,562.50 | $130.00 | $ 10,725.00 |
| 16 | AGGREGATE BASE | 74.6 | TON | $ 60.00 | $ 4,476.00 | $60.00 | $ 4,476.00 | $ 168.00 | $ 12,532.80 | $ 100.00 | $ 7,460.00 | $300.00 | $ 22,380.00 | $125.00 | $ 9,325.00 | $100.00 | $ 7,460.00 |
| 17 | LEVEL 3, 1/2 INCH ACP MIXTURE | 25.3 | TON | $ 310.00 | $ 7,843.00 | $625.00 | $ 15,812.50 | $ 375.00 | $ 9,487.50 | $ 400.00 | $ 10,120.00 | $400.00 | $ 10,120.00 | $500.00 | $ 12,650.00 | $650.00 | $ 16,445.00 |
| 18 | 20 INCH ASPHALT CONCRETE PAVEMENT REPAIR | 80.2 | SQYD | $ 200.00 | $ 16,040.00 | $190.00 | $ 15,238.00 | $ 110.00 | $ 8,822.00 | $ 40.00 | $ 3,208.00 | $400.00 | $ 32,080.00 | $400.00 | $ 32,080.00 | $150.00 | $ 12,030.00 |
| 19 | CONCRETE CURBS, CURB AND GUTTER | 160.0 | FOOT | $ 110.00 | $ 17,600.00 | $72.00 | $ 11,520.00 | $ 92.00 | $ 14,720.00 | $ 80.00 | $ 12,800.00 | $70.00 | $ 11,200.00 | $100.00 | $ 16,000.00 | $100.00 | $ 16,000.00 |
| 20 | CONCRETE WALKS | 1,200.0 | SQFT | $ 18.00 | $ 21,600.00 | $14.00 | $ 16,800.00 | $ 13.00 | $ 15,600.00 | $ 24.00 | $ 28,800.00 | $25.00 | $ 30,000.00 | $20.00 | $ 24,000.00 | $30.00 | $ 36,000.00 |
| 21 | EXTRA FOR NEW CURB RAMPS | 4.0 | EACH | $ 1,000.00 | $ 4,000.00 | $825.00 | $ 3,300.00 | $ 770.00 | $ 3,080.00 | $ 2,000.00 | $ 8,000.00 | $5,000.00 | $ 20,000.00 | $1,500.00 | $ 6,000.00 | $6,000.00 | $ 24,000.00 |
| 22 | TRUNCATED DOMES ON NEW SURFACES | 53.4 | SQFT | $ 30.00 | $ 1,602.00 | $53.00 | $ 2,830.20 | $ 70.00 | $ 3,738.00 | $ 60.00 | $ 3,204.00 | $50.00 | $ 2,670.00 | $37.00 | $ 1,975.80 | $50.00 | $ 2,670.00 |
| 23 | THERMOPLASTIC, EXTRUDED, SURFACE, PROFILED | 2,300.0 | FOOT | $ 4.50 | $ 10,350.00 | $3.50 | $ 8,050.00 | $ 2.85 | $ 6,555.00 | $ 3.00 | $ 6,900.00 | $5.00 | $ 11,500.00 | $3.00 | $ 6,900.00 | $3.00 | $ 6,900.00 |
| 24 | PAVEMENT LEGEND, TYPE B-HS: BICYCLE LANE STENCIL | 9.0 | EACH | $ 450.00 | $ 4,050.00 | $475.00 | $ 4,275.00 | $ 515.00 | $ 4,635.00 | $ 450.00 | $ 4,050.00 | $600.00 | $ 5,400.00 | $550.00 | $ 4,950.00 | $500.00 | $ 4,500.00 |
| 25 | PAVEMENT BAR, TYPE B-HS | 360.0 | SQFT | $ 22.00 | $ 7,920.00 | $20.00 | $ 7,200.00 | $ 21.00 | $ 7,560.00 | $ 18.00 | $ 6,480.00 | $20.00 | $ 7,200.00 | $22.00 | $ 7,920.00 | $20.00 | $ 7,200.00 |
| 26 | GREEN BICYCLE LANE, PREFORMED THERMOPLASTIC FILM | 2,700.0 | SQFT | $ 5.00 | $ 13,500.00 | $16.00 | $ 43,200.00 | $ 15.00 | $ 40,500.00 | $ 15.00 | $ 40,500.00 | $20.00 | $ 54,000.00 | $18.00 | $ 48,600.00 | $15.00 | $ 40,500.00 |
| 27 | CROSSWALK CLOSURE SUPPORTS | 2.0 | EACH | $ 900.00 | $ 1,800.00 | $850.00 | $ 1,700.00 | $ 1,450.00 | $ 2,900.00 | $ 1,800.00 | $ 3,600.00 | $500.00 | $ 1,000.00 | $1,500.00 | $ 3,000.00 | $2,000.00 | $ 4,000.00 |
| 28 | REMOVE EXISTING SIGNS | 1.0 | LS | $ 1,000.00 | $ 1,000.00 | $1,750.00 | $ 1,750.00 | $ 65.00 | $ 65.00 | $ 6,000.00 | $ 6,000.00 | $10,000.00 | $ 10,000.00 | $7,000.00 | $ 7,000.00 | $8,000.00 | $ 8,000.00 |
| 29 | REMOVE AND REINSTALL EXISTING SIGNS | 1.0 | LS | $ 3,000.00 | $ 3,000.00 | $3,250.00 | $ 3,250.00 | $ 350.00 | $ 350.00 | $ 600.00 | $ 600.00 | $10,000.00 | $ 10,000.00 | $625.00 | $ 625.00 | $1,000.00 | $ 1,000.00 |
| 30 | SIGN SUPPORT FOOTINGS | 2.5 | CUYD | $ 3,500.00 | $ 8,820.00 | $175.00 | $ 441.00 | $ 4,000.00 | $ 10,080.00 | $ 2,000.00 | $ 5,040.00 | $1,000.00 | $ 2,520.00 | $5,000.00 | $ 12,600.00 | $4,000.00 | $ 10,080.00 |
| 31 | SIGNAL POLE MOUNTS | 670.0 | LB | $ 12.00 | $ 8,040.00 | $5.75 | $ 3,852.50 | $ 20.00 | $ 13,400.00 | $ 8.00 | $ 5,360.00 | $5.00 | $ 3,350.00 | $21.00 | $ 14,070.00 | $7.00 | $ 4,690.00 |
| 32 | PERFORATED STEEL SQUARE TUBE SLIP BASE SIGN SUPPORTS | 1,900.0 | LB | $ 9.00 | $ 17,100.00 | $6.75 | $ 12,825.00 | $ 10.00 | $ 19,000.00 | $ 8.00 | $ 15,200.00 | $5.00 | $ 9,500.00 | $8.50 | $ 16,150.00 | $8.00 | $ 15,200.00 |
| 33 | PERFORATED STEEL SQUARE TUBE ANCHOR SIGN SUPPORTS | 550.0 | LB | $ 9.00 | $ 4,950.00 | $5.00 | $ 2,750.00 | $ 10.00 | $ 5,500.00 | $ 8.00 | $ 4,400.00 | $5.00 | $ 2,750.00 | $10.00 | $ 5,500.00 | $9.00 | $ 4,950.00 |
| 34 | SIGNS, STANDARD SHEETING, SHEET ALUMINUM | 400.0 | SQFT | $ 65.00 | $ 26,000.00 | $20.00 | $ 8,000.00 | $ 35.00 | $ 14,000.00 | $ 50.00 | $ 20,000.00 | $29.00 | $ 11,600.00 | $65.00 | $ 26,000.00 | $60.00 | $ 24,000.00 |
| 35 | SIGNS, STANDARD SHEETING, PLYWOOD | 130.0 | SQFT | $ 70.00 | $ 9,100.00 | $25.00 | $ 3,250.00 | $ 35.00 | $ 4,550.00 | $ 30.00 | $ 3,900.00 | $29.00 | $ 3,770.00 | $38.00 | $ 4,940.00 | $35.00 | $ 4,550.00 |
| 36 | SIGNS, WIDE ANGLE SHEETING, EXTRUDED ALUMINUM | 66.9 | SQFT | $ 67.00 | $ 4,482.30 | $50.00 | $ 3,345.00 | $ 45.00 | $ 3,010.50 | $ 70.00 | $ 4,683.00 | $29.00 | $ 1,940.10 | $80.00 | $ 5,352.00 | $70.00 | $ 4,683.00 |
| 37 | SIGNS, WIDE ANGLE SHEETING, SHEET ALUMINUM | 360.0 | SQFT | $ 76.00 | $ 27,360.00 | $35.00 | $ 12,600.00 | $ 105.00 | $ 37,800.00 | $ 70.00 | $ 25,200.00 | $20.00 | $ 7,200.00 | $85.00 | $ 30,600.00 | $75.00 | $ 27,000.00 |
| 38 | FLASHING BEACON INSTALLATION, HALL BLVD AT ASHFORD ST | 1.0 | EACH | $ 58,000.00 | $ 58,000.00 | $63,426.18 | $ 63,426.18 | $ 72,000.00 | $ 72,000.00 | $ 90,000.00 | $ 90,000.00 | $93,000.00 | $ 93,000.00 | $95,000.00 | $ 95,000.00 | $90,000.00 | $ 90,000.00 |
| 39 | UNINTEGRATED SPEED FEEDBACK ASSEMBLY | 4.0 | EACH | $ 15,000.00 | $ 60,000.00 | $15,048.54 | $ 60,194.16 | $ 16,500.00 | $ 66,000.00 | $ 15,000.00 | $ 60,000.00 | $20,000.00 | $ 80,000.00 | $25,000.00 | $ 100,000.00 | $17,000.00 | $ 68,000.00 |
| 40 | LAWN SEEDING | 30.0 | SQYD | $ 50.00 | $ 1,500.00 | $45.00 | $ 1,350.00 | $ 35.00 | $ 1,050.00 | $ 30.00 | $ 900.00 | $1.00 | $ 30.00 | $29.00 | $ 870.00 | $40.00 | $ 1,200.00 |
| 41 | TOPSOIL | 3.0 | CUYD | $ 200.00 | $ 600.00 | $95.00 | $ 285.00 | $ 225.00 | $ 675.00 | $ 150.00 | $ 450.00 | $300.00 | $ 900.00 | $200.00 | $ 600.00 | $250.00 | $ 750.00 |
| 42 | COMPOST MULCH | 2.0 | CUYD | $ 200.00 | $ 400.00 | $95.00 | $ 190.00 | $ 225.00 | $ 450.00 | $ 150.00 | $ 300.00 | $300.00 | $ 600.00 | $200.00 | $ 400.00 | $250.00 | $ 500.00 |
| TOTAL | $ 439,197.30 | $ 455,241.44 | $ 498,472.10 | $ 527,725.00 | $ 694,395.10 | $ 697,716.30 | $ 709,683.00 |
File details come from the government source that posted it. Updated .